This document is an amendment to a solicitation for the Bonneville Powerhouse 1 Main Unit Breaker (MUB) Replacement project. The amendment provides additional instructions to offerors, modifies evaluation criteria, and clarifies requirements. Key details include: the solicitation is for the design, manufacturing, and installation of custom medium voltage switchgear to replace an existing main unit breaker; proposals are due on September 25th, 2023; the award will be a firm-fixed-price construction contract determined by best value tradeoff procedures; evaluation criteria encompass past performance, preliminary design and technical approach, and small business commitment; and offerors must meet product standards including IEEE, ANSI, and ISO specifications for switchgear components and quality control processes.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is to:
1) Add Bidder Inquiry information (See Instructions to Offerors)
2) Confirm "Recency" is w ithing 12 years. (Page 7 Summary of Changes)
3) Comfirms Past Performance maximum number of pages for all projects is six (6) pages, not including CPARS or PPQs. (Page 8 Summary of Changes) See Summary of Changes for additional details.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 14
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 07-Sep-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127N23R0010
X 9B. DATED (SEE ITEM 11)
25-Aug-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Sep-2023
CODE
USACE, PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204
W9127N 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9127N23R0010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
INSTRUCTIONS TO OFFERORS
BIDDER INQUIRY INFORMATION
All inquiries regarding this solicitation are to be submitted via ProjNet-Bid at https://www.projnet.org/projnet/.
ProjNet will be closed for inquiries after the Close of Business on the twelfth business day preceding the solicitation due date. Telephone and email inquiries will not be accepted. ProjNet-Bid is a web-based program that allows offerors to post questions regarding the solicitation, and to view all questions by other offerors, and answers by the U.S. Army Corps of Engineers.
Responses to bidder inquiries will be posted to ProjNet by Close of Business on the seventh business day preceding the solicitation due date. All bidders will be held to have reviewed the questions and responses in ProjNet –Bid prior to bid submission. Nothing in the solicitation is changed unless an amendment is sent out.
The Bidder Inquiry Key for this solicitation is: 2MKAER-353TN3
To access the ProjNet-Bid website the first time:
1) Register.
2) Click Quick Add Key. (The Agency is USACE.)
3) Enter the following information for access:
The Bidder Inquiry Key for this solicitation Valid business contact information
4) Submit questions or review questions and answers. When an answer is posted to a question, the question and answer is then available for all other bidders to review. For questions about the ProjNet-Bid, access the help tab on the ProjNet website.
1. BASIS FOR AWARD.
A. General.
(1) The acquisition is being conducted using Full and Open Compe(tition using Best Value Tradeoff (BVTO) source selection procedures in accordance with FAR Part 15. The Government intends to award a single, firm-fixed-price construction contract to the responsible offeror whose proposal represents the best value to the Government after evaluation in accordance with the evaluation factors in the solicitation. The Government reserves the right to accept other than the lowest-priced offer or to reject all offers. Offerors shall submit a technical volume and a price volume. The evaluation results of the non-price and price volumes as the entire proposal will determine an awardee. All non-price factors are approximately equal in importance. All non-price evaluation factors, when combined, are significantly more important than price.
(2) The Government intends to make an award without discussions but reserves the right to conduct discussions should discussions prove to be necessary or advantageous to the Government. Because the Government does not intend to hold discussions, offerors are encouraged to include their best pricing in their initial proposal.
(3) All proposals received will stand alone and be considered complete and final. Accordingly, proposals submitted in response to this solicitation should provide clear, complete, concise, and straightforward responses to the evaluation factors. The evaluation board will not consider any information or data incorporated by reference or otherwise referred to. The successful offeror will be selected solely on the basis of the evaluation factors set forth below. Elaborate proposals, color brochures, and other excesses are discouraged. The offeror’s technical proposal will be incorporated into the awarded contract.
(4) Joint Ventures (JV). A joint venture is defined as follows: a legal business entity formed between two or more companies (parties) to undertake the performance activities of a contract together. This does not include other arrangements such as “teaming agreements” or “strategic alliances” which are not recognized as bona fide joint ventures for the purposes of this solicitation. A company that is part of a joint venture shall submit a legally binding joint venture agreement. Joint ventures shall include a copy of the legal joint venture agreement signed by an authorized officer from each of the firms comprising the joint venture with the chief executive of each entity identified. If submitting a proposal as a joint venture, the past performance of each of the joint venture partners can be submitted for the joint venture entity.
The past performance for each joint venture partner will be considered the past performance of the joint venture entity. Page and project form limits apply to the joint venture as a whole. Prospective offerors that submit proposals may not change their firm (including Letters of Commitment (LOC) and proposed subcontractors) or their Joint Venture firms, if selected to submit Final Proposal Revisions (FPR).
2. SUBMISSION OF PROPOSALS AND EVALUATION
A. Administrative Details and General Instructions: Proposals are due no later than the time and date specified in Block 09 of Standard Form 33.
(1) General Proposal Format. The proposal shall be in electronic Portable Document Format, filename extension “.pdf” and suitable for viewing in Adobe Reader. Offerors shall bookmark and label each electronic PDF to afford easy identification from the proposal table of contents.
Title Page. Each copy must include the offeror’s name and address, phone number and email address, title of the solicitation, solicitation number and date of submittal clearly identified on the front cover.
Table of Contents. Each volume of the proposal shall contain a detailed and complete table of contents.
Submissions. PDF pages containing text are expected to be 8 ½ x 11 inches with at least one-inch margins at the top, bottom, and both sides. Paragraphs should be separated by at least one blank line. A standard 11-point font in either Arial or Times New Roman is required. The use of hyperlinks in proposals is prohibited.
All information must be confined to the appropriate volume. Each volume of the proposal is expected to contain a table of contents, summary section with a brief abstract of the volume, and the narrative discussion.
(2) Proposal Content Limitations.
The offeror must confine the proposal to relevant information and documentation sufficient to provide an adequate basis for evaluation. Offerors are responsible for including sufficient details, in a concise manner, to permit a complete and accurate evaluation of the proposal. Page limitations for each of the non-price factors are listed within the individual factor descriptions.
Extraneous information provided in the proposals will not be considered in the evaluations; therefore, the offeror should only provide information that satisfies the solicitation requirements. Merely restating the specifications without sufficient elaboration demonstrates a lack of understanding of the requirement.
DO NOT cross reference past performance information. It is acceptable to repeat data, project information or experience in more than one non-price area as long as it satisfies the requirements of the factor.
Proprietary information must be clearly marked.
(3) English Language Requirement. In order for a proposal to be considered, it MUST be prepared in ENGLISH.
B. Content of Proposals: All proposals must be prepared in two volumes: A technical proposal (Volume I), a price proposal (Volume II). Each of the volumes shall be separate and complete in itself so that evaluation of one may be accomplished independently from evaluation of the other. The technical proposal (Volume I) must not contain pricing information. The narrative and content structure of the proposal shall follow the format shown under Volume I below. Offerors that fail to submit a complete proposal may be excluded and thus receive no further consideration for award.
(1) Technical Proposal, Volume I: Provide one (1) electronic proposal in Portable Document Format, filename extension “.pdf” and suitable for viewing in Adobe Reader.
Volume I shall consist of information for the three (3) factors, listed in tabular form, as noted below. Repeating or restating the specifications without sufficient elaboration will be determined to show a lack of understanding of the requirement.
Volume I – Technical (Non- Price) Factors Tab 1 – Factor 1 – Past Performance Tab 2 – Factor 2 – Preliminary Design, Data, and Information
Tab 3 – Factor 3 – Small Business Commitment Document
(2) Price Proposal, Volume II: Provide one (1) electronic proposal in Portable Document Format, filename extension “.pdf” and suitable for viewing in Adobe Reader of a complete and detailed Price Proposal on the forms provided in the solicitation. Provide pricing and complete all line items on Standard Form 33 (SF 33). The price proposal must be prepared in accordance with the following and must include:
Tab 1 – SF33, Solicitation, Offer, and Award.
The SF33 shall be filled out completely by the Offeror and signed by an official that is authorized to bind the company. The Offeror shall also acknowledge all amendments to the solicitation in accordance with the instructions on the Standard Form 30 or Block 14 of SF33.
Tab 2 – Section B Supplies or Services and Prices, Proposal Price / Bid Schedule.
The Offeror shall fully complete this section.
Tab 3 – Representations, Certifications and Other Statements of Offerors.
The Offeror shall complete all representations and certifications in Section 00 45 00 and also ensure current registration and completed/updated Annual Representations and Certifications on the System for Award Management (SAM) website, www.sam.gov.
Tab 4 – Banking and Bonding Points of Contact.
The Government is required to determine a contractor’s responsibility. Accordingly, the Offeror shall provide contact information (company name, point of contact, address, email address, and phone number) for the Offeror’s bank and bonding institutions.
Tab 5 – Bid/Offer Guarantee.
The Bid Bond shall be at least 20% of the bid price but shall not exceed $3 million. See FAR 52.228-1 – Bid Guarantee. Submit one (1) scanned copy of the completed Bid Bond, Standard Form 24. Corporate sureties must appear on the list contained in the Department of Treasury list at: https://fiscal.treasury.gov/surety-bonds/list-certified-companies.html. This item is not rated. However, the Government will review the bid bond for legal sufficiency. Any bid bond found to be legally insufficient may render an offer ineligible for award.
Tab 6 – Subcontracting Plan Must conform to Small Business Commitment Document and follow template provided as an Attachment to the Solicitation.
Tab 7 – Government Furnished Property (GFP) If the contractor’s proposal includes any of the GFP listed in Attachment 1, Government Furnished Property, the offeror shall submit the following in accordance with FAR 45.201(c):
1. A list or description of all Government property that the offeror or its subcontractors propose to use on a rent-free basis. The list shall identify the accountable contract under which the property is held and the authorization for its use (from the contracting officer having cognizance of the property);
2. The dates during which the property will be available for use (including the first, last, and all intervening months) and, for any property that will be used concurrently in performing two or more contracts, the amounts of the respective uses in sufficient detail to support prorating the rent;
3. The amount of rent that would otherwise be charged in accordance with FAR 52.245-9, Use and Charges; and
4. A description of the offeror's property management system, plan, and any customary commercial practices, voluntary consensus standards, or industry-leading practices and standards to be used by the offeror in managing Government property.
C. Submission of Proposals: Proposals are due no later than the time and date established in Block 9, SF 33. There will not be a public proposal opening.
Proposals are due no later than the time and date specified in Block 09 of Standard Form 33, or SF 30 if applicable. Proposals received after the date and time in block 09 of the solicitation will be considered late and will not be considered for award.
Offeror shall submit its proposal via email to Nicole Adams, Nicole.A.Adams@usace.army.mil, and Cory Pfenning, cory.r.pfenning@usace.army.mil.
Offerors should enter a description for every file submitted. For files over 20 megabytes (MB) the offeror shall break the file into smaller files sent via separate emails, each marked to identify which number the email is relative to the total number of emails submitted (i.e. “one of four”). Once all the emails submitted have been received, the Government will confirm receipt via return email. If an offeror submits multiple proposals, the Government will only consider the last proposal submitted prior to the due date and time.
The electronic proposal shall be in Portable Document Format, filename extension: “.pdf” and suitable for viewing in Adobe Reader. Offerors shall bookmark and label each electronic PDF to afford easy identification from the table of contents.
Do not assume submission will be instantaneous. File size and number of files submitted shall be considered. Offeror/Teammate/Subcontractors should allow adequate time for submission completion because the entire proposal (i.e. offerors submission and all teammate/subcontractor(s) independent submissions) must be received by the time and date specified in Block 09 of Standard Form 33, or SF 30 if applicable.
To avoid rejection of an offer, the offeror must make every effort to ensure its electronic submission is virus-free. Proposals, or portions thereof, submitted with the presence of a virus or which are otherwise unreadable will be treated as unreadable pursuant to FAR 15.207(c).
The requirement that an original and copy(ies) be submitted as found in block 09 of the SF33 is satisfied through the electronic submission. Additionally, electronic submission of the bid guarantee, when a bid guarantee is required, is due with the bid submission (mailing a bid guarantee is not allowed).
3. EVALUATION FACTORS
Definitions
The Government will use the following definitions when evaluating proposals:
Deficiency: A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See FAR 15.001.
Significant Strength: An aspect of an Offeror's proposal with appreciable merit or will exceed specified performance or capability requirements to the considerable advantage of the Government during contract performance.
Significant Weakness: in the proposal is a flaw that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.
Strength: An aspect of an Offeror’s proposal with merit or will exceed specified performance or capability requirements to the advantage of the Government during contract performance.
Uncertainty: is any aspect of a non-cost/price factor proposal for which the intent of the offer is unclear (e.g., more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission, or mistake).
Weakness: A flaw in the proposal that increases the risk of unsuccessful contract performance. See
FAR 15.001.
Volume I – Technical (Non-Price) Submission Requirements and Evaluation Method
FACTOR 1 – Past Performance
Submission Requirements:
Submit information* for three substantially complete projects that demonstrate the offeror’s experience performing projects similar in size, scope, and complexity to the work required by this solicitation. Each project must be completed or be substantially completed within the last twelve (12) years from solicitation issue date.
“Substantially complete” is defined as having completed the design, testing, and more than 75% of manufacturing complete at the time of proposal submission. If an offeror submits a project that it represents is “substantially complete,” the offeror must reasonably explain why the project meets the stated requirement. If an offeror submits an ongoing project without providing an accompanying reasonable explanation that explains how the project substantially complete, the Government will not evaluate the project for relevancy.
A maximum of three (3) projects will be evaluated. If an offeror disregards these instructions and submits more than three projects, only the first three projects will be evaluated. Offerors should describe each project with enough detail to ensure that the Government can meaningfully assess how well the projects submitted meet the evaluation criteria outlined below.
Instructions on the use of subcontractor past performance: Offerors may use the past performance of subcontractors. If the offeror submits past performance of a subcontractor, the offeror must submit a letter of commitment from the subcontractor on the letterhead of the firm to be subcontracted. The letter of commitment must be signed by an authorized individual from the subcontractor that is proposed to perform the work. If a letter of commitment is not submitted, the past performance will not be considered.
*For each project, submit the following information:
Information outlined in Attachment A, Offeror Experience Form. The offeror must address all items included in Attachment A. The Offeror may submit no more than two (2) pages per project, totaling a maximum of eight (8) six (6) pages. If more than two (2) pages are submitted for a project, only the first two (2) pages will be evaluated.
A completed Contractor Performance Assessment Reporting System (CPARS) evaluation, if a completed CPARS evaluation is available.
If there is not a completed CPARS evaluation, the offeror shall submit a Past Performance Questionnaire (PPQ) for the project. See Attachment B. Do not submit a PPQ when a completed CPARS is available.
o If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s).
o Offerors should follow up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Nicole Adams, via email at Nicole.A.Adams@usace.army.mil and Cory Pfenning at cory.r.pfenning@usace.army.mil, prior to proposal closing date. The offerors shall instruct the clients to refer to the solicitation number in the subject line.
o PPQs are source selection materials. All successfully submitted PPQs will receive an email confirmation upon receipt. If the offeror does not receive the confirmation, it is the offeror’s responsibility to follow up to ensure the government has received the information.
Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other procurements. However, this does not preclude the Government from utilizing previously submitted past performance information in the past performance evaluation.
Offerors may provide explanation on problems encountered on past projects, whether the project was submitted by the offeror or is a project that the offeror did not submit but for which there is a CPARS evaluation, and the corrective actions taken by the offeror.
In addition to the above, the Government may review other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the PPIRS (Past Performance Information Retrieval System) including CPARS, using all CAGE/DUNS (Commercial and Government Entity Code/Data Universal Numbering System) numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), FAPIIS (Federal Awardee Performance and Integrity Information System), Electronic Subcontract Reporting System (eSRS), or other databases, telephone interviews with organizations familiar with the offeror’s performance, Government personnel with personal knowledge of the offeror’s performance capability, and any other known sources not provided by the offeror.
Past performance information retrieved through PPIRS, CPARS, or other sources are not subject to the same evaluation criteria but will instead be reviewed for recent negative performance, trends of negative performance, and any other performance information that may negatively impact the offeror’s Confidence rating.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate, and complete past performance information rests with the offeror.
Evaluation Method:
The Government seeks a contractor who maintains a strong commitment to customer satisfaction and superior performance. It is the offeror’s responsibility to affirmatively document these qualities in the technical proposal.
The past performance evaluation results in an assessment of the offeror’s probability of meeting the solicitation requirements. The past performance evaluation considers each offeror’s demonstrated recent and relevant record of performance in supplying construction services that meet the contract’s requirements. The evaluation method that the Government will use with respect to Factor 1 – Past Performance is detailed below.
There are two (2) aspects to the past performance evaluation: 1) recency and relevancy (including context of data), and 2) quality (including general trends in contractor performance and source of information).
The first aspect is to evaluate the recency and relevancy of the offeror’s past performance. For this solicitation, recent projects are those completed or substantially completed** (as defined above) within ten (10) twelve (12) years of the date that proposals are due. The relevancy rating is not a separate proposal rating but is only used in developing overall past performance confidence assessment rating assigned to the Past Performance Factor. With respect to relevancy, past performance on projects with more relevance will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment rating than past performance on projects of lesser relevance.
There are four (4) levels of relevancy as shown in the Table below.
PAST PERFORMANCE RELEVANCY
RATING DESCRIPTION
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
In assessing the relevancy of the offeror’s past performance, the Government will consider the following:
The extent to which a submitted project involved manufacturing custom MV Switchgears.
o Examples of either type produced including electrical ratings, physical size, and specific requirements for why custom manufacturing was needed.
• Metal enclosed switchgear IEEE C37.20.2 and/or
• Metal Clad switchgear IEEE C37.20.3 Standard
The extent to which a submitted project involved manufacturing and design testing custom MV switchgear to IEEE C37.20.3 and/or IEEE C37.20.2 and ANSI C37.55 standards and/ or ANSI C37.57.
The extent to which a submitted project involved manufacturing and testing of custom 15kV Segregated phase and Isolated Phase Bus and connections
The extent to which a submitted project involved Quality Control processes such as ISO 9000, Three-step QC process, or a similar Quality Control process widely accepted in the industry.
More relevant past performance will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment than past performance of lesser relevance.
The second aspect of the past performance evaluation, quality, is to determine how well the Offeror performed on its past performance projects. If any performance issues are identified, the Government will consider the number, type and severity of the problems and effectiveness of corrective actions taken.
Based on a consideration of those two aspects for each project, the Government will assign a final Performance Confidence Assessment Rating for this factor. The Government will review the past performance information and determine the quality and usefulness as it applies to performance confidence assessment. In conducting a performance confidence assessment, each Offeror shall be assigned one of the ratings using the table below.
PERFORMANCE CONFIDENCE ASSESSMENT
RATING DESCRIPTION
Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Neutral Confidence
No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence
Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the Offeror will successfully perform the required effort.
No Confidence
Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
In the case of an offeror without a record of relevant past performance or for which information on past performance is not available, the offeror will receive a Neutral Confidence rating, which is neither favorable nor unfavorable (see FAR 15.305(a)(2)(iv).); it is considered “Neutral.” The SSA may determine that a “Substantial Confidence” or “Satisfactory Confidence” past performance rating is worth more than a “Neutral Confidence” past performance rating in a best value tradeoff as long as the determination is consistent with stated solicitation criteria.
FACTOR 2 – Technical
Offers will submit the following requirements for the MV Switchgear:
1) Preliminary Drawings and Data:
a. Scaled elevation and plan views of the switchgear outline shown in the intended location to demonstrate the offeror's clear understanding of the technical requirements and the site limitations.
b. Front view of equipment with internal one-line diagram to indicate the intended location of the disconnects, breakers, and instrument transformers.
c. Physical Dimensions from existing constraints (dimensions & configuration)
d. Bus connections and configuration details to connect to existing 15 kV Bus
e. Catalog data or otherwise tabulated data to indicate ratings for all major components to be provided to include switchgear, bus, removable circuit breakers, instrument transformers, and breaker auxiliary equipment.
f. Component’s size and ratings for the following:
i. Breaker per IEC/IEEE 62271-37-013 & IEEE C37.09
ii. MV bus per IEEE C37.23
iii. MV disconnect switch per IEEE C37.20.4
iv. Metal Enclosed or Metal Clad switchgear per ANSI C37.57
2) Narrative:
a. A description of the proposed switchgear and all components required to achieve the complete switchgear technical requirements.
b. A description of the proposed switchgear interface with the existing 15 kV bus including all components and technical details.
c. Demonstrate an understanding and intent to comply with the specification technical requirements.
Evaluation Method
The Government will rate this factor using the combined technical/risk rating as follows:
TECHNICAL RISK RATING METHOD
ADJECTIVAL RATING DESCRIPTION
Low
Proposal may contain weakness/weaknesses which have low potential to cause disruption of schedule, increased cost, or degradation of performance. Normal contractor emphasis and normal Government monitoring will likely be able to overcome any difficulties.
Moderate
Proposal contains a significant weakness or combination of weaknesses which may have a moderate potential to cause disruption of schedule, increased cost, or degradation of performance. Special contractor emphasis and close Government monitoring will likely be able to overcome difficulties.
High
Proposal contains a significant weakness or combination of weaknesses which is likely have a high potential to cause significant disruption of schedule, increased cost, or degradation of performance. Special contractor emphasis and close Government monitoring will unlikely be able to overcome any difficulties.
Unacceptable Proposal contains a or a combination of significant weaknesses that causes an unacceptable level of risk of unsuccessful performance.
FACTOR 3 – Small Business Commitment
a. The purpose of this criterion is to evaluate the offeror’s understanding of the Government’s
Small Business Program objectives (see 52.219-8,-9, & FAR 19.7) as demonstrated through the amount of work (%) proposed to be performed by all small business categories in relation to the total value of the project, the types of work small businesses will be performing (particularly major project phases – design, supply, manufacturing, installation/testing) as well as the extent of the commitment (enforceable & long-term) in using the small and
COLOR RATING DESCRIPTION
Blue Outstanding Proposal demonstrates an exceptional approach and understanding of the requirements and contains multiple strengths and/or at least one significant strength, and risk of unsuccessful performance is low.
Purple Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength or significant strength, and risk of unsuccessful performance is low to moderate.
Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Red Unacceptable
Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies and is unawardable, and/or risk of unsuccessful performance is unacceptable.
specific socioeconomic business firms identified in the proposal.
b. Other than small business Offerors will be evaluated on the level of proposed commitment to U.S. small businesses in the performance of this project relative to the objectives and goals established for the Government’s Small Business Program and required by FAR 52.219-8, as well as Offerors’ past performance in complying with the requirements of FAR 19.704 (12), FAR 19.705-7 and FAR 52.219-9, Small Business Subcontracting Plan.
c. Other than small business Offerors will be rated using the small business commitment rating method table below. NOTE: In accordance with 13 C.F.R. § 125.3(g)(3), small business offerors shall receive the maximum rating under this evaluation factor without having to submit any information in connection with this factor.
Other than small business Offerors shall submit the following:
1) Small Business Commitment Document – Complete and submit Attachment Small Business Commitment Document (SBCD), to identify the extent to which small business and all included socioeconomic categories will participate in the performance of the proposed acquisition.
2) A suggested Total Small Business Commitment goal of 5% of the total contract value
(through small business participation from small-, small disadvantaged-, HUB Zone-, Service Disabled Vet-, Vet-, or Woman-owned small businesses) Government policy is to provide maximum practicable opportunity.
3) Small Business Past Performance – Submit past performance information reflecting the
Offeror’s past level of small business participation for each project listed by the Offeror under Factor 1, Past Performance.
If the project was performed for a Federal agency, all Individual Subcontract Reports
(ISRs) and Summary Subcontract Reports (SSRs) from the Electronic Subcontracting Reporting System (eSRS) for the project.
For all other projects submitted under Factor 1, Past Performance, submit the following (totaling no more than 2 pages per submitted project in Factor 1):
(a) Name of the project and customer;
(b) Total dollar amount of the contract, total dollar value and percentage of the total contract that was self-performed;
(c) Total dollar amount and percentage of the total contract value that was subcontracted;
(d) Total dollar amount and percentage of the total contract value subcontracted to small business - indicating socioeconomic categories, if applicable
(e) Total dollar amount and percentage of the total contract value subcontracted to other than small businesses, and
4) In addition to the above project submission information, the Government reserves the right to review Offerors’ ISRs and SSRs from the eSRS.
Evaluation Method:
The Government will rate this factor using the technical rating as follows:
COLOR RATING DESCRIPTION
Blue Outstanding Proposal indicates an exceptional approach and understanding of the small business objectives.
Purple Good Proposal indicates a thorough approach and understanding of the small business objectives.
Green Acceptable Proposal indicates an adequate approach and understanding of small business objectives.
Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the small business
Red Unacceptable Proposal does not meet small business objectives.
a. The Government will consider the following:
i. The extent of the offeror’s proposed small business commitment expressed as a percentage of the total contract value.
ii. The extent to which the offeror meets or exceeds the suggested small business goal.
All goals are expressed as a percentage of the total value of the acquisition.
A suggested small business commitment goal is assigned to this acquisition for the following socioeconomic categories:
{5%} Small Business (SB)
These goals are based on Total Contract Value.
In addition to the suggested small business goal, the following goals are suggested for the individual socioeconomic categories and determined to be reasonable based on market research for this requirement. Goals are expressed as a percentage of the TOTAL contract value:
{1%} Small Disadvantaged Business {1%} Woman-Owned Small Business (WOSB) {1%} Historically Underutilized Zone (HUB Zone) Small Business {1%} Veteran Owned Small Business (VOSB) {1%} Service Disabled Veteran Owned Small Business (VOSB)
iii. The extent to which proposed small business firms, are specifically identified by name in the SBCD (DFARS 215.304(c)(1)(C)). Firms must also be listed in the subcontracting plan that is incorporated into the contract award.
iv. The extent of the commitment to use the identified small business firms (enforceable and/or long-term commitments will be considered more favorably than non- enforceable commitments). Copies of written commitments must be provided and will not count toward page limitation.
v. The complexity and variety of the work small business including all socioeconomic categories are proposed to perform (for example: work requiring specific certifications or licenses, i.e. welding, mechanical, electrical, manufacturing, supply, etc. in order to expand competitive pool - particularly major project phases – design, manufacturing, installation/testing, and demolition/removal.
vi. The extent of the offeror’s past success in complying with and demonstrating a good faith effort with the requirements of FAR 52.219-9, Small Business Subcontracting Plan, FAR Part 19.704 (12) and 19.705-7 https://www.acquisition.gov/far/subpart- 19.7#:~:text=19.705%2D7%20Compliance%20with%20the%20subcontracting%20 plan (eSRS and CPARS evaluations).
Volume II – Price
Price Evaluation
The Price Proposal will be evaluated to determine fairness and reasonableness. For evaluation purposes, the total evaluated price will be calculated by adding the total price for all optional items to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the options.
The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Procurement Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(End of Summary of Changes)