DRAFT Project Suite Solicitation Summary

This is a Draft Project Suite Solicitation and Initial Announcement for the Initial Minot Sentinel Beddown (IMSB) project at Minot Air Force Base, North Dakota, issued by the U.S. Army Corps of Engineers (USACE), Omaha District on behalf of the Air Force Civil Engineering Center (AFCEC). The solicitation seeks a single Design-Bid-Build (D-B-B) contractor under an Other Transaction Agreement (OTA) pursuant to 10 U.S.C. § 2808a to deliver three facilities: the Consolidated Vehicle Maintenance Complex (CVMC), Security Forces Operations Complex (SFOC), and Athletic Complex (AC). The total construction cost limitation is $203,000,000, with performance periods of 1,440 days for CVMC, 920 days for SFOC, and 550 days for AC from notice to proceed. The delivery model emphasizes collaborative project development, innovation, speed, qualifications-based selection, and risk management outside traditional FAR constraints. The Government will not require preliminary or construction pricing during the initial selection phase.

The competitive selection process consists of two steps: Step 1 White Paper submission (due November 5, 2026) evaluating contractor qualifications, bonding capacity, experience, staffing, and collaborative approach; and Step 2 Pitch Meeting (on or around February 1, 2027) by invitation only for approximately three qualified contractors to present their understanding of the project, subcontractor engagement strategy, technical approach, and team capabilities. Phase 1 (Pre-Construction Services) involves collaborative design adjustments, open-book cost estimating, and integrated schedule development, followed by negotiation of a Final Construction Price functioning as Firm-Fixed-Price. Phase 2 (Construction) may be awarded by modification upon successful Phase 1 negotiation and is contingent upon Congressional authorization, appropriations, and Government determination that progression is warranted. The OTA includes an off-ramp provision allowing the Government to discontinue the relationship and pursue alternative acquisition methods if fair and reasonable pricing cannot be achieved. Contractors must demonstrate bonding capability of at least $100,000,000, maintain SAM registration with a valid UEI, and handle Federal Contract Information (FCI) under CMMC principles, though CMMC certification is not applicable to all IMSB projects. Selection notification is anticipated for March 17, 2027, with all projects intended for award in FY27.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

*Note: This is a DRAFT version of the IMSB Solicitation, meant only to solicit feedback from interested parties in an effort to improve the Government’s OTA process. Feedback from industry may be incorporated into the final RFQ and Solicitation documents. The official IMSB Solicitation and RFQ will be posted once industry comments have been evaluated and incorporated as necessary.

Instructions for providing feedback via Projnet are provided as a separate document within this posting. Feedback is due at 1200 CST on 23 September 2026.

DRAFT - PROJECT SUITE SOLICITATION

Initial Minot Sentinel Beddown (IMSB), Minot Air Force Base, North Dakota (ND)

[Solicitation Number TO BE DETERMINED]

PROJECT SUITE SOLICITATION OVERVIEW INFORMATION

Federal Agency Name: U.S. Army Corps of Engineers (USACE), Omaha District (NWO)

Project Suite Title: Initial Minot Sentinel Beddown

Project Titles:

Consolidated Vehicle Maintenance Complex (CVMC) Security Forces Operations Complex (SFOC) Athletic Complex (AC)

Announcement Type: Initial Announcement

Solicitation Number: [TO BE DETERMINED]

Project Need:

The Air Force requires the construction of facilities to facilitate early Sentinel-related activities and prepare for future Sentinel construction at Minot AFB, ND. This collection of facilities is essential to bed down the new Sentinel mission without interrupting the operation and maintenance of the current missions at Minot AFB. The Sentinel program encompasses the effort by the U.S. Air Force to modernize the nation's land-based nuclear deterrent by replacing the aging Minuteman III intercontinental ballistic missile (ICBM) system.

Project Suite Location: Minot AFB, North Dakota (ND)

Authority for Award: Title 10 U.S.C. § 2808a

Type of Instrument:

Other Transaction Agreement (OTA) for Design-Bid-Build. Phase 1 will be for Pre-Construction Services. Phase 2 may be added by modification(s) for final construction upon successful negotiation(s) of a Final Construction Price within a Fixed Price model subject to authorization, approvals, and availability of funds.

Delivery Model: Design-Bid-Build (D-B-B) under an Other Transaction Agreement

(OTA)

NAICS Code: 236220 PSC Code: Y1JZ Total Construction Cost Limitation:

$203,000,000.00

Anticipated Award:

Single OT award intended. The Government reserves the right to select, not select, or continue discussions with any Design-Bid- Build Team at any phase.

This announcement, including all stated attachments and any websites incorporated by reference, constitutes the entire solicitation and forms the basis for all content resulting in the OT.

Solicitation POCs:

Ariel Vogan (ariel.e.vogan@usace.army.mil), Jennifer Gilbreath (jennifer.c.gilbreath@usace.army.mil)

ANTICIPATED SCHEDULE

Note: This schedule is subject to change at the Government's discretion.

Milestone Dates/Time - All Times are Central Time Zone (CT)

Notice to Industry Posting: 14 August 2026

Industry Day Questions Due: Submitted through ProjNet, due by 25 August 2026, 02:00 PM Central

Industry Day (Virtual): 27 August 2026, 10:00AM Central Notice to Industry Responses: 31 August 2026 Draft RFQ Solicitation and Attachments: 9 September 2026 Draft RFQ Responses 23 September 2026 RFQ Issuance: 14 October 2026 White Papers Due: 05 November 2026, 2:00PM Central Down Select Notifications and Request for Pitch Meeting(s): 4 January 2027

Pitch Presentation Preparation Duration: Approximately 4 weeks to the Pitch Meeting

Pitch Meeting Q&A: On or around 25 January 2027 Pitch Meeting: On or around 01 February 2027 Selection Notification: 17 March 2027

The Government anticipates completing the competitive selection process and making an award within approximately eight (8) months after the release of the Request for White Papers. Companies that are interested in proposing but unable to meet the approximate timeline may be removed from consideration for award.

Attachments:

• Attachment 1 – Request for White Papers (Step 1)

• Attachment 2 – IMSB Requirement Overview

• *Attachment 3 – Invitation for Pitch Meeting (Step 2-Final Competitive Evaluation, by invitation only

• *Attachment 4 – Model OT Agreement Template

• **Attachment 5 – Post-Selection Phase 1 Instructions (Provided only to the selected Contractor after completion of the Qualifications-Based Selection process)

*NOTE 1: Attachments 3 and 4 will be provided at a future date, as appropriate, to shortlisted Team(s) selected to participate in Step 2.

**NOTE 2: Attachment 5 will be provided at a future date, as appropriate, to the Team selected as the most advantageous to the Government.

1.0 PROJECT SUITE INFORMATION

1.1 The U.S. Army Corps of Engineers (USACE) Omaha District (NWO), on behalf of the Air Force Civil Engineering Center (AFCEC), is seeking to identify a Contractor for the Initial Minot Sentinel Beddown (IMSB), Minot Air Force Base, North Dakota.

1.2 Project Goals:

Project Goal / Objective

Description / Key Focus Areas

Collaborative Project Development

Facilitate early and continuous collaboration between the contractor, stakeholders, and the Government to jointly develop the project’s design, cost, and schedule in a non-adversarial environment.

Innovation, Speed, and Flexibility

Leverage the OT framework outside traditional FAR constraints to emphasize speed, innovation (in materials, methods, and delivery), and optimal mission outcomes.

Qualifications- Based Selection

Prioritize the selection of a Design-Bid-Build Partner based on proven past performance, team merit, and technical approach rather than detailed construction price proposals at this initial stage.

Risk Management & Feasibility

Ensure the chosen team has a deep understanding of complex Military Construction (MILCON) requirements, coupled with proactive risk identification and mitigation strategies.

Integrated Team Execution

Establish a cohesive team structure for construction (including Prime, Designer of Record, Key Subcontractors, and the Government) that demonstrates clear reporting lines, continuity, and collaborative execution capabilities.

1.3 The established period of performance is 1,440 days for the CVMC, 920 days for the SFOC, and 550 days for the AC project from notice to proceed. Total project suite funding must not exceed $203M. White Papers, Pitch Meeting responses, and the selected Contractor’s post-selection Phase 1 Proposal must demonstrate a credible approach to delivering the project within these time and affordability constraints. The Government will not require a preliminary or construction price at the time of initial selection.

NOTE: The issuance of notice to proceed is subject to availability of funds. Each project will have a unique notice to proceed date that may or may not be concurrent with the other projects in this suite, although it is Government’s intention to award all projects in FY27. These dates will be communicated to the selected Contractor during Phase 1 Pre-Construction Services.

1.4 The Government intends to utilize a Design-Bid-Build (D-B-B) under an Other Transaction Agreement (OTA) project delivery method. This approach emphasizes collaboration between the selected Contractor and the Designer of Record (DOR), qualifications-based selection, open-book pricing, and shared risk management between the Government and the Contractor.

2.0 ACRONYMS AND DEFINITIONS

• CMAR (Construction Manager At Risk): A delivery model that is functionally similar to the D-B-B under OTA delivery method. Differences exist between these two methods, but experience with CMAR will generally be recognized as valid experience with D-B-B under OTA.

• CUI (Controlled Unclassified Information): Information that requires safeguarding or dissemination controls pursuant to and consistent with applicable law, regulations, and government-wide policies, but is not classified under Executive Order 13526 or the Atomic Energy Act, as amended.

• D-B-B under OTA (Design-Bid-Build under Other Transactional Agreement):

A two-stage project delivery method where the owner selects a Contractor based on qualifications. The Contractor then works collaboratively with the Government and DOR during Phase 1 (pre-construction activities) to adjust the design and establish a Final Construction Price and schedule for Phase 2 (construction).

• DOR (Designer of Record): The licensed professional, firm, or team responsible for the planning, design, and technical drawings/specifications for the facility.

IMSB involves two discrete DOR teams, with one responsible for the CVMC design and the other responsible for the SFOC and AC designs.

• FFP (Firm-Fixed-Price): A pricing structure where the price is not subject to any adjustment on the basis of the Contractor's cost experience in performing the contract. This places maximum risk on the Contractor and provides full responsibility for all costs and resulting profit or loss.

• Final Construction Price: A pricing structure that will be developed collaboratively during Phase 1 using Open Book methodology. Once negotiated and incorporated into the OT Agreement through modification, the Final Construction Price functions as a Firm-Fixed-Price (FFP) commitment for the final design documents resulting from Phase 1 collaboration. The Contractor assumes the risk for completing the work within the negotiated price and is generally responsible for cost overruns, except for Government directed changes, differing site conditions, or other authorized modifications that formally adjust the Final Construction Price.

• IMSB (Initial Minot Sentinel Beddown): The three projects contained within this solicitation, they are initial facilities intended to facilitate early Sentinel-related activities Minot Air Force Base, North Dakota.

• Model OT Agreement Template: The Government’s baseline OT agreement template that will be provided as Attachment 4. The Model OT Agreement Template identifies anticipated terms and conditions for the resulting Phase 1 OT Agreement and future Phase 2 modification, as applicable. The final agreement will be completed after selection and negotiation with the selected Contractor.

• Off-Ramp: Refers to a contractual mechanism that allows the Government to discontinue the D-B-B under OT relationship if a fair and reasonable Final Construction Price or schedule for construction cannot be achieved. Upon off-ramp, the Government retains rights to continue the project through another delivery method or Contractor.

• Open Book: A transparent cost estimating methodology used during the D-B-B under OT process where the Contractor shares complete, detailed, and auditable cost information with the Government and DOR. This includes, but is not limited to, direct and indirect costs, subcontractor quotes, and fee structures, for the purpose of collaboratively validating and negotiating a Final Construction Price.

• OT/OTA (Other Transaction/Other Transaction Agreement): A legally binding instrument other than a standard contract, grant, or cooperative agreement. OTs are not subject to the Federal Acquisition Regulation (FAR) and provide significant flexibility in tailoring the procurement process and terms to the needs of a project.

• SAM (System for Award Management): The official U.S. government website where all entities must be registered to do business with the federal government.

• UEI (Unique Entity Identifier): The 12-character alphanumeric identifier assigned to all entities (public and private companies, individuals, institutions, or organizations) who register to do business with the federal government in the System for Award Management (SAM).

• USACE (U.S. Army Corps of Engineers): The federal agency, acting as the engineering and construction agent for the Department of Defense, responsible for managing this solicitation and the resulting OT.

3.0 THE D-B-B UNDER THE OT PROCESS

The D-B-B under the OT model is a collaborative project delivery approach in which the Government, DOR, and Contractor work together to reduce risk and improve cost and schedule certainty. Under this OT, the process will be executed in two parts:

Phase 1: Pre-Construction Services

• Scope: The selected Contractor shall collaborate with the Government and DOR to adjust the design documents as necessary to improve constructability and develop progressively more detailed cost and schedule information.

• Purpose: The purpose of Phase 1 is to de-risk the project, resolve constructability issues, and align the parties on a common path forward before establishing the Final Construction Price and schedule.

• Constructability Design Adjustments: This phase will begin upon issuance of the Selection Notification and will continue through an agreed-upon milestone. That milestone will allow sufficient time for the Contractor to develop a fixed price model for construction via Open Book Costing and finalize the Integrated Schedule prior to award of Phase 2.

• Open Book Costing: During Phase 1 and concurrent with the Constructability Design Adjustments, the Contractor shall develop a transparent, "Open Book" cost estimate, sharing subcontractor quotes, labor, equipment, material, and detailed pricing data to support cost reconciliation and scope validation with the Government and DOR to inform the Final Construction Price.

• Integrated Schedule Development: During Phase 1 and concurrent with the Constructability Design Adjustments, the Contractor shall develop an integrated schedule in coordination with the Government and DOR. This schedule shall identify long lead items, allocated resources, phasing strategies, and other critical items that are identified by the Contractor, Government, or DOR to inform the final construction schedule

• Pricing & Negotiation: Upon completion of the Constructability Design Adjustments in Phase 1, the Contractor will submit a Final Construction Price and schedule, to be awarded in Phase 2 based on the Open Book Costing model and Integrated Schedule Development. The Agreements Officer will lead a formal negotiation with the Contractor to finalize a fair and reasonable price.

• Award: If the parties successfully negotiate a fair and reasonable price and schedule, the Government may modify the Phase 1 OT to authorize the awardee to complete the Phase 2 construction activities.

Phase 2: Construction

• Scope: Phase 2 consists of all physical construction activities required to deliver the complete and usable IMSB facilities as identified in the final design documents.

• The Off-Ramp: The Government is not obligated to award Phase 2. The OT includes an off-ramp provision allowing the Government, if unable to reach an agreement on a fair and reasonable price for Phase 2, a lack of sufficient funds, or any other reason determined (in its sole discretion), to use the adjusted design and associated project information to pursue another acquisition approach, including a competitive solicitation for construction.

4.0 OT PROCESS

The Government will conduct a two-step competitive Qualifications-Based Selection (QBS) process to identify the most qualified Contractor for this D-B-B under an OT delivery method. The competitive selection process consists of Step 1, White Paper evaluation, and Step 2, Pitch Meeting evaluation. The Pitch Meeting will serve as the final competitive evaluation step.

Step 1: White Paper Submission and Evaluation

Interested D-B-B under OT Contractors shall submit a White Paper in accordance with Attachment 1. The Government will evaluate White Papers to identify the most qualified Contractor to proceed to Step 2.

Step 2: Pitch Meeting Phase — By Invitation Only

A target of three of the most highly qualified Contractors from Step 1 will be invited to participate in a Pitch Meeting in accordance with Attachment 3. Each participant(s) will receive formal notification of their selection or non-selection. The 100% Design drawings and specifications for each of the three projects will be provided to the selected Contractors at this time. Prior to the Pitch Meeting, the Government will host an optional Q&A where questions and comments submitted by the selected Contractors will be addressed. This Q&A meeting will also provide an opportunity for open dialog between the Government and Contractor(s) as final preparations are being made for the Pitch Meeting. The Pitch Meeting will allow Contractors to present their approach and strategy to both pre-construction services and construction execution in-person. The meeting will focus on the Contractor’s understanding of the IMSB project suite, including a high-level review of the 100% design documents, strategy for subcontractor engagement, technical approach to suite-specific construction activities and schedule, ability to support the Phase 1 pre-construction services, and overall team chemistry.

The 100% design documents and Attachments 3 and 4 will be distributed to the Contractors who are selected to participate in Step 2 upon the issuance of Down Select Notifications.

The Government may select the most advantageous Contractor based on the totality of the Step 1 White Paper and Step 2 Pitch Meeting evaluation.

Post-Selection Phase 1 OT Agreement - Development and Negotiation

• Attachment 4 – Model OT Agreement Template, provided upon issuance of Down Select Notifications, will serve as the baseline agreement template for award of the Phase 1 OT Agreement.

• After completion of the competitive QBS process, the Government will issue Attachment 5 – Post-Selection Phase 1 Instructions only to the selected Contractor.

• Attachment 5 - Post-Selection Phase 1 Instructions will include the proposed Phase 1 scope and will request information to assist in the development of the Phase 1 OT Agreement. Requested information may include a staffing plan, level of effort details, Phase 1 schedule, assumptions, exclusions, suggested alterations to the Model OT Agreement Template, and other information necessary to support the Phase 1 OT Agreement. Negotiations will be conducted as necessary based on the information received from the selected Contractor.

• Attachment 5 is not part of the competitive Step 2 evaluation and will not be issued to all down-selected Contractors; it is a post-selection document used only with the selected Contractor.

• If the Government and selected Contractor cannot reach agreement on fair and reasonable Phase 1 OT Agreement terms, the Government reserves the right to discontinue negotiations and take any action in the Government’s interest, including engaging other highly qualified Contractors, revising the acquisition approach, or cancelling the solicitation.

Award

• Phase 1 — Pre-Construction Services: The selected Contractor may be awarded a Phase 1 OT Agreement after successful negotiation of fair and reasonable Phase 1 terms. No construction activities will be authorized under Phase 1. Subject to the availability of funding, the Contractor will receive a stipend for Phase 1 activities using appropriated funds for planning, design, and pre-construction services, as applicable.

• Phase 2 — Construction: Phase 2 may be added by modification to the OT Agreement upon successful negotiation of a fair and reasonable Final Construction Price and schedule. Phase 2 is subject to statutory authorization, required approvals, availability of Military Construction funds in or around FY27, and the Government’s determination that progression to construction is in the Government’s interest. If the Government and the Contractor cannot agree upon a Final Construction Price and/or schedule, the Government deserves the right to exercise its off-ramp, terminate negotiations, and utilize the Phase 1 design to procure construction through alternative methods.

5.0 SUBMISSION REQUIREMENTS

Step 1: White Paper

• Contractors shall submit their White Paper in accordance with Attachment 1.

• Submission Requirements: The White Paper must address all requirements outlined in Attachment 1. Incomplete submissions may be deemed non-conforming and disqualified from further consideration. Additionally, as discussed in Attachment 1, submissions that do not demonstrate the required bonding capacity will be disqualified from further consideration.

Step 2: Invitation for Pitch Meeting

• Shortlisted Contractors shall participate in the Pitch Meetings in accordance with Attachment 3 (provided to the shortlisted Contractors).

• Submission Requirements: Attachment 3 will provide the official requirements for the Pitch Meeting in Step 2 to the selected Contractors.

• The Pitch Meeting will serve as the final competitive evaluation step. The Government intends to select the most qualified Contractor based on the Step 1 White Paper and Step 2 Pitch Meeting evaluation.

Post-Selection Phase 1 OT Agreement - Development and Negotiations

• After selection, the Government will issue Attachment 5 – Post-Selection Phase 1 Instructions only to the selected Contractor.

• Submission Requirements: The selected Contractor shall provide information as requested in Attachment 5, which may include suggested alterations to Attachment 4 – Model OT Agreement Template. This information and resulting negotiations will serve as the basis for the Phase 1 OT Agreement.

• The Post-Selection Phase 1 Instructions is not a separate competitive evaluation step and will not be issued to all shortlisted Contractors.

• Development and negotiation of the Phase 1 OT Agreement will not establish the Phase 2 OT Agreement, Final Construction Price, or final schedule. The Post- Selection Phase 1 Instructions response and resulting negotiations may include preliminary cost information, cost approach, labor rates, level of effort, fee, assumptions, schedule and other information necessary to support future open-book cost and integrated schedule development. Any target construction price or schedule for Phase 2 will be developed and negotiated later during Phase 1.

• Attachment 4 provides the Model OT Agreement Template for informational and negotiation purposes. The final OT Phase 1 Agreement will be completed after selection and negotiation of Phase 1 terms with the selected Contractor.

6.0 EVALUATION CRITERIA — STEP 1 AND STEP 2

The Government has sole discretion of the evaluation criteria and process. The descriptions below and provided in Attachments 1 and 3 are meant to provide a general framework for each submission or pitch. They do not constitute final evaluation factors.

Step 1 White Paper Evaluation and Step 2 Pitch Meeting Evaluation will both be considered for the final selection decision of the most qualified Contractor. No competitive price, Phase 2 Final Construction Price, Conceptual Design submission, or Scope of Services submission will be evaluated during the competitive selection process.

Step 1: White Paper

• Each Contractor will be evaluated using a qualifications-based selection methodology for Step 1.

• Evaluation Criteria: Evaluation criteria for Step 1 are described in Attachment 1.

In general, Step 1 evaluates the Contractor’s bonding and written qualifications based on relevant experience, staffing and organizational approach, and collaborative approach to pre-construction services and construction execution.

Step 2: Invitation for Pitch Meeting

• Shortlisted Contractors will be evaluated using a qualifications-based selection methodology for Step 2.

• Evaluation Criteria: Evaluation criteria for Step 2 will be described in Attachment 3, provided to the Shortlisted Contractors. In general, the Pitch Meeting will evaluate the Contractor’s understanding of the IMSB project suite, including a high-level review of the 100% design documents, strategy for subcontractor engagement, technical approach to suite-specific construction activities and schedule, ability to support the Phase 1 pre-construction services, and overall team chemistry.

7.0 COMMUNICATIONS AND SUBMISSION INSTRUCTIONS

• Bidding Inquiry System: All questions regarding this Project Suite Solicitation must be submitted through the ProjNet Suite Bidder Inquiry System at https://www.projnet.org/projnet.

o Step 1 White Paper Information Solicitation Number: [Will be provided upon official RFQ issuance] Bidder Inquiry Key: [Will be provided upon official RFQ issuance] Inquiry Deadline: ProjNet will be closed to new inquiries on the date and time identified in the Overview Schedule.

o The Government will post answers to questions received. Companies are encouraged to monitor ProjNet for updates.

https://www.google.com/url?q=https%3A%2F%2Fwww.projnet.org%2Fprojnet o The Step 2 Pitch Meeting inquiry process, if applicable, will be provided only to shortlisted Contractors invited to Step 2. Any post-selection Phase 1 Proposal questions will be handled directly with the selected Contractor during post-selection Phase 1 OT Agreement development and negotiations.

• White Paper Submission:

o Due Date: White Papers are due no later than the time and date specified in the official RFQ.

o Submission POCs: Jennifer Gilbreath

(jennifer.c.gilbreath@usace.army.mil) and Ariel Vogan (ariel.e.vogan@usace.army.mil) via PIEE Solicitation Module. Step-by- Step instructions are posted on the sam.gov. ONLY PIEE submissions will be accepted for required competitive submissions, unless otherwise instructed by the Government. Step 2 Pitch Meeting logistics and any required materials will be provided to invited Contractors in Attachment 3.

The post-selection Phase 1 Proposal process will be provided only to the selected Contractor in Attachment 5.

o File Formats: Only .pptx, .pdf, .doc, .docx, .xlsx, or .xls attachments are permitted. Files ending in .zip or .exe will not be accepted.

NOTE: Submissions that are generic, boilerplate, or fail to demonstrate project-specific understanding may be assessed with lower confidence.

8.0 SPECIAL CONSIDERATIONS

8.1 Governing Documents and Registration

This announcement, its stated attachments, and any websites incorporated by reference constitute the entire solicitation. In the event of a discrepancy between the announcement, the attachments, or the websites, this main solicitation announcement shall take precedence.

All Contractors must be registered in the System for Award Management (SAM) at www.sam.gov and possess a valid Unique Entity Identifier (UEI) to be eligible for award. The selected Contractor shall maintain an active SAM registration during contract performance and through final payment of the OT.

As of the time of publication of this solicitation, all proposal submissions are anticipated to be unclassified.

8.2 Cybersecurity Requirements

(a) Authority & Applicability: The Department of War (DoW) has established the Cybersecurity Maturity Model Certification (CMMC) program, as codified in 32 CFR Part 170, to ensure that entities handling government information implement appropriate cybersecurity standards. As a matter of DoW policy, the principles of the CMMC https://www.google.com/url?q=http%3A%2F%2Fwww.sam.gov program are applicable to the OT resulting from this solicitation. Performance under the resulting Agreement will require the handling of Federal Contract Information (FCI).

(b) Required Level & Scope: The Government has determined that CMMC is not applicable for all projects in the IMSB project suite.

8.3 Government-Provided Resources for Cybersecurity and Contracting

The U.S. Government provides several no-cost resources to assist businesses in navigating the federal marketplace and strengthening their cybersecurity posture. All Contractors are encouraged to explore these programs.

• APEX Accelerators (Government Contracting Assistance): APEX Accelerators (formerly PTAP) offer free, expert guidance to businesses seeking to enter or expand their work within the government sector. Their mission is to help build a strong U.S. supply chain through confidential, one-on-one coaching (e.g., SAM.gov registration, finding opportunities, proposal processes). Find your local APEX Accelerator: https://www.apexaccelerators.us/#/

• Project Spectrum (Cybersecurity Compliance Support): Project Spectrum is a DoW-funded, vendor-neutral initiative dedicated to helping businesses in the Defense Industrial Base (DIB) improve cybersecurity readiness. They provide tools, training, and individualized dashboards to help small and medium-sized businesses meet DoW requirements, including CMMC. Access resources:

https://www.projectspectrum.io/#/

8.4 Project-Specific Terms and Conditions

(a) Congressional Authorization Limitation: Construction under any resulting OT is contingent upon statutory authorization and appropriation of funds. No construction activities shall be initiated unless and until the project is authorized in the National Defense Authorization Act (NDAA) and funded through applicable appropriations. Initial performance will be limited to pre-construction activities (Phase 1), which may proceed using MILCON Design funds following Congressional notification. Transition to construction (Phase 2) is contingent upon satisfaction of these requirements. The Government is not obligated to proceed with construction, and performance of Phase 1 shall not be construed as a commitment to do so.

(b) Performance and Payment Bonds: The successful Contractor must demonstrate the capability to provide single project Performance and Payment Bonds of at least $100,000,000.

(c) Commitment to Small Business Participation: Small business participation is encouraged but not required for award eligibility under 10 U.S.C. § 2808a. Contractors have full flexibility to structure their teams in a manner that best supports successful project performance. If a Contractor identifies a small business partner, the partner’s https://www.apexaccelerators.us/#/ https://www.projectspectrum.io/#/ role should be clearly described and may be incorporated into the resulting Agreement, as applicable.

(d) Site Visit: Site visit information and logistics may be provided to Contractors invited to the Step 2 Pitch Meeting or to the selected Contractor during post-selection Phase 1 proposal development and negotiation, as determined by the Government. The Government reserves the right to control timing, access, attendance limitations, and security procedures for any site visit. USACE will not reimburse the Contractors for costs associated with the Site Visit.

(e) DBB OT Approach — Step 1, Step 2, Post-Selection Phase 1 Proposal, and Phase 1 Performance: This requirement will be executed using a D-B-B under OT model under OT pursuant to 10 U.S.C. § 2808a. The Government intends to establish a collaborative, integrated team environment where the selected Contractor works closely with the Government and DOR to refine the design, manage risk, and align cost and schedule within the established affordability constraints.

(f) INFORMATIONAL PURPOSES ONLY / REFERENCE ONLY

SPECS/DRAWS/REPORTS ATTACHMENTS:

TBD

INFORMATIONAL PURPOSES ONLY / REFERENCE ONLY:

TBD

9.0 WHITE PAPER CONTENT

Issuance of this solicitation is a Request for White Papers only, the required Attachment 1 – Request for White Paper (Step 1) is the only submission required to be submitted by the solicitation closing date stated in the posting.

***End of Section***

DRAFT - PROJECT SUITE SOLICITATION
PROJECT SUITE SOLICITATION OVERVIEW INFORMATION
ANTICIPATED SCHEDULE
Note: This schedule is subject to change at the Government's discretion.
1.0 PROJECT SUITE INFORMATION
3.0 THE D-B-B UNDER THE OT PROCESS
Phase 1: Pre-Construction Services
Phase 2: Construction
4.0 OT PROCESS
8.0 SPECIAL CONSIDERATIONS
9.0 WHITE PAPER CONTENT