W9127822R0008 AM07.pdf
PDF 117 KB Posted
- Solicitation number
- W9127822R0008
About this file
This solicitation is for the construction of an approximately 7,000 square foot extension to Building 73 at Eglin Air Force Base in Florida. The project involves constructing a concrete foundation, split-faced concrete block structure with a steel frame and sloped standing seam metal roof to accommodate the ongoing mission of the cyberspace security test facility. Approximately 95% of the facility will be secured to SCIF standards. The work includes site work and utility connections. The NAICS code is 236220. Bids are due by the date specified in SAM.gov where all solicitation documents, plans and specifications are available for download. Registration on SAM.gov is required to receive notifications of any amendments. The critical path method is required and small businesses must have average annual receipts less than $39.5 million for the past three years. Options may be included in the award and all questions must be submitted through ProjNet as specified in the RFP.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE 4. REQUISITION/PURCHASE 5. PROJECT NO. (If applicable)
W9127822R0008-0007 01 APR 2022 MEF22002
6. ISSUED BY CODE 7. ADMINISTERED BY(If other than item 6)
CODE
Corps of Engineers 109 St. Joseph St.
Mobile, AL 36602
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP code) 9A. AMENDMENT OF SOLICITATION
NO.
W9127822R0008
9B. DATED (SEE ITEM 11)
17 DEC2021
10A. MODIFICATION OF
CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
The subject solicitation for: BUILDING 73 LAB EXPANSION, EGLIN AIR FORCE BASE, FLORIDA
Is modified in the following: REFER TO THE ENCLOSED SPECIFICATION REVISIONS FOR AMENDMENT NO. 0007.
Except as provided herein, all terms and conditions of the document reference in item 9A or 10A, as Heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICE (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of contracting officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
BUILDING 73 LAB EXPANSION W9127822R0008
EGLIN AIR FORCE BASE, FLORIDA MEF22002
SF 30 Page 2 Amendment No. 0007
PART I - REVISIONS MADE BY ADDED AND/OR REPLACEMENT PARAGRAPHS/PAGES/SECTIONS
The items listed below are to be replaced by the corresponding added and/or revised paragraphs/pages or sections. Added and/or revised paragraphs/pages or sections are indicated by a note in bottom right-hand corner of each paragraph or page. Added sections are hereby made a part of the contract and are to be inserted in the specification in the proper numerical/alphabetical sequence.
Within the specifications, deletions from the specifications are indicated by strikethrough, e.g.: deletions are marked with strikethrough and additions to the specifications including revisions/substitutions are indicated in bold, italic and underlined, e.g.: additions are indicated thus.
Corresponding Added or Revised Paragraph SECTION Page, and/or Section
VOLUME 1
Bidding Schedule Revised Bid Items 3 and 4 as indicated herein.
Encl as stated:
Revised pages of the specifications as indicated in Part I.
Bid Schedule page - 1 Revised by Amendment No. 0007
BIDDING SCHEDULE
BIDDER'S NAME:_______________________________________________________________
Item Estimated Unit Estimated No. Description Quantity Unit Price Amount___
Base Bid
1 Construction of New Facility Addition and Alterations 1 Job XXX ___________
2 Construction of Site Work 1 Job XXX ___________
3 Privatized Utility Authority (ASUS) Water and Wastewater $137,040.00 Work 1 Job XXX $182,013.00
4 Privatized Utility Authority (CHELCO) Site Electrical $136,110.00 Work 1 Job XXX $189,865.00
Total Base Bid ___________
Bid Option No. 1
5 Material Lift 1 Job XXX ___________
Bid Option No. 2
6 Bridge Crane and Hoist 1 Job XXX ___________
Total Base Bid Plus Options 1 & 2 ___________
Bid Schedule page - 2 Revised by Amendment No. 0007
NOTES FOR BIDDING SCHEDULE
NOTE NO. 1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest bid schedules as published in the solicitation or the latest amendment thereto.
In lieu of indicating additions/deductions to contract line items, bidder should state the revised prices for each item. The company name should be indicated on the face of the bidding schedule to preclude being misplaced.
NOTE NO. 2. Bidders must insert a price on all numbered items of the Bidding Schedule. Failure to do so will disqualify the bid.
NOTE NO. 3. If a modification to a bid is submitted and provides for a job adjustment to the total estimated cost, the application of the job adjustment to each unit price and/or job price, in the bid schedule must be stated or, if it is not stated, the bidder agrees that the job adjustment shall be applied on a pro rata basis to every bid item in the bid schedule.
NOTE NO. 4. CONDITIONS GOVERNING EVALUATION OF BIDS AND AWARD OF CONTRACT.
Only one contract will be awarded on this Bid Schedule and award will be made on the Base Bid and selected Options, in accordance with the paragraph entitled Evaluation of Options (JUL 1990) in Section 00 21 16: INSTRUCTIONS TO PROPOSERS. Award will be made according to the "Best Value" approach as defined in Section 00 12 00: SELECTION PROCEDURES AND BASIS OF AWARD.
The Government may require the delivery of the numbered line items, identified in the schedule as option items, in the quantity and at the price stated in the schedule. Subject to the availability of funds, the Contracting Officer may exercise Bid Options No. 1 and 2 by written notice to the Contractor within 120 days of Notice to Proceed.
END OF BIDDING SCHEDULE