TE-11-10_MASS NOTIFICATION SYSTEM SUPP RECORD OF INSP AND TEST.pdf

PDF 212 KB Posted

Attached to
FACILITY INVESTMENT SERVICES FOR THE 63RD READINESS DIVISION (RD) FOR REGION 5
Solicitation number
W9127S21Q0057
Issued by

View the file

Other files

File Type Posted
Contactor guidance doc_20210922 (002).pdf PDF
21Q0057_Amendment_0005_20211101.pdf PDF
63d RD_REGION 5_FIS_PWS_Final Rev 4_20211029.pdf PDF
FY22-FY24 Region 5-FIS_Index of Files_20211029.xlsx XLSX spreadsheet
W9127S21Q0057_Combined_Solicitation_Synopsis_Amend_4.pdf PDF
FIS_PWS_Sect J_ATCH-05_ELINs_FIS_Region 5_20211029.xlsx XLSX spreadsheet
W9127S21Q0057_AMENDMENT_4_20211029.pdf PDF
Region5_FIS_PWS_Section J_TE-01_Facilities Site Index and Maps_20211028.pdf PDF
TE-11-2_DIESEL FIRE PUMP ASSEMBLIES.pdf PDF
Region 5 Site Visit Minutes.pdf PDF
TE-11-15_FIRE HYDRANT ANNUAL INSPECTION.pdf.pdf PDF
TE-10-5_ENG_FORM_3394_2021Aug.pdf PDF
TE-10-3_GSA_FORM_376_11-1967.pdf PDF
FIS_PWS_Section J_TE-07_2018_GSA_PM Guide_FINAL.pdf PDF
DA_Fm5477_MAR2008.pdf PDF
TE-11-3_DRY PIPE FIRE SPRINKLER SYSTEMS.pdf PDF
TE-11-4_ELECTRIC FIRE PUMP ASSEMBLIES.pdf PDF
Region5_FIS_PWS_Section J_TE-03_Detailed Equipment Inventory_20211028.pdf PDF
Region 5 Site Visit Briefing Slides.pdf PDF
Site_Visit_Attendance_Sheet_21Q0057.pdf PDF
FIS_PWS_Sect J_ATCH-05_ELINs_FIS_Region 5_20211026.xlsx XLSX spreadsheet
TE-11-7_FIRE DEPARTMENT CONNECTIONS.pdf PDF
TE-11-13_WET PIPE FIRE SPRINKLER SYSTEMS.pdf PDF
Projnet_Inquiries_Region_5.pdf PDF
TE-10-1_Certification of Work.pdf PDF
Region5_FIS_PWS_Section J_TE-06_Quality Assurance Surveillance Plan_20211028.pdf PDF
TE-11-9_MAIN DRAIN TEST.pdf PDF
TE-11-11_NOTIFICATION AND INITIATING APPLIANCE SUPPLEMENT.pdf PDF
63d RD_REGION 5_FIS_PWS_Final Rev 3_20211028.pdf PDF
TE-11-12_PORTABLE FIRE EXTINGUISHER ANNUAL INSPECTION.pdf PDF
Region5_FIS_PWS_Section J_TE-02_Summary Equipment Inventory_20211028.pdf PDF
FIS_PWS_Section J_TE-09_Acronym_Definitions_20211028.pdf PDF
TE-11-1_DELUGE FIRE SPRINKLER SYSTEMS.pdf PDF
TE-10-2_Work Request Estimate and Completion Form.pdf PDF
W9127S21Q0057_Combined Solicitation And Synopsis_Amend 3.pdf PDF
TE-11-14_WATER STORAGE TANKS.pdf PDF
FY22-FY24 Region 5-FIS_Index of Files_20211028.xlsx XLSX spreadsheet
W9127S21Q0057_AMENDMENT 3_20211028.pdf PDF
TE-10-6_SPILL RESPONSE INCIDENT REPORT FORM.pdf PDF
TE-11-5_EMERGENCY LIGHT ANNUAL INSPECTION.pdf PDF
TE-11-6_FIRE ALARM ANNUAL INSP TESTING REPORT.pdf PDF
TE-11-8_KITCHEN HOOD SYSTEM ANNUAL INSPECTION.pdf PDF
Region5_FIS_PWS_Section J_TE-04_Government Points of Contact_20211028.pdf PDF
DA_Fm5479_MAR2008.pdf PDF
FIS_PWS_Sect J_ATCH-05_ELINs_FIS-ENV_Region 5_20211026.xlsx XLSX spreadsheet
Region5_FIS_PWS_Section J_TE-08_HVAC-Refrigeration Temp Standards_20211028.pdf PDF
TE-10-4_GSA_FORM_55_07-2002.pdf PDF
Region5_FIS_PWS_Section J_TE-05_Deliverables_20211028.pdf PDF
63d RD_REGION 5_FIS_PWS_Final Rev 2_20210928.pdf PDF
W9127S21Q0057_Combined Solicitation And Synopsis_Amend 2_10-5-2021.pdf PDF
Show 40 more

Latest 50 of 61 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

63rd Readiness Division MNS Supplementary Record of Inspection and Testing

MASS NOTIFICATION SYSTEM

SUPPLIMENTARY RECORD OF INSPECTION AND TESTING

This form is a supplement to the Fire Alarm Inspection & Test Report.

It includes a mass notification system test record.

This form is to be completed by the system inspection and testing contractor at the time of the inspection and/or test.

Insert N/A in all unused lines.

FACID

Building Number

Date of Inspection

Complete the remainder of this page once inspection is complete.

Mass Notification System Assessment Green Yellow Red

Fire Alarm system appears to operate as designed—Color Code (Color code is based on the following criteria: Green = No deficiencies or only noncritical

Comments/Deficiencies

Mass Notification System Information (if MNS is combination, enter “Combination” under Manufacturer)

Control Unit Manufacturer: Model Number: Location: Software Revision:

Primary Power

Voltage: Amps: Overcurrent Protection Type: Amps: Disconnecting Means Location:

Battery 1 Voltage: Amps: Mfr Year: Load Test

Battery 1 VDC: Ah: Temp (F):

Result of Battery 1 & 2

Battery 2 Voltage: Amps: Mfr Year: Load Test

Battery 2 VDC: Ah: Temp (F):

Pass Fail Replaced

Secondary Power

Other Power Present Description Yes No

MNS Power Supplies (for combination MNS panels where all tests are previously conducted, enter N/A for the tests below)

Type Visual Functional N/A Results

120-volt Power Pass Fail N/A

Generator or UPS

Battery Condition

Load Voltage

Discharge Test

Charger Test

Mass Notification System Type In-building MNS— combination

In-building MNS— stand alone

Wide Area

MNS

Indicate the MNS System Type

Mass Notification Equipment Tests Type Visual Functional N/A Results

Functional Test

Reset/Power Down test

Fuses

Primary Power Supply

UPS Power Test

Trouble Signals

Disconnect Switches

Ground Fault Monitoring

CCU Security Mechanism

Prerecorded Message Content

Prerecorded Message Activation

Software Backup Performed

Test Backup Software

Fire Alarm to MNS Interface

MNS to Fire Alarm Interface

Sound Pressure Levels Ambient dBA ______ Alarm DBA ______

System Intelligibility Test Method ______ Score ______ CIS Value ______