This solicitation package includes a pricing schedule and details for a federal contract opportunity to construct a Radio Frequency Facility at Ellsworth Air Force Base in South Dakota. The contractor will be required to provide design and construction services for a new approximately 64,500 square foot RF Hangar facility including an aircraft measurement bay, back shop spaces, administrative areas, and support spaces. One secure area will be constructed to Intelligence Community Directive 705 standards. The facility must be designed and constructed in accordance with DoD and Air Force standards including unified facilities criteria for building requirements, sustainable building practices, and antiterrorism/force protection requirements. The pricing schedule outlines various contract line items and optional items for the design and construction work. Pricing is requested for different periods of performance with weighting given to earlier periods for evaluation. The total potential period of performance is 900 days. The Department of the Army Corps of Engineers District Office in Omaha is listed as the contracting agency.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICING CLIN SCHEDULE

SOLICITATION NUMBER: W9128F22R0054

Section 00 10 00: PRICING CLIN SCHEDULE

Project Title:

B-21: Radio Frequency Facility (RF Hangar)

Location:

Ellsworth Air Force Base, Rapid City, South Dakota

Base Contract Line Item Number (CLIN) Schedule
Item No.DescriptionQuantityUnitUnit PricePeriod #1
(0-90 days*)Period #2
(91-180 days*)Period #3

(181-270 days*) Entire work complete for Construction of the B-21 Radio Frequency Facility (RF Hangar), complete to the five-foot line, excluding items separately listed below. Scope includes construction of the design and associated systems described above and throughout this Contract. (MILCON)

1JOBXXX$0.00$0.00$0.00
0002

Entire work complete for Construction of Sitework, Utilities, and Pavements from five-foot line to the limits of construction of the B-21 RF Hangar, excluding items listed separately below. (MILCON)

1JOBXXX$0.00$0.00$0.00
0003

Entire work complete for Demolition of Dock 63 and associated existing Features, Paving, Airfield Paving, Utilities and Infrastructure on the B-21 RF Hangar site excluding items separately listed below and as communicated in the Demolition drawings and specifications. (MILCON)

1JOBXXX$0.00$0.00$0.00
0004

Entire work complete for Construction of all Flightline paving - including Airfield Concrete, Airfield Ground Support Equipment (GSE) paving, and Airfield Shoulder Paving – to include all site preparation, base, drainage layer, underdrains, earthwork, underdrains, and pavement markings - excluding bid option paving listed separately below. (MILCON)

1JOBXXX$0.00$0.00$0.00
0005

Entire work complete for cybersecurity documentation, and alterations to commercial equipment, devices, firmware, and software to satisfy cybersecurity requirements. (MILCON)

1JOBXXX$0.00$0.00$0.00
TOTAL BASE OFFER-$0.00$0.00$0.00
OPTION CLIN SCHEDULE
0006

Entire work complete for Procurement and Installation of a 5-Part ESD Fuel Resistive Resinous Flooring System per specification 09 67 23.16 in lieu of a 3-Part Fuel Resistive Resinous Flooring System per specification 09 67 23.15. (MILCON)

1JOBXXX$0.00$0.00$0.00
0007

Entire work complete for Construction of additional asphalt shoulders - to include all associated site preparation, base, earthwork, and pavement markings. (MILCON)

1JOBXXX$0.00$0.00$0.00
0008

Entire work complete (cost add) to perform finishing phases of project with US Citizens only in lieu of US Citizens or US Persons per specification 01 14 00 Work Restrictions. (MILCON)

1JOBXXX$0.00$0.00$0.00
0009

Entire work complete for Procurement and Installation of FF&E. (O&M)

1JOBXXX$0.00$0.00$0.00
0010

Entire work complete for Procurement, Installation, Commissioning, and Cybersecurity of Intrusion Detection System (IDS), and Access Control System (ACS). (O&M)

1JOBXXX$0.00$0.00$0.00
0011

Entire work complete for removal and disposal of additional asbestos containing material (ACM) measured in square feet (SF) (i.e., tile, mastic, cladding, etc.) in Dock 63 not previously identified in the project hazardous material survey documentation, and not otherwise included in the basic amount. Assume 2,500 SF of material for this CLIN. See CLIN 0012 for ACM measured in LF. (MILCON)

1JOBXXX$0.00$0.00$0.00
0012

Entire work complete for removal and disposal of additional asbestos containing material (ACM) measured in linear feet (LF) (i.e., insulation, pipe insultation, etc.) in Dock 63 not previously identified in the project hazardous material survey documentation, and not otherwise included in the basic amount. Assume 500 LF of material for this CLIN. See CLIN 0011 for ACM measured in SF. (MILCON)

1JOBXXX$0.00$0.00$0.00
0013

Entire work complete for additional removal and disposal of contaminated soils not previously identified in the project hazardous material survey documentation, and not otherwise included in the basic amount. Assume 500 CY of material for this CLIN. (MILCON)

1JOBXXX$0.00$0.00$0.00
0014

Entire work complete for removal and disposal of non-adhered lead based paint in Dock 63 not previously identified in the project hazardous material survey documentation, and not otherwise included in the basic amount. Assume 2,500 CY of material for this CLIN. (MILCON)

1JOBXXX$0.00$0.00$0.00
0015

Entire work complete for removal and disposal of additional ACM piping not previously identified in the project hazardous material survey documentation, and not otherwise included in the basic amount. Assume 250 LF of material for this CLIN. (MILCON)

1JOBXXX$0.00$0.00$0.00
TOTAL OPTION OFFER$0.00$0.00$0.00
TOTAL (Base + Option) OFFER PRICE$0.00$0.00$0.00
GOVERNMENT WEIGHTS (By Period)85%10%5%
ADJUSTED PRICE (Total Base + Options * Weighted Periods)$0.00$0.00$0.00

TOTAL ADJUSTED PRICE (TAP) $0.00 Period of Performance (number of calendar days after issuance of Notice to Proceed) 900

NOTES:

1. See SECTION 00 21 01, INSTRUCTIONS TO OFFERORS for evaluation of options. The Government reserves the right to exercise Option Items 0006 and 0008 within 90 days of Notice to Proceed. The Government reserves the right to exercise Option Items 0007, 0009, and 0010 within 730 days of Notice to Proceed. The Government reserves the right to exercise Option Items 0011 - 0015 within 365 days of Notice to Proceed. Abbreviation: Operations and Maintenance (O&M).

2. This solicitation will use a "Pricing Includes Variation Over Time" (PIVOT) pricing strategy. The Total Adjusted Price (TAP) is a weighted average of the total contract price across all requested and active pricing periods, as defined above. The TAP will be the single pricing indicator for the best value determination. In the event of an award, the award price will be the pricing (per CLIN) submitted by the awardee in the period that the proposal is awarded. See Section 00 22 00, paragraph 9.1.4 for Price Factor submission instructions. Prices must be entered for all items of the schedule (highlighted in yellow above). Total amounts submitted without prices being entered on individual items will be rejected.

3. Option Items 0011-0015 have been written as extended pricing to simplify the TAP calculation. These Option Items will be written as unit prices (rounded to the nearest cent) in the final award documents, with unit price calculated based upon the units and quantities referenced in the CLIN description(s).

4. A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item No. 0001.

5. Contract duration is for award basic and option items. No contract duration extension will be provided upon award of any option items.

6. Pricing in each PIVOT period should represent the offeror's best pricing, per CLIN, within the respective award period(s). Period durations will be tracked from the due date of first pricing proposals through contract award. Subsequent amendments will retain and utilize that date for active period calculation purposes. In the event that an award period (as defined in this solicitation bid schedule) expires, the respective period will automatically be declared 'dead.' In that event, an amendment may or may not be issued, but the period(s) will be removed from the TAP calculation and the BVTO will occur with a TAP calculated only with active remaining periods. The offeror should not assume that updated/revised pricing may be requested prior to award within any period indicated.

7. The Government reserves the right to amend the project period of performance, pricing period durations, the respective period weighting(s), the number of active periods, and/or the contents of the CLIN schedule via amendment. Any revision(s) will be clarified in the respective amendment(s), and revised pricing for all CLINs for all periods will be requested.

8. Quantities for unit priced items are estimated only and the respective unit price will prevail in the event of an overrun or underrun subject to General Conditions (Contract Clauses) Clause FAR 52.211-18 “Variation in Estimated Quantities”.

9. Provide a supplemental price breakdown as part of the Volume I Pricing proposal. The pricing breakdown should total the sum of all basic CLINs in the first period of the PIVOT Proposal/Price Schedule. A template file has been provided under separate cover with this solicitation. In addition to the Supplemental Price Breakdown, the offeror may provide a short narrative that communicates primary cost drivers to the base bid that may not be clearly depicted in the Supplemental Price Breakdown. The contents of the narrative is at the Offeror’s discretion, but may be used by the Government to gauge current market trends/conditions, may be used in the development of future projects, and may be used if an amendment should be issued for the project. Please note that the contents of your Supplemental Price Breakdown and/or narrative will have no impact on the award decision.