Addendum_No2-18Apr2016.pdf

PDF 21 KB Posted

Attached to
Building 1467 Renovations Federal contract opportunity
Solicitation number
W9124D-16-B-0001
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Knox

About this file

Addendum No. 2 dated 18 April 2016

View the file

Other files for this federal contract opportunity

Other files attached to Building 1467 Renovations, newest first.
File Type Posted
W9124D-16-B-0001_Amendment_0003_Conformed_Copy.pdf PDF
CS100-ADDENDUM3.pdf PDF
A-481_-_INTERIOR_SECTION_DETAILS-ADDN3.pdf PDF
Addendum_No3-22Apr2016.pdf PDF
Responses_to_Requests_for_Information _W9124D-16-B-0001 _22Apr2016.pdf PDF
AD111_-_FIRST_FLOOR_DEMOLITION_PLAN_A-ADDN3.pdf PDF
W9124D-16-B-0001 _Pre-Bid_Site_Visit_Attendees.pdf PDF
9 INT-Combined Int-Furniture Set.zip ZIP file
7 ELEC-Electrical-ALLwithADDN1.zip ZIP file
3 ARCH-Architectural-ALLwithADDN1.zip ZIP file
1 GEN-CIVIL- Combined.zip ZIP file
2 STRC-Structural.zip ZIP file
8 TELE-Telecomm-ALLwithADDN1.zip ZIP file
4 FIRE-LS- Fire Protection-ALLwithADDN1.zip ZIP file
1_GEN-CIVwAmnd_2_(2).zip ZIP file
3 ARCHwAmnd 2.zip ZIP file
6 PLUMwAmnd 2.zip ZIP file
7 ELECwAmnd 2.zip ZIP file
9 INTwAmnd 2.zip ZIP file
2 STRCwAmnd 2.zip ZIP file
4 FIREwAmnd 2.zip ZIP file
5 MECHwAmnd 2.zip ZIP file
Volume_2-ALLwith_Amnd_2.pdf PDF
Volume_1-ALLwith_Amnd_2.pdf PDF
Solicitation_Amendment_W9124D-16-B-0001-0002_1467_Renovation_13_Apr_16.pdf PDF
W9124D-16-B-0001-0001.pdf PDF
5_MECH.zip ZIP file
9_INT.zip ZIP file
9a_INT.zip ZIP file
8_TELE.zip ZIP file
9b_INT.zip ZIP file
6_PLUM.zip ZIP file
4_FIRE.zip ZIP file
1_GEN-CIVIL.zip ZIP file
2_STRC.zip ZIP file
3_ARCH.zip ZIP file
9_INT.zip ZIP file
8_TELE.zip ZIP file
6_PLUM.zip ZIP file
7_ELEC.zip ZIP file
5_MECH.zip ZIP file
1_GEN-CIVIL.zip ZIP file
Attachment_1a_-_Drawings_Volume_1_31Mar2016.pdf PDF
Attachment_6_-_Fort_Knox_Safety_Reg_385-10.pdf PDF
Attachment_7_-_Fort_Knox_Fire_Department_specifications.pdf PDF
Attachment_4_-_Ft_Knox_DPW_CADD_Deliverables.pdf PDF
Attachment_9_-_Bldg_1467_Site_ _Storage_Plan.pdf PDF
Attachment_3_-_Combined_Specification_Book.pdf PDF
Solicitation_W9124D-16-B-0001_Fort_Knox_Building_1467_Renovation.pdf PDF
SOW_draft_16-Q-5098_Construction_Bldg_1467_22_Mar_16_Redacted.pdf PDF
Show all 50

Building 1467 Renovations has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 2

Renovation and Restoration of Building 13467

Drawings and Specifications 18 April 2016

The following clarifications, amendments, additions, deletions, revisions, and/or modifications are hereby made part of the Contract Documents, and change the original Contract Documents only in the manner and to the extent herein.

Please make the following changes/clarifications to the drawings and specifications.

DRAWINGS

CIVIL

CS100 – Reference Outdoor Storm Pump note. Add text to note as follows clarifying the pump requirements: “Outdoor storm pump shall be Zoeller 50 Series Model or approved equal.

ARCHITECTURE

“AD” Sheets: All doors shown graphically as dashed as noted on plans are “EXISTING TO BE

DEMOLISHED”. Doors and walls shown as dashed are to be demolished whether specifically noted or not with call outs “001” and “010”. This includes, but is not limited to, doors to new rooms 1C04, 1C08, 2A11, 2A12, 2B08, 2B21, 2C06, 3C00, 3C23, and 3D13.

Regarding Key Note #131, on A-110, A-120, A-130 series of drawings and Details #5 and 6, A-481:

“Cementitious Underlayment” shall be as follows:

Self-leveling gypsum cement product that can be applied in a minimum uniform thickness of 1/8” and that can be feathered at edges. Gypsum cement shall comply with ASTM C 219 and shall have a compressive strength of not less than 4000 psi at 28 days when tested according to ASTM C 109.

Provide primer and aggregate as recommended by the manufacturer.

Revise Key Note #131, on A-110, A-120, A-130 series of drawings and Details #5 and 6, A-481 to add the following text: “Full depth batt insulation shall be provided between the metal stud joists when the finish floor applied over the cement board is either vinyl composition tile or porcelain tile. Metal stud joists shall be 16” on center maximum.”

Details #1, #2, and #3, A-406: Railings depicted shall be as follows in lieu of that shown on the drawing:

36” high 1-1/2” diameter painted steel railing consisting of a horizontal top rail, middle rail, and bottom rail with vertical posts 36” on center maximum.

Detail #8, A-406: Railing shall be 1-1/2” in diameter and spaced a minimum of 2-1/2” clear from the adjacent wall.

Detail #2, A-320: 8” CMU used for Ground Floor window infill shall be 100% solid CMU. Exterior of CMU shall be painted with “Tuff-Kote” by TKO Industrial Coatings or approved equal. Color and texture shall match the existing finish on the exterior concrete wall surrounding the CMU infill.

Refer to Plans #1, #2, and #3, A-422: Provide (4) soap dishes and (4) robe hooks in each of the following showers: Mens Shower 2A18, Womens Shower 2B13, and Mens Shower 2C05. Soap dish shall be surface mounted, stainless steel with a #4 finish (satin); robe hook shall be double-prong, stainless steel with a #4 finish (satin). Verify exact mounting location with the government.

A-104: Provide (6) soap dishes and (6) robe hooks in each of the following showers: Shell Shower GD31 and Shell Shower GD33. Soap dish shall be surface mounted, stainless steel with a #4 finish (satin); robe hook shall be double-prong, stainless steel with a #4 finish (satin). At least one soap dish and one robe hook in each of the rooms shall be ADA/ABA compliant. Verify final mounting locations with the government.

Wall Section #1, A-310: The note “Concrete Fill” shall be replaced with the note “Floor Infill with 3/4” Cement Board over 3-5/8” C-Joist Metal Framing (16” on center maximum) with Cementitious Underlayment Leveler over Existing Slab.” Provide 1/2" cork expansion joint filler strip where the floor infill abuts the aluminum storefront or curtainwall. The expansion joint shall extend the full height of the aluminum sill.

The 3-5/8” metal framing runner facing the aluminum storefront or curtainwall shall be solid without perforations and shall be painted to match the color of the aluminum storefront/curtainwall.

At the following doors: GC000, GD000, 1D000, 1A002, 1A09, 1A210, 1A220, 1B002, 1D000, 2A001, 2D000, 3A000, 3A001, 3B000, 3C000, 3D000, 3D001, 3D071, 3D25, 3D26, where new doors and frames are set into new openings in existing masonry walls, the gypsum wall board at new metal stud walls shall be returned to the hollow metal door frame at the door head and jambs fully concealing the existing masonry wall that was cut.

Refer to sheets A-104 and A-124: In Conference Rooms GD13, GD14, and 2D14 provide the following items in each of the conference rooms:

Projection Screen: Da-Lite (or approved equal) Tensioned Advantage Electrol 16:9 HDTV format 54”high x 96” wide

Projector: NEC (or approved equal)

P502HL

1080p 1920 x 1080 Television: NEC (or approved equal) E655 65” viewable image size

Provide all electrical connections for each item. Verify final mounting locations of each item with the government.

Sheet A-603: Revise hardware set for doors GA23 and GB16 to be Hardware set HW-40.

Sheet A-604: Revise hardware set for doors 1A22, 1A220, 1C07, and 1D09 to be Hardware set HW-40.

MECHANICAL

M110A: Revised Sheet Keynote 1 “All door undercuts shall be ½” except doors with STC rating. “ M110B: Revised Sheet Keynote 1 “All door undercuts shall be ½” except doors with STC rating.”

M110D: Revised Sheet Keynote 1 “All door undercuts shall be ½” except doors with STC rating.”

ELECTRICAL

E120A: Remove Sheet Keynotes 2 and 3.

E120B: Remove Sheet Keynotes 4 and 5.

E120C: Added conduit for storm pump.

E120D: Added conduit for storm pump.

E120D: Add ceiling mounted receptacles in rooms GD13 and GD14 and connected to circuit to LGCSB-16.

E121A: Remove Sheet Keynotes 3 and 4.

E121C: Remove Sheet Keynotes 7 and 8.

E122D: Added wall receptacle for TV in room 2D14 and connected to circuit L2CSB-28.

E306: Added circuit breaker number 18 in panel “LGCR” for storm pump.

TELECOMMUNICATIONS

T-101, T-102, T-111, T-113, T-114: Add notation for “CR” (Card Reader) at all doors to rooms GA23, GB16, 1A22, 1C07, and 1D09 (Doors GA23, GB16, 1A22, 1A220, 1C07, and 1D09)

SPECIFICATIONS:

Add Section 03 35 43 titled POLISHED CONCRETE FINISHING Section 08 71 00 - DOOR HARDWARE, Paragraph 3.5 HARDWARE SETS: Add the following hardware set:

HW-40

3 Hinges A8112 652 1 Power Transfer CEPT-10 1 Electric Lock w/Key Overide F07 Grade 1 RX LX 626 1 Wall Stop L02251 630 1 Power Supply BPS-12/24-1 --- 1 Door Position Switch DPS-M/W-GY Grey 1 Credential Reader by Access Control Contractor.

*120VAC Power, Conduit, and Wiring by Electrical Contractor.

**Heavy Weight or Cam Lift Hinges (as required), seals, door bottom, and threshold, by Sound Door

Supplier.

Operation: Door is normally closed and locked. Valid credential unlocks trim for entry. Free egress at all times.

*** For STC Rated openings, Heavy Weight or Cam Lift Hinges (as required), seals, door bottom, and threshold, by Sound Door Supplier.

ATTACHMENTS:

DRAWINGS

M110A - MECHANICAL GROUND FLOOR DUCT WORK - NEW WORK PLAN 'A'

M110B - MECHANICAL GROUND FLOOR DUCT WORK - NEW WORK PLAN 'B'

M110D - MECHANICAL SECOND FLOOR DUCT WORK - NEW WORK PLAN 'D'

E120C - ELECTRICAL GROUND FLOOR NEW WORK - POWER PLAN 'C'

E120D - ELECTRICAL GROUND FLOOR NEW WORK - POWER PLAN 'D'

E306 - ELECTRICAL PANEL SCHEDULES

SPECIFICATIONS

03 35 43 POLISHED CONCRETE FINISHING