B08 - W9123822B0006 - Amendment 3 - 20220311.pdf

PDF 173 KB Posted

Attached to
USACE SPK ARCF LAR Project 2 - Erosion Control, Bank Protection, and Stabilization Sites 2-2 and 2-3 - Sacramento, CA
Solicitation number
W9123822B0006
Issued by

About this file

This document provides details of Amendment 3 to a federal contract solicitation for erosion control and bank stabilization projects along the American River in Sacramento, California. The U.S. Army Corps of Engineers, Sacramento District, is seeking bids to provide roughly 7,800 feet of stream bank protection and stabilization at two sites totaling approximately 8,800 feet in length to protect critical infrastructure from erosion. Work will include clearing, excavating, and placing soil and rock revetment along the riverbank and levee, installing soil-filled rock protection and tiebacks, constructing planting benches, installing instream wood structures, and revegetating the sites. Contractors will be required to import and place over 100,000 tons of rock riprap, bedding material, and soil; excavate approximately 365,000 cubic yards of soil for off-hauling; and install approximately 295 trees and 4,700 plant cuttings. The amendment provides revised specification sections and plan sheets, an updated bid schedule, and boring logs for the sites.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See SF30 Continuation Page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Mar-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123822B0006

X 9B. DATED (SEE ITEM 11)

16-Feb-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Mar-2022

CODE

USACE SACRAMENTO DISTRICT

ATTN: CONTRACTING DIVISION

1325 J STREET

SACRAMENTO CA 95814-2922

W91238 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123822B0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

SF 30 CONTINUATION PAGE

The purpose of this amendment is to:

1. Provide Amended Specification Sections Dated 08March2022:

a. 01 00 00 - Added survey submittal and survey requirements;

b. 01 22 00 - Entire Section Replaced;

c. 01 33 00 - Added survey submittal;

d. 01 57 19 - Added paragraph "Work Below Ordinary High Water";

e. 31 00 00 - Revised paragraph "Offsite Disposal";

f. 35 42 38 - Revised paragraph "Pre- and Post-Construction Surveys"(Amendment 1)

2. Amended Plan Sheets to indicate Ordinary High Water Elevations Dated 08March2022: C-301, C-302, C-303, C-304, C-305, C-306, & C-307 (Amendment 1)

3. Provide Updated Bid Schedule Dated 08March2022

4. Provide Boring Log Location and Reports

(End of Summary of Changes)

File details come from the government source that posted it. Updated .