AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The Solicitation for Simulations Center, Mission Training Complex (MTC); Fort Hood, Texas is amended as follows:
See SF30 Continuation Sheet(s)
NOTE: Proposal Receipt date has remained the same, 21 March 2017, at 2:00 p.m. Central Time.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
W9126G-17-R-0008
X 9B. DATED (SEE ITEM 11)
16-Mar-2017
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended,X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Mar-2017
CODE
US ARMY ENGINEER DISTRICT, FORT WORTH
ATTN: CESWF-CT
819 TAYLOR ST, ROOM 2A19
P.O. BOX 17300
FORT WORTH TX 76102-0300
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL: TEL:
W9126G-17-R-0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
CHANGES TO THE SPECIFICATIONS
1. New Sections - Add the following accompanying new sections.
01 45 00.15 10 – RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS)
2. Replacement Sections - Replace the following sections with the accompanying new sections of the same number and title:
01 91 00.00 40 - COMMISSIONING
10 14 00.20 – SIGNAGE
10 22 39 – FOLDING PANEL PARTITIONS
27 51 16 – RADIO AND PUBLIC ADDRESS SYSTEMS
31 63 26 – DRILLED CAISSONS
32 31 13.53 – CHAIN LINK FENCES AND GATES
CHANGES TO THE DRAWINGS
3. Replacement Drawings.- Replace the drawings listed below with the attached new drawings(s) of the same number:
AE102 - PARTIAL FLOOR PLAN - AREA 'A'
AE108 - PARTIAL FLOOR PLAN - AREA 'G'
AE109 - PARTIAL FLOOR PLAN - AREA 'H'
CG501 - DRAINAGE DETAILS
CI104 - SITE IMPROVEMENT PLAN
ES100 - ELECTRICAL SITE DEMOLITION PLAN
ES101 - PARTIAL ELECTRICAL SITE PLAN - AREA A
F-001 - FIRE PROTECTION LEGEND
FP-111 - PARTIAL FLOOR PLAN - AREA 'L'
FP-112 - PARTIAL FLOOR PLAN - AREA 'M'
IF-103 - PARTIAL FURNITURE AND SIGNAGE PLAN -
AREA 'B'
MP-109 - PARTIAL FLOOR PLAN - AREA 'J'
MP-112 - PARTIAL FLOOR PLAN - AREA 'M'
SF-114 - PARTIAL ROOF FRAMING PLAN - AREA 'P'
T-503 - TELECOM DETAILS
T-702 - SIPR RISER DIAGRAM
TY001 - SYSTEMS LEGEND, NOTES AND ABBREVIATION
TY101 - SECURITY PARTIAL FLOOR PLAN - AREA A
TY109 - SECURITY PARTIAL FLOOR PLAN - AREA J
TY111 - SECURITY PARTIAL FLOOR PLAN - AREA L
TY112 - SECURITY PARTIAL FLOOR PLAN - AREA M
End of Summary of Changes
Simulations Center, Mission Training Complex (MTC) 5650RBDSIGNAMEND
01 91 00.00 40
COMMISSIONING
11/12
PART 1 GENERAL
The requirements of this Section apply to, and are a component part of, each section of the specifications.
This Section includes:
a. Building commissioning of the following systems:
(1) HVAC components and equipment
(2) HVAC system: interaction of cooling, heating, and comfort delivery systems
(3) Building Automation System (BAS): control hardware and software, sequence of operations, and integration of factory controls with
BAS
(4) Lighting Control System and interface with daylighting
(5) Domestic Plumbing hot water systems, plumbing systems, domestic water pumping systems
(6) Renewable energy generation systems
(7) Building envelope air tightness
(8) Building envelope thermal/moisture
b. Building commissioning activities and documentation in support of the U.S. Green Building Council (USGBC) LEED BD+C™ rating program include the "Energy and Atmosphere" prerequisite of "Fundamental Building Systems Commissioning."
c. Building acceptance testing indicated in ASHRAE 189.1 -2011 Section 10.3.1.1
The Government, or Commissioning Agent are not responsible for construction means, methods, job safety, or management function related to commissioning on the job site.
The commissioning process does not take away from or reduce the responsibility of the system designers or installing contractors to provide a finished and fully functioning product.
The following Sections are an integral part of this project Commissioning:
a. Section 01 33 00 SUBMITTAL PROCEDURES
b. Section 01 33 29 SUSTAINABILITY REPORTING
c. Section 01 45 00.00 10 QUALITY CONTROL
SECTION 01 91 00.00 40 Page 1
d. Section 01 78 23 OPERATION AND MAINTENANCE DATA
e. Section 22 00 00 PLUMBING, GENERAL PURPOSE
f. Section 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST
SYSTEMS
g. Section 23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 189.1 (2011) Standard for the Design of High-Performance Green Buildings Except Low-Rise Residential Buildings
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED BD+C (2009; R 2010) Leadership in Energy and Environmental Design(tm) Building Design and Construction (LEED-NC)
LEED GBDC Ref Guide (2009; R 2010) LEED Reference Guide for Green Building Design, Construction and Major Renovations of Commercial and Institutional Buildings including Core & Shell and K-12 Projects
1.2 DEFINITIONS
a. Basis of Design - The basis of design is the documentation of the primary thought processes and assumptions behind design decisions that were made to meet the Project Requirements. The basis of design describes the systems, components, conditions and methods chosen to meet the intent. Some reiterating of the Project Requirements may be included.
b. Commissioning - Commissioning is a comprehensive and systematic process to verify that the building systems perform as designed to meet the requirements. Commissioning during the construction, acceptance, and warranty phases intends to achieve the following specific objectives:
(1) Verify and document that equipment is installed and started per manufacturer's recommendations, industry accepted minimum standards, and the Contract Documents.
(2) Verify and document that equipment and systems receive complete operational checkout by the installing contractors.
(3) Verify and document equipment and system performance.
(4) Verify the completeness of Operations and Maintenance materials.
SECTION 01 91 00.00 40 Page 2
(5) Ensure that the operating personnel are adequately trained on the operation and maintenance of the building equipment.
c. Commissioning Agent - develops the functional test procedures in a sequential written form, coordinates, oversees and documents the actual testing, which is usually performed by the installing contractor or vendor. Functional Performance Tests are performed after pre-functional checklists and startup are complete.
d. Commissioning Plan - an overall plan that provides the structure, schedule and coordination planning for the commissioning process.
e. Deficiency - a condition in the installation or function of a component, piece of equipment or system that is not in compliance with the Contract Documents, does not perform properly, or is not complying with the Project Requirements.
f. Project Requirements - a dynamic document that provides the explanation of the ideas, concepts and criteria that are considered to be very important to the Government. It is initially the outcome of the programming and conceptual design phases.
g. Functional Performance Test - test of the dynamic function and operation of equipment and systems using manual (direct observation) or monitoring methods. Functional testing is the dynamic testing of systems (rather than just components) under full operation (e.g., the chiller pump is tested interactively with the chiller functions to see if the pump ramps up and down to maintain the differential pressure setpoint). Systems are tested under various modes, such as during low cooling or heating loads, high loads, component failures, unoccupied, varying outside air temperatures, fire alarm, power failure, etc. The systems are run through all the control system's sequences of operation and components are verified to be responding as the sequences state. Traditional air or water test and balancing (TAB) is not functional testing, in the commissioning sense of the word.
h. Manual Test - using hand-held instruments, immediate control system readouts or direct observation to verify performance (contrasted to analyzing monitored data taken over time to make the "observation").
i. Monitoring - the recording of parameters (flow, current, status, pressure, etc.) of equipment operation using data loggers or the trending capabilities of control systems.
j. Pre-functional Checklist - a list of items to inspect and elementary component tests to conduct to verify proper installation of equipment, provided by the Commissioning Agent to the contractor. Pre-functional checklists are primarily static inspections and procedures to prepare the equipment or system for initial operation (e.g., belt tension, oil levels OK, labels affixed, gages in place, sensors calibrated, etc.).
However, some pre-functional checklist items entail simple testing of the function of a component, a piece of equipment or system (such as measuring the voltage imbalance on a three-phase pump motor of a chiller system). The word "pre-functional" refers to before functional testing. Pre-functional checklists augment and are combined with the manufacturer's start-up checklist.
k. Seasonal Performance Tests - Functional Performance Test that are
SECTION 01 91 00.00 40 Page 3 deferred until the system(s) will experience conditions closer to their design conditions.
l. Warranty Period - warranty period for entire project, including equipment components. Warranty begins at Substantial Completion and extends for at least one year, unless specifically noted otherwise in the Contract Documents and accepted submittals.
1.3 ADMINISTRATIVE REQUIREMENTS
Perform commissioning services for the system. Expedite the testing process and minimize unnecessary delays, while not compromising the integrity of the procedures. The commissioning requires cooperation of the Contractor, subcontractors, vendors, Commissioning Agent, and Contracting Officer.
1.3.1 Co-ordination
The Contractor shall provide a Commissioning Agent (CA) employ the services of an independent Commissioning Firm for overall co-ordination and management of the commissioning program. The Cx Agent shall report directly to the Government. The CA shall be an independent contractor and not an employee or subcontractor of the Contractor or any other subcontractor on this project, including the design professionals (i.e.
the DOR or their firm(s)) and shall report directly to the Government.
The Commissioning Firm must be a first tier subcontractor of the General or Prime Contractor and must be financially and corporately independent of all other contractors. The Commissioning Firm must employ a Lead Commissioning Specialist that coordinates all aspects of the commissioning process. The Lead Commissioning Specialist must have direct communication with the Government regarding all elements of the commissioning process.
The commissioning team comprises the following groups:
a. Contractor's Project Manger and Test Engineer
b. Sub-contractor for the system being commissioned
c. Commissioning Agents Project Manager and Project Engineers
d. Contracting Officers Representative
e. Architect/Engineer and Specialty Consultant
1.3.2 Progress Meetings
Plan and co-ordinate meetings as required to monitor construction and commissioning progress the work. Notify the Contracting Officer of construction job-site meetings to address co-ordination, deficiency resolution and planning issues.
1.3.3 Functional Testing Co-ordination
Do not "temporarily" start equipment for commissioning. Do not conduct functional performance testing until a pre-functional, start-up and TAB is completed for a given system. Do not functionally test the controls system and equipment it controls until all points have been calibrated and the pre-functional checklists are completed.
SECTION 01 91 00.00 40 Page 4
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Commissioning Plan; G
Commissioning Schedule; G
SD-05 Design Data
Basis of Design; G
SD-06 Test Reports
Functional Performance Testing Results; G
Deficiency Report and Resolution Record; G
SD-07 Certificates
Commissioning Agents Qualifications; G
SD-10 Operation and Maintenance Data
Operations and Maintenance Manuals; G
Training Plan; G
Operations and Maintenance Database; G
SD-11 Closeout Submittals
Final Commissioning Report; G
LEED™ Documentation; G
1.5 QUALITY CONTROL
Commissioning Agents Qualifications: Engage commissioning service personnel that specialize in the types of inspections and tests to be performed.
Inspection and testing service agencies are members of the Building Commissioning Association (BCA).
1.6 DESIGN REVIEW AND DOCUMENTATION
Document basis of design and Project Requirements as they relate to environmentally responsive characteristics, including:
a. Functionality
SECTION 01 91 00.00 40 Page 5
b. Energy performance
c. Water efficiency
d. Maintainability
e. System cost
f. Indoor environmental quality
g. Local environmental impacts
Review design documents to verify that each commissioned system meets the Project Requirements and LEED GBDC Ref Guide for new construction.
Review construction documents to verify that commissioning is adequately specified, that each commissioned system can be commissioned and is likely to meet the Project Requirements.
PART 2 PRODUCTS
2.1 TEST EQUIPMENT
Ensure instrumentation used for testing meets the following standards:
a. Sufficient quality and accuracy to test and measure system performance within the tolerances required to determine adequate performance.
b. Calibrated on the manufacturer's recommended intervals with calibration tags permanently affixed to the instrument being used.
c. Maintained in good repair and operating condition throughout the duration of use on this project.
Provide all standard testing equipment required for performing startup and initial checkout and required functional performance testing for the system. Datalogging equipment or software required to test equipment will be provided by the Commissioning Agent, and not become the property of the Government.
2.1.1 Commissioning Plan
Develop a commissioning plan to identify how commissioning activities will be integrated into general construction and trade activities. The commissioning plan identifies how commissioning responsibilities are distributed. The intent of this plan is to evoke questions, expose issues, and resolve them with input from the entire commissioning team early in construction.
The Plan identifies who is responsible for producing the various procedures, reports, forms, and notifications. It will include the commissioning schedule and describe the test/acceptance procedure.
2.2 START-UP/PRE-FUNCTIONAL CHECKLISTS
Coordinate start-up plans and documentation formats, including pre-functional checklists to be completed during the startup process.
Manufacturer's start-up checklists and other technical documentation
SECTION 01 91 00.00 40 Page 6 guidelines can be used as the basis for pre-functional checklists.
PART 3 EXECUTION
3.1 COMMISSIONING PROCESS
The Commissioning Agent coordinates all activities. The following activities outline the commissioning tasks and the general order in which they occur.
a. Design Review and documentation consisting of:
(1) Documentation of Basis of Design and Project Requirements
(2) Design Development Review
(3) Construction Document Review
b. Commissioning Scoping Meeting
c. Commissioning Plan
d. Submittals Review
e. Start-Up/Pre-Functional Checklists
f. Functional Performance Testing
g. Short-Term Diagnostic Testing
h. Deficiency Report and Resolution Record
i. Operations and Maintenance Training
j. Record Documents Review
k. Final Commissioning Report and LEED™ Documentation
l. Deferred testing due to unforeseen deferred tests.
3.2 FUNCTIONAL PERFORMANCE TESTING
Fully describe system test procedures identifying configuration and steps required for each test. Provide appropriate documents so that another party can repeat the tests with virtually identical results.
Submit documentation to the Contracting Officer verifying conformance with the following standards:
3.2.1 Functional Performance Test Procedures
Develop functional performance test procedures for equipment and systems.
Identify specific test procedures and forms to verify and document proper operation of each piece of equipment and system. Coordinate test procedures with the contractor for feasibility, safety, equipment and warranty protection.
Include the following information on the functional performance test forms:
SECTION 01 91 00.00 40 Page 7
a. System and equipment or component name(s)
b. Equipment location and ID number
c. Date
d. Project name
e. Participating parties
f. Instructions for setting up the test, including special cautions, alarm limits, etc.
g. Specific step-by-step procedures to execute the test
h. Acceptance criteria of proper performance with a Yes / No check box
i. Comment section
3.2.2 Test Methods
Methods for functional performance testing and verification include direct manipulation of system inputs (i.e. heating or cooling sensors), manipulation of system inputs with the building automation system (i.e.
software override of sensor inputs), trend logs of system inputs and outputs using the building automation system, or short-term monitoring of system inputs and outputs using stand alone data loggers. The Commissioning Agent determines which method, or combination of methods, is most appropriate.
3.2.3 Setup
Perform each test procedure under conditions that simulate normal operating conditions as closely as possible. Where equipment requires integral safety devices to stop/prevent equipment operation unless minimum safety standards or conditions are met, have functional performance test procedures demonstrate the actual performance of safety shutoffs in a real or closely-simulated conditions of failure.
3.2.4 Sampling
The Commissioning Agent develops a sampling strategy when multiple identical pieces of non-life-safety or non-critical equipment may be functionally tested. If, after three test attempts at testing the specified sample percentage, failures are still present, then test all remaining units at the contractors' expense.
3.2.5 Functional Performance Testing Results
Coordinate, observe and record the results of the functional performance testing. Coordinate retesting as necessary until satisfactory performance is verified. Verify the intended operation of individual components and system interactions under various conditions and modes of operation.
3.3 DEFICIENCY REPORT AND RESOLUTION RECORD
Document items of non-compliance in materials, installation or operation.
SECTION 01 91 00.00 40 Page 8
3.3.1 Non-Conformance
Immediately address observed non-conformance and deficiencies in terms of notification to responsible parties, and provide recommended actions to correct deficiencies.
Corrections of minor deficiencies identified may be made during the tests at the discretion of the Commissioning Agent. In such cases document the deficiency and resolution on the procedure form.
3.3.1.1 Identified Deficiencies Correction Procedure
If there is no dispute on the deficiency and the responsibility to correct it:
a. The Commissioning Agent documents the deficiency and the adjustments or alterations required to correct it. The Contractor corrects the deficiency and notifies the Commissioning Agent that the equipment is ready to be retested.
b. The Commissioning Agent reschedules the test and the test is repeated.
If there is a dispute about a deficiency or who is responsible:
a. The deficiency is documented on the non-compliance form and a copy given to the Contracting Officer's representative.
b. Resolutions are made at the lowest management level possible.
Additional parties are brought into the discussions as needed.
Contractor has responsibility for resolving construction deficiencies. If a design revision is deemed necessary and approved by the Contracting Officer, the Contractor has responsibility for providing a design revision.
c. The Commissioning Agent documents the resolution process.
d. Once the interpretation and resolution have been decided, the appropriate party corrects the deficiency and notifies the Commissioning Agent that the equipment is ready to be retested. The Commissioning Agent reschedules the test and the test is repeated until satisfactory performance is achieved.
The Contractor is responsible for retesting costs.
3.4 OPERATIONS AND MAINTENANCE TRAINING
The Contractor shall provide complete operations and maintenance manuals, a training plan and an operations and maintenance database.
Coordinate and review with the Contracting Officers' representative the training program for O&M personnel.
Develop the database from the O&M manual containing the information required to start a preventative maintenance program.
Provide additional materials as necessary to stress and enhance the importance of system interactions, troubleshooting, and long-term preventative maintenance and operation.
SECTION 01 91 00.00 40 Page 9
3.5 FINAL COMMISSIONING REPORT AND LEED™ DOCUMENTATION
Compile and submit a Final Commissioning Report. Summarize all of the tasks, findings, conclusions, and recommendations of the commissioning process.
Compile and submit LEED™ Documentation. Format as required by USGBC for submittal under the referenced green building rating system.
3.6 DEFERRED TESTING
3.6.1 Unforeseen Deferred Tests
If a test cannot be completed due to the building structure, required occupancy condition, or other deficiency, the functional testing may be delayed upon recommendation of the Commissioning Agent and the approval of the Contracting Officer. Conduct these tests in the same manner as the seasonal tests as soon as possible.
3.6.2 Deferred Tests
Schedule, coordinate, observe, and document additional testing for seasonal variation in operations and control strategies during the opposite season to verify performance of the system and controls.
Complete testing during the warranty period to fully test all sequences of operation.
3.6.3 End-of-Warranty Review
Conduct end of warranty review prior to the end of the warranty period.
Review the current building operation with the facility maintenance staff. Include in the review all outstanding issues from original or seasonal testing. Interview facility staff to identify concerns with building operation. Provide suggestions for improvements and assist Contracting Officer in developing reports or documentation to remedy problems.
Update O&M manuals and Record Documents as necessary due to the testing.
3.7 EQUIPMENT AND SYSTEM SCHEDULE
Commission the following equipment in this project.
System Equipment Check
HVAC Systems Variable frequency drives
Packaged Rooftop Units
DX Split Systems
VAV Terminal units
Unit heaters
Computer Room Air Conditioners
SECTION 01 91 00.00 40 Page 10
System Equipment Check
Exhaust fans
Chiller
Boilers
Pumps
Lighting Controls Day light dimming controls
Lighting occupancy sensors
BAS System
Domestic Hot Water Systems Hot water heaters
Recirculating pump
Plumbing Systems Booster pumps
Building Envelope Air tightness
Renewable Energy Photovoltaics
-- End of Section --
SECTION 01 91 00.00 40 Page 11
SECTION 10 14 00.20
SIGNAGE
11/12
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
ALUMINUM ASSOCIATION (AA)
AA DAF45 (2003; Reaffirmed 2009) Designation System for Aluminum Finishes
AA PK-1 (2009) Pink Sheets: Designations and Chemical Composition Limits for Aluminum Alloys in the Form of Castings & Ingot
AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA)
AAMA 2604 (2010) Voluntary Specification, Performance Requirements and Test Procedures for High Performance Organic Coatings on Aluminum Extrusions and Panels
AMERICAN WELDING SOCIETY (AWS)
AWS D1.2/D1.2M (2014) Structural Welding Code - Aluminum
ASTM INTERNATIONAL (ASTM)
ASTM B209 (2014) Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate
ASTM B221 (2014) Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
36 CFR 1191 Americans with Disabilities Act (ADA) Accessibility Guidelines for Buildings and Facilities; Architectural Barriers Act (ABA) Accessibility Guidelines
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in
SECTION 10 14 00.20 Page 1 accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Detail Drawings; G
SD-03 Product Data
Installation; G Warranty; G
SD-04 Samples
Signage; G Software; G
SD-10 Operation and Maintenance Data
Approved Manufacturer's Instructions; G Protection and Cleaning; G
1.3 EXTRA MATERIALS
Provide 20 extra frames and extra stock of the following: Changeable message strips for sign type A4 or A5. Provide paper inserts and one copy of the software for user produced signs and inserts after project completion and equipment necessary for removal of signage parts and pieces.
1.4 QUALITY ASSURANCE
1.4.1 Samples
Submit interior signage samples of each of the following sign types showing typical quality, workmanship and color: Directional sign, Standard Room sign, Changeable message strip sign. The samples may be installed in the work, provided each sample is identified and location recorded.
1.4.2 Detail Drawings
Submit detail drawings showing elevations of each type of sign, dimensions, details and methods of mounting or anchoring, mounting height, shape and thickness of materials, and details of construction. Include a schedule showing the location, each sign type, and message.
1.5 DELIVERY, STORAGE, AND HANDLING
Materials shall be packaged to prevent damage and deterioration during shipment, handling, storage and installation. Product shall be delivered to the jobsite in manufacturer's original packaging and stored in a clean, dry area in accordance with manufacturer's instructions.
1.6 WARRANTY
Warrant the signage for a period of 2 years against defective workmanship and material. Warranties shall be signed by the authorized representative of the manufacturer. Submit warranty accompanied by the document authenticating the signer as an authorized representative of the guarantor. Guarantee that the signage products and the installation are free from any defects in material and workmanship from the date of
SECTION 10 14 00.20 Page 2 delivery.
PART 2 PRODUCTS
2.1 STANDARD PRODUCTS
Signs, plaques, directories, and dimensional letters shall be the standard product of a manufacturer regularly engaged in the manufacture of such products that essentially duplicate signs that have been in satisfactory use at least 2 years prior to bid opening. Obtain signage from a single manufacturer with edges and corners of finished letterforms and graphics true and clean.
2.2 ROOM IDENTIFICATION/DIRECTIONAL SIGNAGE SYSTEM
2.2.1 Standard Room Signs
Signs shall consist of core sandwiched between plastic laminate face and back. Sign face shall be 0.035" (nominal) thick high pressure surface laminate. Signs shall conform to the following:
a. Metal accent bars shall be aluminum.
b. Units shall be frameless. Corners of signs shall be squared and all edges eased.
2.2.2 Changeable Message Strip Signs
Changeable message strip signs shall be of same construction as standard room signs to include a clear non-glare acrylic window that will accept a paper or acetate insert identifying changeable text. The insert shall be prepared typeset message mounted on paper card stock. Provide paper and software for creating text and symbols for computers identified by owner for Owner production of paper inserts after project completion. Furnish one suction device to assist in removing face sheet. Sliding inserts or slide knobs that slide horizontally exposing different graphic information shall be provided as identified in the signage placement schedule and drawings
2.2.3 Type of Mounting For Signs
Provide extruded aluminum brackets for hanging, projecting, and double-sided signs. Mounting for framed, hanging, and projecting signs shall be by mechanical fasteners. Surface mounted signs shall be mounted with 1/16 inch thick closed cell vinyl foam tape and silicone adhesive fabricated from materials that are not corrosive to sign material and mounting surface.
2.2.4 Graphics
Signage graphics for modular signs shall conform to the following:
2.2.5 Character Proportions and Heights
Letters and numbers on signs conform to 36 CFR 1191 .
2.2.6 Tactile Letters, Symbols and Braille
Raised letters and numbers on signs shall conform to 36 CFR 1191 . Tactile
SECTION 10 14 00.20 Page 3 lettering shall be precision machined, raised 1/32", matte PETG and subsurface colored for scratch resistance. Acrylic sphere Braille dots inserted directly into a scratch resistant, high pressure laminate, pressure fit in high tolerance drilled holes. Braille dots shall protrude minimum 0.025".
2.3 BUILDING DIRECTORIES
2.3.1 Fabrication
Front and back faces shall be pressure laminated and precision machined together to a 90 degree angle, with no exposed fasteners.
2.3.2 Non-Illuminated Unit
Directory shall consist of a non-illuminated unit . capable of a accepting paper or acetate inserts. Insert components shall have a 0.08 inch thick non-glare acrylic window and shall be inlayed flush to sign face for a smooth, seamless appearance. Design of unit shall be as shown in the drawings on AG60 12 Detail C1A5, A-5A, A-5B, A-5C .
2.3.2.1 Construction
The directory shall be constructed utilizing the same materials and manufacturing process as room ID's and directional to assure a consistent appearance throughout.
2.3.2.2 Message Strips
Message strips shall be updatable by user. Message strips shall be sized in accordance with manufacturer's standard. Letters and numbers shall be provided in accordance with the drawings. signage contractor shall provide and install all message strips. Manufacturer shall provide a template containing layout, font, color, artwork, and trim lines to allow Owner to produce message strips on laser or ink-jet printer. Template shall be in Acrobat or Word format.
2.3.3 Electronic Directory System
Provide interactive electronic directory. Electronic directory system shall be a complete turnkey system consisting of digital display, hardware, software connected through the local area network (LAN) to a server. Electrical equipment shall be UL listed and shall comply with NFPA 70 . Unit shall be free-standing. See Sheet AG602 Detail C1.
2.4 METAL PLAQUES
2.4.1 Cast Metal Plaques
2.4.1.1 Fabrication
Cast metal plaques shall have the logo, emblem and artwork cast in the bas relief technique. Plaques shall be fabricated from prime aluminum.
2.4.1.2 Border
Border shall be flat band.
SECTION 10 14 00.20 Page 4
2.4.1.3 Finish
Letter Finish satin
Background Finish Colors to match artwork
Background Texture leather
2.4.1.4 Mounting
Mounting shall be concealed.
2.5 DIMENSIONAL BUILDING LETTERS
2.5.1 Fabrication
Letters shall be cast. Letters shall be aluminum. Package letters for protection until installation.
2.5.2 Size
Letter size shall be as indicated. Provide letter thickness that is as indicated.
2.5.3 Finish
Provide clear anodized and dark anodized bronze.
2.5.4 Mounting
Threaded studs of number and size recommended by manufacturer, shall be supplied for concealed anchorage. Letters which project from the mounting surface shall have stud spacer sleeves. Letters, studs, and sleeves shall be of the same material. Templates for mounting shall be supplied.
2.6 ALUMINUM ALLOY PRODUCTS
Aluminum extrusions shall be at least 1/8 inch thick, and aluminum plate or sheet shall be at least 0.0508 inch thick. Extrusions shall conform to ASTM B221; plate and sheet shall conform to ASTM B209. Where anodic coatings are specified, alloy shall conform to AA PK-1 alloy designation
514.0. Exposed anodized aluminum finishes shall be as shown. Welding for aluminum products shall conform to AWS D1.2/D1.2M .
2.7 ANODIC COATING
Anodized finish shall conform to AA DAF45 as follows:
a. Clear (natural) designation AA-M10-C22-A31, Architectural Class II 0.4 mil or thicker.
b. Electrolytically deposited color-anodized designation AA-M10-C22-A34, Architectural Class II 0.4 to 0.7 mil.
2.8 ORGANIC COATING - PLAQUE SIGNS
Organic coating shall conform to AAMA 2604, with total dry film thickness not less than 1.2 mils.
SECTION 10 14 00.20 Page 5
2.9 FABRICATION AND MANUFACTURE
2.9.1 Factory Workmanship
Holes for bolts and screws shall be drilled or punched. Drilling and punching shall produce clean, true lines and surfaces. Exposed surfaces of work shall have a smooth finish and exposed riveting shall be flush.
Fastenings shall be concealed where practicable.
2.9.2 Dissimilar Materials
Where dissimilar metals are in contact, the surfaces will be protected to prevent galvanic or corrosive action.
2.10 COLOR, FINISH, AND CONTRAST
Color shall be as indicated. Finish of all interior signs shall be eggshell, matte, or other non-glare finish as required in handicapped-accessible buildings.
2.11 TYPEFACE
ADA-ABA compliant font for Room Signs Helvetica Regular and as indicated.
PART 3 EXECUTION
3.1 INSTALLATION
Signs shall be installed plumb and true and in accordance with approved manufacturer's instructions at locations shown on the drawings. Submit two copies of operating instructions outlining the step-by-step procedures required for system operation. The instructions shall include simplified diagrams for the system as installed, the manufacturer's name, model number, service manual, parts list, and brief description of all equipment and their basic operating features. Each set shall be permanently bound and shall have a hard cover. The following identification shall be inscribed on the covers: the words "OPERATING AND MAINTENANCE INSTRUCTIONS", name and location of the facility, name of the Contractor, and contract number. Mounting height and mounting location shall conform to 36 CFR 1191 . Required blocking shall be installed. Signs on doors or other surfaces shall not be installed until finishes on such surfaces have been installed. Signs installed on glass surfaces shall be installed with matching blank back-up plates in accordance with manufacturer's instructions.
3.1.1 Anchorage
Anchorage shall be in accordance with approved manufacturer's instructions. Anchorage not otherwise specified or shown shall include slotted inserts, expansion shields, and powder-driven fasteners when approved for concrete; toggle bolts and through bolts for masonry; machine carriage bolts for steel; lag bolts and screws for wood. Exposed anchor and fastener materials shall be compatible with metal to which applied and shall have matching color and finish.
a. Signs mounted to painted gypsum board surfaces shall be removable for painting maintenance.
SECTION 10 14 00.20 Page 6
b. Install signs mounted on metal surfaces with magnetic tape.
c. Install signs mounted on fabric surfaces with hook and loop tape or pin mount.
3.1.2 Protection and Cleaning
Protect the work against damage during construction. Hardware and electrical equipment shall be adjusted for proper operation. Glass, frames, and other sign surfaces shall be cleaned at completion of sign installation in accordance with the manufacturer's approved instructions and the requirements of Section 01 78 23 OPERATION AND MAINTENANCE DATA, Package 1. Submit two copies of maintenance instructions listing routine procedures, repairs, and guides.
SECTION 10 14 00.20 Page 7
SECTION 10 22 39
FOLDING PANEL PARTITIONS
05/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM B221 (2014) Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes
ASTM B221M (2013) Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes (Metric)
ASTM E336 (2014) Measurement of Airborne Sound Insulation in Buildings
ASTM E413 (2010) Rating Sound Insulation
ASTM E557 (2012) Installation of Operable Partitions
ASTM E84 (2014) Standard Test Method for Surface Burning Characteristics of Building Materials
ASTM E90 (2009) Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 101 (2015) Life Safety Code
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED (2009) LEED NC Reference Guide for Green
SECTION 10 22 39 Page 1
Building Design and Construction
1.2 SYSTEM DESCRIPTION
a. No less than 30 calendar days prior to the scheduled commencement of installation, submit the following to the Contracting Officer:
Manufacturer's Qualifications Manufacturer's Sample Warranty Statement of Code Compliance Statement of Standards Conformity Verification of Field Measurements Fabrication Drawings Installation Instructions
b. Supply and install manual operation, acoustical folding panel partitions, factory finished, supported from overhead track without floor guides, as shown on the drawings including all hardware, seals, track and rollers as needed to close the specified opening.
c. Submit drawings to demonstrate that the system has been coordinated and will properly function as a unit. Show layout of the work; track and jamb fastening methods; seal and installation details; and equipment relationship to other parts of the work including clearances for maintenance and operation.
1.2.1 Manual Operation
The manual operation shall be a force no greater than 20 lbf to start movement at the rate of 3.33 ft/s (200 ft/min). Use a removable handle to extend and retract the bottom operable seals; vertical movement of seals shall be 2 inches. Closure to the lead wall shall be by use of a flexible bulb; accomplish final closing by means of a lever exerting pressure against the wall.
1.2.2 Performance Requirements
1.2.2.1 Fire Endurance
For partitions more than 60 square feet in area, provide covering and lining with flame spread rating of 25 or less, fuel contribution rating of 15 or less, smoke generation of 50 or less in accordance with NFPA 101 when tested in accordance with ASTM E84. Submit flame and smoke development tests reports. Provide door and partition finishes with a Class A rating when tested in accordance with ASTM E84.
1.2.2.2 Laboratory Acoustical Requirements
Provide partitions tested in accordance with ASTM E90, by a laboratory accredited by the U.S. Bureau of Standards, that have attained a sound transmission class (STC) of not less than 4547 in a fully extended position, with a Noise Reduction Coefficient (NRC) of 0.25-0.30 for napped, tufted or looped fabric. Partition tested shall be of the same construction, materials, and model number as the partition to be provided and be fully operable. Test specimen shall be not less than 14 feet by 9 feet. Panel weight shall be a minimum of 7.5 psf for STC up to 45.
Design panel thickness ( 4 inch nominal) and composition to provide the required STC rating in accordance with ASTM E90 and ASTM E413.
SECTION 10 22 39 Page 2
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Manufacturer's Qualifications; G Manufacturer's Sample Warranty Statement of Code Compliance; G Statement of Standards Conformity; G Verification of Field Measurements; G
SD-02 Shop Drawings
Installation; G Layouts; G Fabrication Drawings; G
SD-03 Product Data
Recycled Content Materials ( LEED); G, S Low Emitting Materials-Adhesives and Sealants ( LEED); G, S Low Emitting Materials-Paints and Coatings ( LEED); G, S Folding Panel Partitions; G Installation Instructions; G
SD-04 Samples
Folding Panel Partitions; G
SD-06 Test Reports
Acoustical Test; G Flame and Smoke Development Tests; G
SD-07 Certificates
Materials; G Folding Panel Partitions; G
SD-10 Operation and Maintenance Data
Folding Panel Partitions
SD-11 Closeout Submittals
Recycled Content Materials ( LEED); G, S Low Emitting Materials-Adhesives and Sealants ( LEED); G, S Low Emitting Materials-Paints and Coatings ( LEED); G, S
SECTION 10 22 39 Page 3
1.4 SUSTAINABLE DESIGN REQUIREMENTS
1.4.1 Recycled Content Materials
See Section 01 33 29 SUSTAINABILITY REPORTING for cumulative total recycled material requirements. Submit manufacturer's descriptive data.
Documentation shall indicate percentage of postconsumer and preconsumer recycled content per unit of product. Indicate relative dollar value of recycled content products to total dollar value of products included in the project.
1.4.2 Low Emitting Materials-Adhesives and Sealants
See Section 01 33 29 SUSTAINABILITY REPORTING for requirements. Submit manufacturer's documentation that adhesives and sealants are in compliance.
1.4.3 Low Emitting Materials-Paints and Coatings
See Section 01 33 29 SUSTAINABILITY REPORTING for requirements. Submit manufacturer's documentation that paints and coatings are in compliance.
1.5 DELIVERY, STORAGE, AND HANDLING
Deliver materials to the jobsite in the manufacturer's original, unopened, and undamaged packages with labels legible and intact. Provide labels to indicate the manufacturer, brand name, size, finish, and placement location. Store partitions and accessories in unopened packages in a manner that will prevent damage. Handle partition materials in accordance with manufacturer's instructions. Protect materials from the weather, humidity and temperature variations, dirt and dust, or other contaminants.
1.6 WARRANTY
Provide Manufacturer's standard performance guarantees or warranties that extend beyond a 1 year period. In addition, provide guarantee of the pantographs, trolleys and tracks for 10 years from date of acceptance for beneficial use.
PART 2 PRODUCTS
2.1 MATERIALS
Provide material and equipment which are the standard products of a manufacturer regularly engaged in the manufacture of such products and essentially duplicate items that have been in satisfactory use for at least 2 year prior to bid opening. Submit Certificate attesting that the materials meet the requirements specified. Equipment shall be supported by a service organization that is, in the opinion of the Contracting Officer, reasonably convenient to the site. Provide heavy-duty type hardware standard with the manufacturer. Provide pulls and latches for all partitions. Provide partitions with privacy latches. Provide anodized aluminum clear finish hardware.
2.2 FOLDING PANEL PARTITIONS
Provide folding panel partitions using top hung ball bearing carriers which support modular panels.
a. Provide partitions made up of a series of rigid panels, each panel
SECTION 10 22 39 Page 4 being a one-piece assembly. Unless otherwise specified, use the least number of panels. The mechanical seal of the panel shall actuate with a single operating action.
b. Provide panels paired type as indicated.
2.2.1 Panels
Provide panels of steel skin, laminated to appropriate structural acoustical backing, mounted in full perimeter protective frame. Steel for the panel frames shall be a minimum of 22 gauge thick steel with minimum 22 gauge thick face panels spot welded to the frame. Frame shall enclose and protect all edges of the surface material. Panels shall be 4 feet wide, except for end closure panels, and be full height to track. Panels shall lock in place to form a stable, rigid partition; low profile hinges may not project more than 1/4 inch maximum from panel edge.
2.2.1.1 Panels
Panels shall be nominally 4 inches thick, in manufacturer's standard 48 inches widths.
2.2.1.2 Panel Faces
Panel faces shall be of steel backed with gypsum laminated to appropriate substrates to meet the STC requirement and laminated to two vertical full height steel angles. Panel faces shall be mechanically fastened to the frame. Panel faces shall be removable and replaceable on site to accommodate future decor/finish changes.
2.2.1.3 Frames
Extruded frames shall be a composite of steel and aluminum alloys, formed to protect the edges of the face material. Color shall be clear anodized aluminum.
2.2.1.4 Vertical Seals
Interlocking vertical seals between the panels shall consist of tongue and groove aluminum and vinyl astragals creating a shock-absorbing, deep nesting, impact resistant acoustical interlock between panels.
2.2.1.5 Top Seals
Horizontal top seals shall be retractable and operate simultaneously with the bottom seals. Top seals which can make contact with track soffit or ceiling during movement of the panels will not be permitted.
2.2.1.6 Bottom Seals
Horizontal bottom seals shall be mechanically retractable, providing nominal operating clearance, and exert downward force when extended.
Crank type seals requiring more than one rotation of the actuator to set or release or the use of a fixed sweep on any panel shall not be acceptable.
SECTION 10 22 39 Page 5
2.2.2 Finish Covering
OP1: Finish material shall be minimum 54 inches wide, acoustical material of 100 percent polyester. Provide acrylic backed fabric of 100 percent polyester N.R.C. 0.20. Provide non-allergenic stain and mildew resistant fabric which will not rot or support growth of bacteria.
OP2: Finish material shall be minimum 54 inches wide, acoustical material of polyester/olefin with teflon finish. Backing to be acrylic/latex with mildew inhibitor. Provide non-allergenic stain and mildew resistant fabric which will not rot or support growth of bacteria.
2.2.3 Track
Provide recess extruded aluminum track as shown. Conform aluminum to ASTM B221, ASTM B221M. Provide track that is the manufacturer's standard product designed for the weight of the finished partition, including doors. Provide track sections in the maximum lengths practicable, and not less than 6 feet long except for narrow doors and at ends of runs where short length is required. Provide suitable joint devices such as interlocking keys at each joint to provide permanent alignment of track.
2.2.4 Suspension System
Provide a suspension system consisting of heavy duty extruded aluminum track connected to the structural support by threaded rods, and trolleys designed to support the weight of the partition. Provide extruded aluminum track with minimum thickness of 1/8 inch.