Solicitation W9127N23R0010 Amend 0003.pdf
PDF 557 KB Posted
- Solicitation number
- W9127N23R0010
About this file
This document is an amendment to a solicitation for the Bonneville Powerhouse 1 Main Unit Breaker (MUB) Replacement project. The amendment extends the response deadline from October 12th to October 26th, 2023 at 2:00 PM Pacific Time. It updates the contract line item descriptions and units of measure. It also modifies the specifications and pricing schedule in response to bidder inquiries. Specifically, it increases the quantities for on-site technical support during switchgear installation and commissioning/acceptance testing from one to three each. The solicitation seeks to replace the main unit breaker at the Bonneville Powerhouse 1 for the Department of the Army Corps of Engineers Engineering District Portland.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of Amendment 0003 is to:
1. Extend the submittal date from 2:00PM PT on 12 Oct 2023 to 2:00PM PT on 26 Oct 2023.
2. Updated CLIN Descriptions and Units of Measure.
3. Update Specif ications in response to Bidder Inquiries.
See Summary of Changes for more detail.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Oct-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127N23R0010
X 9B. DATED (SEE ITEM 11)
25-Aug-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Oct-2023
CODE
USACE, PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204
W9127N 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9127N23R0010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMEND 0003 SUMMARY
Amendment 0003 updates the following Specifciations:
Note revision marks are included to show changes.
Division 01 Specification Changes:
1. 01 10 00.00 25 Contract Administration Data
a. Was deleted in its entirety.
2. 01 10 10.00 25 Contractor’s Operations and Requirements
a. Was renamed to Security Procedures
b. Most of the section was deleted, see attached for changes.
3. 01 11 00.00 25
a. Revised “supervision” to “onsite technical support”, see attached for changes.
4. 01 22 00.00 25 Measurement and Payment
a. CLIN’s 5 and 6 were updated to “onsite technical support”, see attached for changes.
b. The price schedule was also modified to match, see attached.
5. 01 32 01.00 25 Project Schedule
a. Was deleted in its entirety.
6. 01 35 26.00 25 Government Safety Requirements
a. Was deleted in its entirety.
7. 01 45 00.00 25 Quality Control
a. Was deleted in its entirety.
Division 26 Specification Changes:
1. 26 13 13 Metal-Enclosed Switchgear
a. Paragraph 1.3, SD-01: Removed Preconstruction Submittals and Work Plan.
b. Paragraph 1.3, SD-07: Added “Field Personnel” to the submittal register.
c. Paragraph 3.5: Revised requirements for on-site technical support during installation.
d. Paragraph 3.5.c: Removed the paragraph and the associated submittal.
e. Paragraph 3.6.1: Revised requirements for on-site technical support during testing and commissioning.
f. Paragraph 3.11: Deleted the word “installation” at the end of the paragraph
Submittal Register
The following attachments are added to SAM.gov:
Updated CLIN Schedule (CLIN Schedule _ AMD 0003) Specifications Package (Technical Specs _ AMD 0003)
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 12-Oct-2023 02:00 PM to 26-Oct-2023 02:00 PM.
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 0003
The unit of issue has changed from Each to Job.
CLIN 0004
The unit of issue has changed from Each to Job.
CLIN 0005
The CLIN description has changed from Support and Supervise Switchgear Install to OnSite Tech Support
- Switchgear Install.
The CLIN extended description has changed from:
Provide Support and Supervision Services for Switchgear Installations
To:
Provide InstallationsOn-Site Technical Support for Switchgear Installation.
The pricing detail quantity has increased by 2.00 from 1.00 to 3.00.
The unit of issue has changed from Job to Each.
CLIN 0006
The CLIN description has changed from Support and Supervise Commissioning/AT to OnSite Tech
Support - Commissioning/AT.
The CLIN extended description has changed from:
Provide Support and Supervision Services for Commissioning and AcceptanceTesting for Switchgear Installations.
To:
Provide On-Site Technical Support for Commissioning and Acceptance Testing.
The pricing detail quantity has increased by 2.00 from 1.00 to 3.00.
The unit of issue has changed from Job to Each.
CLIN 0011
The unit of issue has changed from Each to Job.
CLIN 0012
The unit of issue has changed from Lot to Job.
SECTION F - DELIVERIES OR PERFORMANCE
The following Delivery Schedule item for CLIN 0005 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
31-AUG-2026 1 N/A
FOB: Destination
To:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
31-AUG-2026 3 N/A
FOB: Destination
The following Delivery Schedule item for CLIN 0006 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
31-AUG-2026 1 N/A
FOB: Destination
To:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
31-AUG-2026 3 N/A
FOB: Destination
(End of Summary of Changes)