This document summarizes an amendment to a federal solicitation for upgrade of an access control point at a defense depot in Tracy, California. The solicitation seeks contractors to provide all labor, materials, equipment and supervision necessary to upgrade gatehouse facilities, including active barriers, a vehicle inspection facility with under vehicle inspection system, guard booths, and over-watch buildings. The facilities will receive fire suppression and alarm systems, mass notification systems, HVAC, electrical, building automation, energy monitoring and control systems, and utilities. Contractors are responsible for measuring and determining actual lengths and quantities. The estimated cost range is $15-25 million. The period of performance after notice to proceed is 540 days. The solicitation is proceeding as an invitation for bid under NAICS code 236220, with a size standard of $36.5 million. The IFB is anticipated to be issued by the end of October 2019 and available at fedbizopps.gov.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W9123820B0001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
A. The purpose of Amendment 0005 is to:
1) Extend the date for the bid opening to 10 December 2019 @ 9:00 AM
2) Provide revised Specifications
3) Update section 00 21 13 - Instructions to Bidders, Preparation of Subcontracting plan (e)
4) Provide revised Draw ings.
B. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Nov-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9123820B0001
X 9B. DATED (SEE ITEM 11)
01-Oct-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Nov-2019
CODE
US ARMY CORPS OF ENGINEERS, SACRAMENTO
CONTRACTING DIVISION
1325 J STREET
SACRAMENTO CA 95814-2922
W91238 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 01 10 - TABLE OF CONTENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 01 Specifications 22Jul19 2014 22-JUL-2019 Attachment 02 Drawings 22Jul19 262 22-JUL-2019 Attachment 03 Wage Determination
26Jul19
122 26-JUL-2019
Attachment 04 DD1354 Transfer of Real property 01April19
2 01-APR-2019
Attachment 05 Furniture Fixtures Equipment 22Jul19
98 22-JUL-2019
Attachment 06 Structural Interior Design 14Jun19
100 14-JUN-2019
Attachment 07 Bid Schedule 1 to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 01 Specifications 2254 2098 Attachment 02 Drawings 22Jul19 262 22-JUL-2019 Attachment 03 Wage Determination
26Jul19
122 26-JUL-2019
Attachment 04 DD1354 Transfer of Real property 01April19
2 01-APR-2019
Attachment 05 Furniture Fixtures Equipment 22Jul19
98 22-JUL-2019
Attachment 06 Structural Interior Design 14Jun19
100 14-JUN-2019
Attachment 07 Bid Schedule 1
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 03-Dec-2019 09:00 AM to 10-Dec-2019 09:00 AM.
SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS
The following have been modified:
SUPPLEMENTARY INSTRUCTIONS
SUBMITTAL INFORMATION FOR BIDDERS:
See Section 00 22 13 – SUPPLEMENTARY INSTRUCTIONS TO BIDDERS on how to prepare and submit your Bid.
The following documents must be returned with your quote, bid, or offer.
--The completed Standard Form 1442 with continuation pages, duly executed with an original signature by an official authorized to bind the company. Ensure that the firm’s DUNS or DUNS+4 Number is entered in the block with its name and address.
--Your acknowledgement of any and all Amendments to the solicitation in accordance with the instructions on the Standard Form 30 Amendment.
Note: If the SF 1442 and/or the pricing schedule was changed by amendment, be sure to use the amended pages when submitting your quote, bid, or offer.
--The completed Pricing Bid Schedule with your proposed contract line item prices inserted in the appropriate spaces. Prices must be proposed for all contract line items and priced sub-line items. Unit prices are to be extended to the actual “dollar and cents” amounts (i.e., to two decimal places). Do not round off extended prices to the nearest dollar. Check your pricing submission very carefully for mathematical and clerical errors prior to submission.
--Your completed Representations, Certifications, and Other Statements of Bidders/Offerors (Section 00 45 00).
--Your Bid Guarantee (e.g., Standard Form 24, “Bid Bond”)
INQUIRIES:
Prospective bidders should submit inquiries related to this solicitation in accordance with the following (collect calls will not be accepted):
a. For information related to amendments, and the dates set for bid opening, please check http://www.fedbizopps.gov
b. Contractual and Technical inquiries and questions relating to proposal procedures are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.
1. To submit and review bid inquiry items, offerors will need to be a current registered user or self-register into the system. To self-register go to the aforementioned web page and click on the QUICK ADD link. Select agency as USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your e-mail address, and then click continue. Fill in all required information and click Add User.
2. From this page you may view all bidder inquiries or add an inquiry.
3. Bidders will receive an acknowledgement of their question via e-mail, followed by an answer to their question after it has been processed.
4. The Solicitation Number is: W91238-20-B-0001 The Bidder Inquiry Key is: BDWNH2-2VA2BH
c. The Bidder Inquiry System will be unavailable for new inquiries 10 days prior to the bid opening date in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
d. Bidders are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
f. The point of contact for this solicitation is:
Contract Specialist: Karen Scott Deanna C. Zemovich Telephone: (916) 557-7109 7027
E-MAIL: Karen.Scott@usace.army.mil deanna.c.zemovich@usace.army.mil
DIRECTIONS FOR SUBMITTING BIDS:
Envelopes containing bids must be sealed, marked and addressed as follows:
MARK ENVELOPES:
Solicitation No. W91238-20-B-0001
ADDRESS ENVELOPES TO:
Department of the Army U.S. Army Engineer District, Sacramento ATTN: Contracting Division 1325 J Street Sacramento CA 95814-2922
SPECIAL INSTRUCTIONS PERTAINING TO HAND-CARRIED BIDS:
Hand-carried bids must be delivered to: The Building Lobby at 1325 J Street, Sacramento, CA.
Due to security precautions, all Corps of Engineers visitors are now required to sign-in, leave a Photo-ID (such as a drivers license), and get a Visitor’s Pass at the Security Desk in the Building Lobby. Bidders may no longer hand-carry their bids directly to Contracting Division. Bids may NOT be either turned-in at the Security Desk or left unattended elsewhere in the Lobby. Additionally, you are advised that there is no public parking in the Building.
The Bid Opening Officer will be in the Building Lobby 20 minutes prior to the scheduled bid opening time to accept sealed bids. After announcing that no further bids will be received, the bidders waiting in the Building Lobby will then be escorted as a group to the Bid Opening Room, where the bids will be publicly opened and read.
Bidders who desire to hand-deliver their bids at an earlier time must coordinate with the contract specialist in advance to arrange to be met in the Building Lobby by Contracting Division personnel. In the event the contract specialist cannot be reached, please call the main Contracting Division telephone number, (916) 557-5201, in order to request assistance.
Please ensure that all courier and delivery personnel are aware of these procedures.
CONTRACTOR RESPONSIBILITY, PREAWARD SURVEY:
In order to determine a contractor's responsibility for purposes of contract award in accordance with FAR Part 9, the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and/or plant to be used in performing the work (see Preaward Survey below). The Preaward Survey is attached to the solicitation for information purposes only. It will be required from only the low bidder. After the Bid Opening, the Government will request this information from the low bidder. The Government will set a due date for its submission. The Preaward Survey is not required as part of the bid package. All offerors will complete and return the Preaward Survey as part of the Price/Cost proposal.
Failure to submit the Pre-award Survey in conjunction with the price proposal will not of itself render the offer unacceptable. In order to be determined to be responsible a prospective contractor must be determined responsible in accordance with FAR 9.104-1. The Pre-award Survey is a tool used by the Government in determining responsibility of the offeror and is submitted as part of the Price/Cost proposal.
In order to be determined to be responsible a prospective contractor must:
a. Have adequate financial resources to perform the contract or the ability to obtain them.
b. Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments.
c. Have a satisfactory performance record. In making the determination of responsibility, the Government Contracting Officer shall consider relevant past performance information. A prospective contractor shall not be determined responsible or nonresponsible solely on the basis of a lack of relevant performance history except when there are special standards set forth in the solicitation which applies to all bidders that must be met in order to receive the award. These special standards may be necessary when unusual expertise or specialized facilities are necessary in the performance of the contract;
therefore, in order to be determined to be responsible for that particular contract, the offeror must be able to meet those special standards. A prospective contractor that is or recently has been seriously deficient in contract performance shall be presumed to be nonresponsible unless the Contracting Officer determines that the circumstances were beyond the contractor's control or that the contractor has taken appropriate corrective action. Other responsibility considerations by the Contracting Officer will include past efforts by the contractor to apply sufficient tenacity and perseverance to perform acceptably, to meet quality requirements of contracts, and the contractor's past compliance with subcontracting plans (if required) under recent contracts.
d. Have a satisfactory record of integrity and business ethics.
e. Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors).
f. Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them.
g. Be otherwise qualified and eligible to receive an award under applicable laws and regulations.
If the contractor or subcontractor does not already have sufficient resources demonstrated in the completed Preaward Survey, acceptable evidence of "the ability to obtain" the required, adequate resources (all of the resources discussed in subparagraphs a, e, and f above) normally consists of a commitment or explicit arrangement that will be in existence at the time of contract award to rent, purchase or otherwise acquire the needed facilities, equipment, other resources, or personnel.
AVAILABILITY OF CORPS OF ENGINEERS PUBLICATIONS DESCRIPTIONS:
a. The internet URL for Corps of Engineers publications is:
http://140.194.76.129/publications/
b. Construction Criteria Base (CCB). The Construction Criteria Base (CCB) system available through the National Institute of Building Sciences includes copies of Corps of Engineers methods and specifications. Information about the CCB can be obtained from:
http://www.wbdg.org/ccb/ccb.php
EVALUATION FOR AWARD:
The Government contemplates award of one contract to the responsive, responsible bidder who submits the low bid for the total of the following items in Pricing Bid Schedule:
All line items listed in Pricing Bid Schedule.
If the solicitation's Pricing Schedule contains options, see evaluation of options clause below for information on the procedure used by the Government to determine "low bid".
EVALUATION FOR AWARD:
The Government contemplates award of one contract to the responsive, responsible bidder who submits the low bid in accordance with evaluation criteria described in DFARS 252.236-7007.
FACSIMILE BIDS/OFFERS:
Facsimile bids/offers, modifications thereto, or cancellations of bids/offers will not be accepted.
PREPARATION OF SUBCONTRACTING PLAN:
(a) See FAR 52.219-9, Section 00 70 00, of this solicitation. Subcontracting Plans will be developed considering only the subcontracts actually to be awarded. Subcontracting Plans are required from other than small businesses if the contract price is over $1,500,000; they are not required from small business firms regardless of the contract price.
(b) For information on the evaluation of subcontracting plans, see Army Federal Acquisition Regulation Supplement, Appendix DD.
(c) Contact Ms. Michelle Morales (916)557-7641, Deputy for Small Business, with questions on the Subcontracting Plan requirements and further instructions on submission of Electronic Subcontracting Reporting System (eSRS) as required by FAR 52.219-9.
(d) The Corps of Engineers highly encourages all bidders/offerors to meet the recommended subcontracting goals as follows:
Small Businesses 30.0%
Small Disadvantaged Businesses 10.0%
Women-Owned Small Businesses 5.0%
HUBZone Small Business 5.0%
Veteran-Owned Small Business 3.0%
Service Disabled Veteran Owned Small Business 3.0%
(e) FAR 19.702(a)(2) provides: In sealed bidding acquisitions, each invitation for bids to perform a contract that is expected to exceed $700,000 ($1.5 million for construction) and that has subcontracting possibilities, shall require the bidder selected for award to submit a subcontracting plan. If the selected bidder fails to submit a plan within the time limit prescribed by the contracting officer, the bidder will be ineligible for award.
As such, the apparent low bidder, as identified at the bid opening (See SF1442 Block 13.A. for date and time), shall provide a subcontracting plan within three calendar days from the bid opening.
Regarding evaluation of subcontracting plans, see FAR 17.705-4(b). Each bidder's plan must cover each of the 15 required elements (see 19.704). If the bidder does not submit a plan that incorporates the required elements within the time allotted, the bidder shall be ineligible for award. If the plan, although responsive, evidences the bidder's intention not to comply with its obligations under the clause at 52.219- 8, Utilization of Small Business Concerns, the contracting officer may find the bidder non-responsible.
Questions on the Subcontracting Plan requirements or the Electronic Subcontracting Reporting System (eSRS) requirements as required by FAR 52.219-9, shall be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.
The goals are calculated as a percentage of the TOTAL SUBCONTRACTING DOLLARS, NOT THE
TOTAL CONTRACT AMOUNT.
FACSIMILE BIDS/OFFERS:
Facsimile bids/offers, modifications thereto, or cancellations of bids/offers will not be accepted.
PERFORMANCE AND PAYMENT BONDS:
The bidder/offeror whose bid/offer is accepted will, within the time established in the contract, furnish performance and payment bonds in accordance with FAR 52.228-15.
INDIVIDUAL SURETIES IN SUPPORT OF BID BONDS:
Bidders/offerors utilizing individual sureties in support of a bid bond shall include a Standard Form (SF) 28 (Affidavit of Individual Surety), accompanied by a pledge of acceptable assets from each person acting as an individual surety, and include these with the SF 24 (Bid Bond), and the bid itself (see clause titled "Pledges of Assets," FAR 52.228-11).
Pledges of acceptable assets shall be in the form of (1) evidence of an escrow account and/or (2) a recorded lien on real estate. If this is an IFB, failure to provide pledges of acceptable assets, with the bid, in the specified form, accompanied by a properly executed SF 24 and SF 28, will render the bidder nonresponsible and thus ineligible for award. If this is an RFP, failure to provide required documentation described herein may cause the offeror to be deemed "unacceptable".
BID GUARANTEE FORM AND AMOUNT:
The bidder shall furnish a separate bid guarantee in accordance with the solicitation provision titled "Bid Guarantee", FAR 52.228-1. In accordance with FAR 28.101-2 the bid guarantee amount shall be at least 20 percent of the "bid price" but shall not exceed $3 million. When the penal sum is expressed as a percentage, a maximum dollar limitation may be stated. If there are option line items on the Pricing Schedule, the term "bid price" is hereby defined as the total bid to include the amount for the Base and line items designated as "options". In bids/proposals that contain "additives", the "bid price" is defined as the total of all bid items including additive line items. FAR 28.106-1 states that a Standard Form (SF) 24 shall be used for the bid bond. In accordance with FAR 28.202(a)(1), corporate sureties utilized must appear on the list contained in the Department of Treasury Circular 570 titled "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and Acceptable Reinsuring Companies."
ACCEPTANCE OF OFFERS:
A written award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.
Pre-Award Survey
The Government will treat the pre-award survey information submitted by the offeror as proprietary.
CONSTRUCTION CONTRACTOR DATA DATE:
Firm Name and Telephone Number Main Office Address (Street, City, and State)
Branch Offices Services Rendered Construction Design Consultant
Organization Individual Joint Venture Partnership Corporation
Date Organized Date Incorporated:
State:
Names of Officers and Other Key Personnel
I – PRESENT PAYROLL PERSONNEL (List Number of Each Category Below) Partners:
Officers:
Other Key:
Remainder: Subtotal Permanent:
Maximum Personnel at Any Time:
Date:
Total:
II—EQUIPMENT OWNED III—FINANCIAL DATA AS OF
(DATE): Present Value ($)
Current Assets:
Acquisition Cost ($) Current Liabilities:
Net Worth:
IV—TOTAL VALUE OF CONSTRUCTION AND DEMOLITION WORK
IN PAST 6 YRS EXCLUSIVE OF JOINT VENTURE (LIST MOST
RECENT FIRST)
V—LARGEST JOB EVER
CONTRACTED
(If Other Than in Past Six Years)
$ LARGEST JOB IN PAST 6 YRS Contract Amount:
Date:
Description:
Owner:
$ Contract Amount:
Date:
Description:
Owner:
Avg. Annual Income
VI—TYPE OF WORK IN WHICH FIRM SPECIALIZES
NAME AND POSITION/TITLE OF PERSON SIGNING SIGNATURE
See attachment for explanations or detailed description of item(s) reported above.
CONSTRUCTION CONTRACTOR DATA – SCHEDULE A – EXISTING COMMITMENTS
List below the construction projects your firm currently has under way, including recent awards. Also list construction projects for which your firm is the apparent successful offeror/bidder, but for which a contract has not yet been awarded.
CONTRACT
NUMBER
AMOUNT
DESCRIPTION/
LOCATION
ORGANIZATION/
CONTACT PERSON/
PHONE NUMBER
PERCENT
COMPLETE
CONSTRUCTION CONTRACTOR DATA – SCHEDULE B – COMPLETED PROJECTS
List below the principal construction projects your firm has completed within the past six years, including all DoD contracts with a total value of $15M or more.
NUMBER
AMOUNT
DESCRIPTION/
LOCATION
ORGANIZATION/
CONTACT PERSON/
PHONE NUMBER
PERCENT
SUBLET
CONSTRUCTION CONTRACTOR DATA – SCHEDULE C –
CONSTRUCTION AND/OR TECHNICAL EQUIPMENT
List total equipment and facilities owned for performing the prospective contract and present status as to whether or not it is currently committed to existing contracts.
QUANTITY
DESCRIPTION
CONDITION
YEARS OF
SERVICE
PRESENT
STATUS
(End of Summary of Changes)