Bid Abstract - W9128F25BA003 - OA Powerhouse Heat Pump Replacement.pdf
PDF 313 KB Posted
- Attached to
- Oahe Powerhouse Heat Pump Replacement
- Solicitation number
- W9128F25BA003
About this file
This document is an Abstract of Offers for a construction solicitation (W9128F25BA003) for the Oahe Powerhouse Heat Pump Replacement project in Hughes County, South Dakota. The solicitation, issued by the US Army Corps of Engineers Contracting Division, opened on 26 June 2025 and received four offers from different contractors: IGE Reagent World, Inc., American Mine Services, MCL-MRKVII, LLC (JV), and Precision Mechanical, LLP.
The project involves four primary work items: (1) removal and replacement of two 180-ton heat pumps and one 8" basket strainer, (2) mechanical and electrical work for nine Air Handling Units, (3) removal and replacement of valve actuators, and (4) remaining associated work. The offers range from approximately $2.06 million to $3.48 million, with the government estimate at $3,379,521.00. All bidders acknowledged three amendments and most provided 20% bid security, with one contractor not providing bid security. The contract is for the Oahe Powerhouse located in Pierre, South Dakota, and involves significant HVAC equipment replacement and related infrastructure modifications.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. DATE ISSUED 3. DATE OPENED
13-May-25 26-Jun-25
I CERTIFY THAT I HAVE OPENED, READ AND
AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE DATE SIGNED
C. REASONABLE CONTRACT
7A 7B 7C D.
ITEM # DESCRIPTION OF OFFER ITEM EST. QUANTITY UNIT
Item 0001 Removal and replacement of two (2) 180-ton heat pumps (screw chiller type) and one (1) 8" basket strainer.
1 JOB
Item 0002 Mechanical and electrical work items pertinent to nine
(9) Air Handling Units.
1 JOB
Item 0003 Removal and replacement of valve actuators.
1 JOB
Item 0004 All Remaining Work
1 JOB
CLIN 0001 TOTAL AMOUNT $2,625,375.00
ESTIMATED AMOUNT
$1,439,924.97
$1,441,818.94
$377,554.85
$120,222.24
$3,379,521.00
$971,388.75
$918,881.25
$210,030.00
$525,075.00
CAGE - 4PQ72
UEI- JV6AKUMZU1S3
Bid Security 20%
C. AMENDMENTS ACKNOWLEDGED - 3
ESTIMATED AMOUNT
NO. 4
A. OFFEROR
Precision Mechanical, LLP
5700 Highway 79
Rapid City, SD 57702
$2,066,683.00 $2,998,765.00 $3,476,515.39
$1,119,876.00
AMOUNT
$332,649.00
$554,735.00
$59,423.00
ESTIMATED AMOUNT
$1,821,039.10
$985,831.26
$279,320.00
$390,325.03
ESTIMATED AMOUNT
$1,499,382.50
$749,691.25
$449,814.75
$299,876.50
UEI- GP66DEVNP2A1
Bid Security 20%
C. AMENDMENTS ACKNOWLEDGED - 3
NO. 3
A. OFFEROR
MCL-MRKVII, LLC (JV)
14558 Portal Circle
LaVista, NE 68138
CAGE - 0QUS6
6. NUMBER OF AMENDMENTS ISSUED
Oahe Powerhouse, Hughes County, South Dakota
Oahe Powerhouse Heat Pump Replacement
UEI- WMD6CT8YXG49
CAGE - 875R6
UEI- CGPZMJ12XGK8
Bid Security- Not Provided
C. AMENDMENTS ACKNOWLEDGED - 3
Bid Security 20%
C. AMENDMENTS ACKNOWLEDGED - 3
CAGE - 6TV08B. REASONABLE CONTRACT
A. OFFEROR A. OFFEROR
18401 Von Karman AVE STE 360 130 Miners Drive
A. HIRED LABOR
IGE Reagent World, Inc. American Mine Services
Irvine, California 92612 Lafayette, Colorado 80026
NO. 1 NO. 2
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER
W9128F25BA003
4. ISSUING OFFICE
8. GOVERNMENT ESTIMATE
(Check A, B or C AND COMPLETE D, E AND F)
5. PROJECT TITLE
9. OFFERS
TO THIS SOLICITATION
SIGNATURE
l PAGES
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
Daniel D. Monahan - Contracting Officer/ Margarette Wolfe - Contracting Specialist
OMAHA, NE 68102-1618
1616 CAPITOL AVENUE
CONTRACTING DIVISION (CENWO-CT)
US ARMY CORPS OF ENGINEERS
26 JUN 2025
| 2025-06-26T15:26:17-0500 | |
| MONAHAN.DANIEL.D.1011397812 |