01 11 00 Am-0001.pdf
PDF 583 KB Posted
- Attached to
- Oahe Switchyard Disconnect Switch Replacement Federal contract opportunity
- Solicitation number
- W9128F23R0003
About this file
This solicitation is for the Oahe Switchyard Disconnect Switch Replacement project. The U.S. Army Corps of Engineers, Omaha District is seeking to replace approximately 40 manual disconnect switches, 13 motor-operated disconnect switches, and 15 grounding switches at the 115kV and 230kV switchyards at Oahe Dam in Pierre, South Dakota. Additional work includes replacing insulators, bus sections, cables, and performing weld repairs to buses. Bids are due by July 6, 2023 with work expected to be completed within 730 calendar days of notice to proceed. The project cost is estimated between $5-10 million. The primary NAICS code is 237130 for power and communication line structure construction with a small business size standard of $45 million.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W9128F23R0003_Am 0003.pdf | ||
| W9128F23R0003 Sign-in_Sheet_061423.pdf | ||
| 13 48 00.00 26 Am-0002.pdf | ||
| W91238F23R0003_AM0002.pdf | ||
| W9128F23R0003 Sign-in_Sheet_062723.pdf | ||
| 01 22 00 Am-0001.pdf | ||
| E-201 Am-0001.pdf | ||
| E-202 Am-0001.pdf | ||
| W91238F23R0003_AM0001.pdf | ||
| 01 12 00 Am-0001.pdf | ||
| REGISTER Am-0001.pdf | ||
| 33 75 10.00 26 Am-0001.pdf | ||
| OA Switchyard W9128F23R0003 Solicitation 1 of 4.pdf | ||
| OA Switchyard W9128F23R0003 Ref Drawings 4 of 4.pdf | ||
| OA Switchyard W9128F23R0003 Contract Dwgs 3 of 4.pdf | ||
| OA Switchyard W9128F23R0003 Specs 2 of 4.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Switchyard Disconnect Switch Replacement Oahe Dam OAA2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
1.1.2 Delivery Location
1.2 DRAWINGS
1.3 OCCUPANCY OF PREMISES
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
Am-0001
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
These specifications include removal of existing equipment and the furnishing and installation of Contractor-furnished equipment at the Oahe Switchyard. Base work and optional work are broken out separately in Section 01 22 00 MEASUREMENT AND PAYMENT. The total work includes but is not limited to:
a. Remove existing, furnish and install nine (9) new 230kV motor operated disconnect switches complete with motor operators.
b. Remove existing, furnish and install twenty-seven (27) new 230kV manual-operated disconnect switches with ten (10) ground switches.
c. Remove existing, furnish and install four (4) new 115kV motor operated disconnect switches complete with motor operators.
d. Remove existing, furnish and install thirteen (13) new 115kV manual-operated disconnect switches with five (5) ground switches.
e. Furnish the services of the manufacturer's Field Engineer to supervise installation of the disconnects, 230kV and 115kV.
f. Remove existing, furnish and install *Am-1 seventy-two (72) eighty-seven (87) **Am-1 total new Unit and Transmission Line String Insulators: *Am-1 forty-five sixty ( 6045) **Am-1 230kV, twenty-seven
(27) 115kV.
g. Prepare and furnish as-built corrections to the Contract Drawings, 230kV work and 115kV work.
h. Systems testing and commissioning, 230kV equipment and 115kV equipment.
i. Provide separate O&M Manuals for all new Contractor-furnished equipment.
j. Provide training of Government personnel for all new Contractor-furnished 230kV and 115kV equipment.
k. Welding services for bus repair, 230kV switchyard and 115kV switchyard.
l. Replace existing power, annunciation, and control cables for the 230kV and 115kV disconnect switches.
m. Furnish special tools, accessories, and spare parts as listed in the DIVISION 26 technical specifications.
SECTION 01 11 00 Page 2
1.1.2 Delivery Location
Delivery location will be at:
United States Army Corps of Engineers Oahe Dam 28563 Powerhouse Road Pierre, SD 57501
1.2 DRAWINGS
a. The Contract Drawings that accompany these Specifications are a part thereof.
b. Contractor shall immediately check furnished For Information Only (FIO) Drawings and Contract Drawings and notify the Government of any discrepancies.
1.3 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --