AM0002 - 01 12 00 W9128F25BA002 FP PH1 Surge Tank Specs.pdf

PDF 595 KB Posted

Attached to
Fort Peck PH 1 Surge Tank Roof Replacement
Solicitation number
W9128F25BA002
Issued by

About this file

This document is a Section 01 12 00 Construction General specification for the Powerhouse #1 Roof Repairs project at Fort Peck Dam in Montana. The specification outlines general construction requirements, including contractor responsibilities for project execution, site access, equipment usage, and work constraints. Key provisions include working hours (0630 to 1700 hrs Monday through Friday), observance of 12 federal holidays, requirement for portable toilets, and specific guidelines for equipment use such as a limited-use 3,000-pound air tugger located at elevation 2289.4 with a floor load rating of 180 lbs per sq. ft.

The document emphasizes contractor obligations such as protecting existing facilities, coordinating with other contractors, submitting proposed methods of operation within 15 days of notice to proceed, and providing a one-year warranty on all work performed. The project site is located at the Ft Peck Dam Powerhouse, with contractors required to coordinate exact work locations and staging areas with the Contracting Officer's Representative (COR) and project office prior to initiating work. Specific restrictions include using a 12,000 lb freight elevator for access and verifying all loading cases before construction.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Powerhouse #1 Roof Repairs Fort Peck Dam, Montana FP00103

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 12 00

CONSTRUCTION GENERAL

PART 1 GENERAL

1.1 SCOPE

1.2 CONSTRUCTION RIGHT-OF-WAY

1.3 PROTECTION OF EXISTING FACILITIES AND WORKS

1.4 CARE OF WATER

1.5 COOPERATION WITH OTHER CONTRACTORS

1.6 ORDER OF WORK

1.7 SUBMITTALS

1.8 WARRANTY OF CONSTRUCTION (MAR 1994)

1.9 TELEPHONE/INTERNET

1.10 USE OF GOVERNMENT EQUIPMENT

1.11 PORTABLE TOILETS

1.12 FEDERAL HOLIDAYS AND WORKING HOURS

1.13 PROJECT LOCATION

PART 2 NOT USED

PART 3 NOT USED

-- End of Section Table of Contents --

SECTION 01 12 00 Page 1

Am-0002

SECTION 01 12 00

CONSTRUCTION GENERAL

PART 1 GENERAL

1.1 SCOPE

The work covered in this section is outlined as a statement of construction requirements common to all the work. Specific requirements for materials and installations are provided under the Technical Sections herewith. No claims for extras shall be made on account of items presumed to have been omitted from this section.

1.2 CONSTRUCTION RIGHT-OF-WAY

The Contractor will be assigned working areas or working right-of-way limits for use in the prosecution of work under this contract, subject to FAR clause 52.236-10 entitled "Operations and Storage Areas."

1.3 PROTECTION OF EXISTING FACILITIES AND WORKS

The Contractor shall be responsible for the protection of the work area from damage and upon completion of the work shall leave existing works in a condition equal to that which existed when the work started. All work, storage of materials, and construction plant shall be kept within the limits of the areas assigned. Prior to construction operations, the Contractor shall confer with the Contracting Officer's representative to determine the proximity of any possible under-ground obstructions, pipe or equipment which could be damaged as a result of construction operations.

Existing utility lines that are shown on the drawings or the locations are otherwise made known to the Contractor shall be protected from damage, and if damaged, shall be repaired by the Contractor at no additional expense to the Government. In the event that the Contractor damages any existing utility lines that are not shown or the locations of which have not been made known to the Contractor, the Contractor shall immediately notify the Contracting Officer. The Contracting Officer will review the information and discuss with the Contractor how to proceed. The Contractor will be responsible for the protection of structures from any structural damage during the construction operations. Roads and surfaces shall be protected from damage by the work or if damaged shall be repaired with equal materials at no additional expense to the Government. At all times the plant and work areas shall be kept in a condition conducive to safety of workmen and the public and neat in appearance. Waste or surplus materials shall not be allowed to accumulate in the construction areas.

1.4 CARE OF WATER

Full responsibility for care of water shall be borne by the Contractor until completion of work under this contract. The Contractor shall provide the materials and equipment and perform all work necessary to facilitate construction and to protect the work from damage by water. The Contractor shall make the needed investigations and determinations of conditions, both existing and anticipated concerning care of water. Plans for care of water are subject to approval by the Contracting Officer prior

SECTION 01 12 00 Page 2 to construction. Facilities shall be removed upon completion of the work.

1.5 COOPERATION WITH OTHER CONTRACTORS

The Contractor shall cooperate and coordinate work with that of others working in the area during the life of this contract. The Contractor shall coordinate work with others to avoid undue interference and shall conduct operations, other than approved required access, within the limits of the assigned construction area or construction right-of-way limits.

The Contractor shall cooperate with others as necessary in the interest of timely completion of all work and in the event of disagreement the decision of the Contracting Officer shall be final.

1.6 ORDER OF WORK

The sequence of operations shall be maintained so that the maximum amount of work may be done under favorable working conditions in accordance with the completion time set forth in FAR clause 52.211-10 entitled "Commencement, Prosecution, and Completion of Work." The Contractor shall submit for approval, within 15 days after receipt of notice to proceed a narrative description of the proposed methods of operation.

1.7 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Proposed Methods of Operation; G-AO

SD-11 Closeout Submittals

Warranty of Construction

(List of warranties with copy of each)

1.8 WARRANTY OF CONSTRUCTION (MAR 1994)

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or

SECTION 01 12 00 Page 3 personal property, when that damage is the result of--

(1) The Contractor's failure to conform to contract requirements; or

(2) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall--

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.

(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.

(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud. (FAR 52.246-21)

1.9 TELEPHONE/INTERNET

The Contractor is responsible for arranging telephone/Internet service for the Contractor's trailer through the local telephone company.

1.10 USE OF GOVERNMENT EQUIPMENT

Limited use of a floor mounted 3,000 pound capacity air tugger located at elevation 2289.4 (T.O. Steel Deck) will be available for the contractors use. *Am-2 The load rating for the floor at elevation 2289.4 (T.O.Steel Deck) with the air tugger is rated at 180lbs per sq. ft (please reference

SECTION 01 12 00 Page 4

Am-0002 g6ctxldr Highlight drawing FP17-60-20). **Am-2 The hatch opening in the floor is 41" x 83".

Use of the air tugger is at the contractor's risk. The government is not responsible for delays as a result of mechanical breakdowns for any reason. Provide a qualified operator in accordance with ANSI/ASME B30.16.

Prior to use, the government will provide orientation on the use of the equipment and the operator must demonstrate to the government knowledge of and proper use of the hoist. The contractor will be responsible for furnishing and performing rigging for all lifts.

A 12,000 lb freight elevator provides access from ground level to a location accessible by the air tugger. Dimensions of the elevator can be found in the reference drawings.

*Am-2

The outer floor (located at elevation 2299.0) load rating is 20lbs per sq.

ft. live load or snow load (please reference drawing FP17-60-34).

Prior to work construction, it is the contractor's responsibility to verify all loading cases.

**Am-2

1.11 PORTABLE TOILETS

Toilet facilities will not be available for Contractor's use. The Contractor shall provide and maintain portable toilets for use by the Contractor's staff. Toilet(s) shall be placed at the location directed by the Contracting Officer. To prevent overturning by high winds, all portable toilets shall be anchored down.

1.12 FEDERAL HOLIDAYS AND WORKING HOURS

The Contractor will have access to the facility for work during normal plant business hours from 0630 to 1700 hrs Monday through Friday, excluding any federally recognized holidays or observance days. The Contractor shall plan all work accordingly. These hours will be strictly adhered to unless the Government determines work outside this time is beneficial to the Government or a bilateral modification for extended working hours is executed.

The following Federal legal holidays are observed by this installation:

New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Juneteenth 19 June Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December

If the wage determination has a discrepancy with the above list of observed Federal holidays, then the wage determination takes precedence.

SECTION 01 12 00 Page 5

Am-0002 g6ctxldr Highlight g6ctxldr Highlight g6ctxldr Highlight

1.13 PROJECT LOCATION

The project is located at the Ft Peck Dam Powerhouse. Coordinate with the COR and Ft Peck project office on the exact work location and worksite staging areas prior to the initiation of work.

PART 2 NOT USED

PART 3 NOT USED

-- End of Section --

SECTION 01 12 00 Page 6