This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a federal solicitation (W9126G25RA043). The amendment provides clarifications to six contractor questions about proposal submission requirements, including guidance on Past Performance Questionnaires (PPQs), page count exclusions, and joint venture submission requirements. Key clarifications include: CPARS evaluations can be used in lieu of PPQs where available, Attachment 1 Data Sheet and Representations and Certifications are not included in page count, and joint venture submissions must comply with 13 C.F.R. 125.8. Contractors are also instructed to submit a complete copy of the original RFP (less attachments) with their proposal, which is not counted in the page limit. The amendment maintains the original offer due date.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised Attachment 3 - Seed Project SOW - CLIN 0001-0002.pdf | ||
| Attachment 11 Amend 0004 Block 14 Continued.pdf | ||
| Revised Attachment 7 - Seed Project Requirements.pdf | ||
| Solicitation Amendment W9126G25RA0430004 SF 30.pdf | ||
| Solicitation Amendment W9126G25RA0430003 SF 30.pdf | ||
| Attachment 10 Trinity Construction MATOC Site Visit.pdf | ||
| Solicitation Amendment W9126G25RA0430002 SF 30.pdf | ||
| Solicitation Amendment W9126G25RA0430001 SF 30.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Purpose of this Amendment is to answer the Block 14 (Description of Amendment/Modification):
following contractor questions regarding proposal submission:
1. Q: Can the Government Please Clarify if a Proposal must include a PPQ, when there is a CPARS available?
A: As per 00 21 16, Paragraph 3.2 - "CPARS evaluations shall be used in lieu of PPQs where CPARS evaluations are available for the submitted project." This means that PPQs would not be submitted where CPARS are available.
2. Q: Can the Government Please Clarify if the Attachment 1 Data Sheet is included in the page count?
A: No, Attachment 1 Data Sheet is not included in the page count.
3. Q: Can the Government Please Clarify their response to question #7 in Amendment 4? Please definitively state if a written certification to the Contracting Officer and SBA is required along with a signed copy of the JV Agreement?
A: Joint Venture submissions must be fully compliant with 13 C.F.R. 125.8. The joint venture certification specified in the C.F.R. is required with proposal submission.
4. Q: Can the Government please confirm that Representations and Certifications are not included in Page Count?
A: Representations and Certifications are not included in the Page Count.
5. Q: The Original RFP on PDF Page 13 of 299 states "Include the following data in this volume in the format indicated. Section 2 A complete copy of this RFP (Division 00, less attachments)". Can the Government please clarify if they are wanting us to provide an actual copy of the original RFP with its proposal submission?
A: Yes, (less attachments). Submit as specified.
6. Q: Can the Government please clarify if the complete copy of the RFP is included in page count?
A: No, not included in the page count.
No change in offer due date.
W9126G25RA0430005
| IDCode: J |
| Page: 1 |
| Pages: 2 |
| AmendNo: 0005 |
| EffDate: 27 AUG 2025 |
| ReqNo: |
| ProjNo: 513638 |
| IssCode: W9126G |
| AdmCode: |
| IssuedBy: W076 ENDIST FT WORTH |
KO CONTRACTING DIVISION, 819 TAYLOR ST BOX 17300
FORT WORTH, TX 76102-6124
UNITED STATES
GARY RIZZOLO, EMAIL: GARY.S.RIZZOLO@USACE.ARMY.MIL TELEPHONE: (816) 389-3853
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W9126G25RA043 |
| SolDate: 29 JUL 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: SEE SCHEDULE |
| ContNameTitle: |
| CoNameTitle: MICHAEL A. VEGA |
| ContDate: |
| CODate: 28 AUG 2025 |