Revised Attachment 3 - Seed Project SOW - CLIN 0001-0002.pdf

PDF 2 MB Posted

Attached to
Solicitation for W9126G25RA043 with Amendments Federal contract opportunity
Solicitation number
W9126G25RA043
Issued by
Department of the Army Corps of Engineers Engineering District Fort Worth

About this file

This Statement of Work (SOW) details two separate contract line items (CLINs) for the U.S. Army Corps of Engineers at Lewisville Lake in Texas:

CLIN 0001 involves replacing parking lot and flagpole lighting at the Lewisville Project Office. The project requires removing 27 existing parking lot light fixtures and 2 flagpole lights, and installing new LED lighting fixtures compatible with existing poles. The work includes new photoelectric sensors, updated cabling, and ensuring compliance with energy efficiency and electrical standards. The contractor must complete all work within 30 calendar days from the Notice to Proceed, with deliverables including a fully operational lighting system, as-built wiring diagrams, and a final inspection report.

CLIN 0002 focuses on constructing an RV Dump Station at Hickory Creek Park, involving infrastructure for wastewater management. The project requires designing and installing a 3,000-gallon holding tank, an aeration treatment system, and a spray field for effluent disposal. The work must accommodate the park's 124 RV sites, with an estimated 67% annual occupancy and potential peak exodus of 80+ RVs after holiday weekends. The performance period is 120 calendar days, with 30 days for design and permitting, 60 days for construction, and 30 days for commissioning and final inspection.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W9126G15RA043

CLIN 0001 Statement of Work

Statement of Work (SOW)

CLIN 0001 - Parking Lot and Flagpole Lighting Replacement Location:

Date: FY2025

1. Objective

2. Scope of Work

2.1 Removal and Disposal

o o on o

2.2 Installation

o -o -of o All associated cabling o Eight (8) new photoelectric sensor (photo eye) -to-

-501-

-1- -

4. Deliverables s feet

As-

5. Period of Performance

30 calendar days

6. Government-

7. Acceptance Criteria

-to-

8. SAFETY REQUIREMENTS

-1-

9. QUALITY CONTROL AND ASSURANCE

10. POINTS OF CONTACT

- A

-1161

-9107

11.0 SUBMITTALS

As-

END OF STATEMENT OF WORK

CLIN 0001 – Lewisville Lake Office Parking Lot Lights Replacement

W9126G25RA043

Revised CLIN 0002 Statement of Work 25 Aug 2025

CLIN 0002: Hickory Creek Park Recreational Vehicle (RV) Dump Station with Holding Tank, Aeration Treatment, and Spray Field Location: Lewisville Lake, Hickory Creek Park, Hickory Creek, Texas

1. Objective

The objective of this project is to design, permit, construct, and commission a fully functional RV Dump Station infrastructure including wastewater storage, treatment, and land application systems in compliance with all local, state, and federal environmental regulations, regulations, to handle flow rates vary based on occupancy rates and departures. The campground has 124 RV sites. The average stay is about 3 days per RV site. The average capacity is around 67% full annually with holiday and weekends close to or at full capacity. The peak exodus of RV sites was at 80+ sites leaving on a single day after a holiday weekend with an additional 40-50 sites leaving within the next few days.

2. Scope of Work

The Contractor shall provide all labor, materials, equipment, and professional services necessary to complete the following components:

2.1 Dump Station Infrastructure

Modify and Construct a reinforced concrete pad with appropriate grading and 2 wastewater drain inlet.

Install inlet plumbing connections with freeze-proof hose bibbs for vehicle discharge.

Provide and install an odor control vent system (optional, pending design).

Install all required signage indicating usage instructions, safety precautions, and restrictions.

Install protective bollards around the dump pad to prevent vehicle damage.

2.2 Underground Holding Tank

Provide and install a polyethylene wastewater holding tank with a minimum capacity of 3,000 gallons.

Install access risers and lockable, tamper-resistant lids at grade level.

Equip the tank with a level monitoring system or alarm to notify when pump-out is required.

2.3 Aeration Treatment System

Design and install a compact aeration treatment system or a small-scale packaged treatment plant.

Provide necessary pumps, blowers, air diƯusers, and associated electrical service.

Incorporate chlorination/dechlorination features if required by regulatory agencies.

Install new exterior electrical panel at treatment location with power source that comes from the main electric panel located at the restroom building.

2.4 Spray Field

Construct a surface or subsurface spray field for eƯluent disposal, including:

o Distribution piping, spray nozzles or sprinklers.

o Valve boxes and flow control mechanisms.

o Establishment of a buƯer zone.

Implement a flow monitoring system or soil percolation monitoring components to verify disposal capacity.

2.5 Permitting and Professional Services

Provide qualified environmental engineering services or licensed wastewater system designer.

Conduct a soil evaluation and percolation test to determine spray field suitability.

Prepare and submit all required documents to obtain permits from local and state environmental regulatory bodies.

Maintain compliance with all applicable environmental protection, public health, and land use regulations.

3. Deliverables

Design Documents: Detailed site plan, plumbing and electrical schematics, equipment specs.

Permits: All required permits, including wastewater discharge authorization.

As-Built Drawings: Final site and utility layout upon project completion.

Operation Manual: For holding tank monitoring, treatment system operation, and spray field maintenance.

Training: Provide basic operational training to designated personnel.

4. Period of Performance

Estimated performance period is 120 calendar days from Notice to Proceed. Schedule shall include:

30 days – Design and Permitting

60 days – Construction

30 days – Commissioning and Final Inspection

5. Government Furnished Property (GFP)

• Access to the facility during regular business hours

• Location of existing electrical panels and circuits

6. Special Considerations

All work must comply with environmental protection regulations.

Worksite safety, traƯic control, and erosion prevention are the responsibility of the contractor.

Contractor must coordinate with utility providers for service installation and inspections.

7. Safety Requirement

Submit and obtain approval of a Site-Specific Safety Plan (SSSP) in accordance with EM 385-1-1 prior to mobilization

Comply with all safety reporting and inspection requirements

8. Quality Control and Assurance

Submit a Contractor Quality Control Plan (CQCP)

Work subject to inspection by the USACE QAR

Deficiencies must be corrected within 5 business days

9. Points of Contact

Contracting OƯicer: Michael Vega, E-mail:michael.a.vega@usace.army.mil

Phone: (817) 886-1161

COR/Lake Manager Kenneth Myers

E-mail: Kenneth.D.Myers@usace.army.mil

Phone: (469) 645-9107

10. Attachments

Attachment A: Product Cut Sheets (to be submitted)

Attachment B: As-Built Markups (upon completion)

11. Layout Photos

Hickory Creek RV Dump Station

A-1 Map – Existing Electrical Utility and Sewer

END OF STATEMENT OF WORK

Existing Holding tank and liftstation

Proposed Sprayfield area

Proposed holding tank/treatment area

Hickory Creek Park RV Dump Station

MAP A-1, REVISED CLIN 0002 SOW – Existing Electrical Utilities and Sewer

CLIN 0001 Lewisville lights site map.pdf
Slide Number 1
CLIN 00002 HC RV Dump Station site map.pdf
Slide Number 1