PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
DIVISION 02 TO 33 – TECHNICAL REQUIREMENTS
- End of Project Table of Contents -
01 00 00 GENERAL REQUIREMENTS
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.10 QUALITY CONTROL SYSTEM (QCS)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 62 35 RECYCLED/RECOVERED/BIOBASED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
02 41 00.00 40 DEMOLITION
02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES
02 83 13.00 20 LEAD IN CONSTRUCTION
03 40 00.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE CONSTRUCTION
00 EARTHWORK
32 11 23 AGGREGATE BASE COURSE
32 11 30 LIME MODIFIED SOILS
32 12 10 BITUMINOUS TACK COAT
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 17 23.00 20 PAVEMENT MARKINGS
33 11 00 WATER DISTRIBUTION
33 30 00 SANITARY SEWERS
33 40 01 STORM DRAINAGE
01 00 00 - 1
SECTION TABLE OF CONTENTS DIVISION
01 - GENERAL REQUIREMENTS SECTION
01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SCRAP MATERIAL
1.3 WRITTEN GUARANTEES AND GUARANTOR'S LOCAL REPRESENTATIVE
1.4 PRICING OF CONTRACTOR-FURNISHED PROPERTY
1.5 TEMPORARY ELECTRIC WIRING
1.5.1 Temporary Power and Lighting
1.5.2 Construction Equipment
1.5.3 Circuit Protection
1.6 UTILITIES
1.7 GENERAL SAFETY REQUIREMENTS
1.7.1 General
1.7.2 The Prime Contractor's Superintendent
1.7.3 Job Hazard Analysis
1.7.4 Violations
1.7.5 Elevated Work Areas
1.7.5.1 Protection
1.7.5.2 Guard Rails
1.7.6 Fire Prevention
1.7.6.1 Inspections
1.7.7 Recordkeeping/Reporting Requirements
1.7.8 Accident Reporting
1.8 PLANNED UTILITY OUTAGES AND STREET CLOSURES
1.9 EXCAVATION PERMITS
1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.11 EQUIPMENT DATA FORM
1.12 SPECIAL CONSTRUCTION PROCEDURES
1.13 CONTRACTOR SAFETY PERSONNEL REQUIREMENTS
1.14 AREAS OF RADAR RADIATION HAZARD
1.15 HAZARDOUS NOISE AREA
1.16 COLOR SCHEME FOR CONTRACTOR FACILITIES
1.17 AFTER AWARD DOCUMENTS
PART 2 PRODUCTS
PART 3 EXECUTION
ATTACHMENTS:
CESPK FORM 450
-- End of Section Table of Contents --
01 00 00 - 2
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2014; AMD 1 2013; Errata 2013; AMD 2
2013) National Electrical Code
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
ER 415-1-15 (1989) Construction Time Extensions for
Weather
U.S. ARMY CORPS OF ENGINEERS, SACRAMENTO DISTRICT (CESPK)
CESPK FORM 450 (1992) Contractor Equipment Data Sheet
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1904 Recording and Reporting Occupational
Injuries and Illnesses
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1926 Safety and Health Regulations for
Construction
1.2 SCRAP MATERIAL
Materials specified to be removed and become the property of the Contractor are designated as scrap, and the Contractor, by signing this contract, hereby acknowledges that he has made due allowance for value, if any, of such scrap in the contract price.
1.3 WRITTEN GUARANTEES AND GUARANTOR’S LOCAL REPRESENTATIVE
Prior to completion of the contract, obtain and furnish to the Contracting
Officer’s representative written guarantees for all the equipment and/or appliances furnished under the contract. Furnish with each guarantee: The name, address, and telephone number of the guarantor’s representative nearest to the location where the equipment and/or appliances are installed, who, upon request of the Using Service’s representative, will honor the guarantee during the guaranty period and will provide the services prescribed by the terms of the guarantee.
01 00 00 - 3
1.4 PRICING OF CONTRACTOR-FURNISHED PROPERTY
At the request of the Contracting Officer, promptly furnish and shall cause any subcontractors to furnish, in like manner, unit prices and descriptive data required by the government for property record purposes of fixtures and equipment furnished and installed by the Contractor.
1.5 TEMPORARY ELECTRIC WIRING
1.5.1 Temporary Power and Lighting
Provide construction power facilities in accordance with the safety requirements of the NFPA 70 and EM 385-1-1. Enforce all the safety requirements of electrical extensions for the work of all subcontractors.
All work shall be accomplished by skilled electrical tradesmen in a workmanlike manner, as approved by the Contracting Officer.
1.5.2 Construction Equipment
In addition to the requirements of EM 385-1-1, all temporary wiring conductors installed for operation of construction tools and equipment shall be either Type TW or THW contained in metal raceways, or may be multiconductor cord. Temporary wiring shall be secured above the ground or floor in a workmanlike manner and shall not present an obstacle to persons or equipment. Open wiring may only be used outside of buildings, and then only in strict accordance with the provisions of the National Electrical
Code.
1.5.3 Circuit Protection
In addition to the present requirements in EM 385-1-1 and NFPA 70, all 15 and 20-ampere receptacle outlets used for obtaining power during construction shall have ground fault circuit interrupters (GFCI) for personnel protection. Block and brick saws shall also be equipped with
GFCI. The Contracting Officer may allow an exception to this requirement for circuits for concrete vibrators or circuits operating at other than 60
Hertz normal (in both cases an assured grounding program as described in the NFPA 70, except utilizing the daily inspection frequency of the grounding means of such equipment, may be permitted). The assured grounding program will not be permitted as a substitute for usage of GFCI'S except as described above. All generator-powered 15- and 20-ampere, 60
Hertz receptacle outlets shall have GFCI'S, and shall be properly grounded.
Provide a testing means which will impose a measured fault of 5 milliamperes, plus or minus 1 milliamperes, and result in tripping the GFCI unit.
1.6 UTILITIES
Immediately notify the Contracting Officer in writing if utilities not shown on the plans and not visible as to the date of this contract are encountered within the construction limits of the entire project, and such utilities will interfere with construction operations, to enable a determination by the Contracting Officer as to the necessity for removal or relocation. If such utilities are removed or relocated as directed by the
Contracting Officer, an equitable adjustment in the contract price shall be made pursuant to the Contract Clause CHANGES to cover the cost of any additional pertinent work or delay.
It is anticipated that pole lines, signs, pipelines and private
01 00 00 - 4 improvements that would interfere with or are to be replaced by new construction will be removed to new locations by the owners (or by the
State of California or its agents) in advance of construction operations.
Notify the Contracting Officer at least 30 days in advance of the date on which work will be started requiring the removal of such utilities or private improvements. Care shall be taken to preserve and protect any such improvements from injury or damage during construction operations. Assume full responsibility for reimbursing the owners for any damage to their properties, utilities, or improvements, or interference with their services caused through construction operations. Should such damage be found to have been caused without the Contractor's fault or negligence, an equitable adjustment in the amount due under the contract will be made under the applicable CONTRACT CLAUSES contained within the basic MATOC.
1.7 GENERAL SAFETY REQUIREMENTS
1.7.1 General
For information regarding specific Safety Requirements see Section 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS. Refer to EM 385-1-1, (see Contract
Clauses, Basic MATOC, ACCIDENT PREVENTION) and the Occupational Safety and
Health Act (OSHA) Standards for Construction 29 CFR 1926; General Industry
Standards 29 CFR 1910; and the National Fire Protection Association Codes are applicable to this contract. In case of conflict the most stringent requirement of the standards is applicable.
1.7.2 The Prime Contractor's Superintendent
The Prime Contractor's superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis (see below), tool box meetings, walk-through inspections, correction of violations, etc., and including that of the subcontractor's work.
1.7.3 Job Hazard Analysis
Based on the construction schedule, submit a job hazard analysis of each major phase of work prior to entering that phase of activity. The analysis shall include major or high risk hazards, as well as commonly recurring deficiencies that might possibly be encountered for that operation, and shall identify proposed methods and techniques of accomplishing each phase in a safe manner. The Prime Contractor's superintendent shall take active participation in the Job Hazard Analysis, including the subcontractors' work. Prior to start of actual work a meeting shall be held with Prime
Contractor, Government, and affected subcontractor to review the Job Hazard
Analysis. In addition, job site meetings shall be held to indoctrinate foreman and workers on details of this analysis.
1.7.4 Violations
If recurring violations and/or gross violation indicate that the safety performance is unsatisfactory, corrective action shall be taken as directed, and at the discretion of the Contracting Officer the retention or some part thereof will be withheld from the progress payment until corrective action has been completed.
1.7.5 Elevated Work Areas
Workers in elevated work areas in excess of 6 feet above an adjoining
01 00 00 - 5 surface require special safety attention. In addition to the provisions of
EM 385-1-1, the following safety measures are required to be submitted to the Contracting Officer's Representative. Prior to commencement of work in elevated work areas, submit drawings depicting all provisions of positive protection system including, but not limited to, all details of guard rails.
1.7.5.1 Protection
Positive protection for workmen engaged in the installation of structural steel and steel joists shall be provided by safety nets, tie-off's, hydraulic man lifts, scaffolds, or other required means. Decking crews must be tied-off or work over nets or platforms not over 6 feet below the work area. Walking on beams and/or girders and the climbing of columns is prohibited without positive protection.
1.7.5.2 Guard Rails
Perimeter guard rails shall be installed at floor, roof, or wall openings more than 6 feet above an adjoining surface and on roof perimeters. Rails shall be designed to protect all phases of elevated work including, but not limited to, roofing operations and installation of gutters and flashing.
Rails around roofs may not be removed until all work on the roof is complete and all traffic on or across the roof ceases. Rails shall be designed by a licensed engineer to provide adequate stability under any anticipated impact loading. As a minimum, the rails shall consist of a top rail at a height of 42 inches, a mid rail and a toe board. Use of tie-offs, hydraulic man lifts, scaffolds, or other means of roof edge protection methods may be utilized on small structures such as family housing, prefabricated metal buildings, etc.
1.7.6 Fire Prevention
Twenty-four hours’ notice shall be given to the Contracting Officer for coordination with the Facility Fire Department prior to conducting any fire hazardous operation. Cutting or welding will be permitted only in areas that are or have been made fire safe. Where possible, all combustibles shall be located at least 35 feet horizontally from the work site. Where such location is impracticable, combustibles shall be protected with fire blankets and/or protective welding screens to prevent slag from running out of the work area. Edges of covers at the floor shall be tight to prevent sparks from going under them. This precaution is also important at overlaps where several covers are used to protect a large pile. Do not allow any welding/cutting or open flame operations in facilities that are protected by a wet pipe fire sprinkler or an automatic detection system, if the system is out of service. First priority of work will be to return the suppression/detection system to operational condition. Return the fire detection and/or suppression system back to an operational status (if possible) during periods that the facility is unoccupied, and at the end of the work day. Post a fire guard for a 24 hour period (or certify to the
Fire Department that the facility is safe) after welding, cutting, and open flame operations in a facility when: (a) fire detection and suppression system cannot be returned to service; (b) fire detection or suppression systems do not exist. Other fire prevention precautions shall be in accordance with the latest National Fire Codes.
1.7.6.1 Inspections
All construction sites are subject to fire and safety inspections without notice. Any violation of fire and safety standards may result in a work
01 00 00 - 6 stoppage at the expense of the Contractor.
1.7.7 Recordkeeping/Reporting Requirements
On all contract operations, record and report all accident exposure and experience incident work. (This includes exposure and experience of the prime contractor and sub-contractor(s)). As a minimum these records shall include exposure work-hours and a log of occupational injuries and illnesses. (OSHA Form 300 or state equivalent as prescribed by 29 CFR
1904). Refer to EM 385-1-1, Paragraph 01.D.04.
1.7.8 Accident Reporting
In addition to the requirements for reporting accidents in accordance with
EM 385-1-1, Section 1, submit at the 50% point and 100% of project completion, a written summary of worker's compensation claims filed by workers on the project. The report will include all subcontractors. The main report covering the Prime Contractor claims will be certified as
"correct and true" by the Contractor's compensation insurance carrier. The same certification will be required for subcontractor reports.
1.8 PLANNED UTILITY OUTAGES AND STREET CLOSURES
All utility outages and street closures shall be of as short a duration as possible and shall be scheduled as far in advance as possible with the
Contracting Officer, in no case less than 7 days before the outage or closure. Obtain from the Contracting Officer in writing a statement or schedule giving the permissible times of outages or closures for particular installations and the maximum time allowed for each. Strictly observe such schedules and the contractor will be held responsible for any violations.
Power outages shall be restricted to off-duty hours and weekends. Other utilities may be connected and streets closed during normal working hours with the outage duration and street closure as short as possible. All outages and street closures shall be scheduled as far in advance as possible with the Contracting Officer and in no case less than 21 days before the outage or closure. Obtain in writing from the Contracting
Officer a statement or schedule giving the permissible times of utility outages or road closures for particular installations and the maximum time allowed for such outage. Strictly observe such schedules and will be held responsible for any violations.
1.9 EXCAVATION PERMITS
All excavation permits will be issued to the Contractor from the Director of Public Works (DPW) or Base Civil Engineer (BCE), through the
Contracting Officer. The appropriate form, for this request, may be obtained from the Contracting Officer. Processing time required is 14 calendar days. Questions concerning the excavation permit should be directed to the Contracting Officer.
(A) General:
Reference is made to the article of the contract entitled "Permits and
Responsibilities," which obligates the Contractor to obtain all required licenses and permits.
L2COSGAH
Cross-Out
L2COSGAH
Cross-Out
L2COSGAH
Callout
L2COSGAH
Line
L2COSGAH
Callout 14 days
01 00 00 - 7
1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
(A) This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the CONTRACT
CLAUSE, Basic MATOC, entitled "DEFAULT (FIXED-PRICE CONSTRUCTION)".
In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
(B) The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
STATE
CALIFORNIA - TRACY AD/SHARPE CARBONA
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
(09) (05) (05) (03) (01) (00) (00) (00) (00) (01) (04) (08)
(C) Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the
Contractor's scheduled work day. Refer to ER 415-1-15.
1.11 EQUIPMENT DATA FORM
Furnish CESPK FORM 450 for all necessary equipment to perform work requiring adjustment of contract price and shall submit these forms with the modification proposals. A sample form is at the end of this section.
1.12 SPECIAL CONSTRUCTION PROCEDURES
1.13 CONTRACTOR SAFETY PERSONNEL REQUIREMENTS
See Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS for all safety requirements.
1.14 AREAS OF RADAR RADIATION HAZARD
The work under this contract may to be performed in, or in the vicinity of, NOT USED
L2COSGAH
Cross-Out
01 00 00 - 8 areas that may be hazardous at times due to radar radiation. Construction activities and Contractor's personnel shall not be allowed within such areas without prior arrangement with and the approval of the Contracting
Officer. Maintain a close working relationship with the Contracting
Officer's representative and shall govern his activities within such areas as said representative may arrange with operating personnel of the pertinent Base or Post.
1.15 HAZARDOUS NOISE AREA
Work area for this contract may be located within a high noise area and can be hazardous to the human ear. The Contractor is responsible for providing adequate ear protection as may be required for Contractor's personnel at the job site.
1.16 COLOR SCHEME FOR CONTRACTOR FACILITIES
(A) All Contractor storage and operational facilities including temporary structures, signs and fencing that remain at the site shall be compatible with the color scheme used on the project signs as directed by the Contracting Officer.
1.17 AFTER AWARD DOCUMENTS
Provide five hard copy sets from the Portable Data Format (PDF) contract drawings and specifications. The hard copy drawings shall be ANSI D (22" x
34"), and the specifications shall be standard 8-1/2" x 11", 3-hole punched with posts. Provide these documents within 5 work days of the receipt of the NTP from the government.
The government will provide a CD/DVD, without charge, containing the electronic CAD files to prepare as-built/as-constructed drawings and a submittal register data file in comma separated value (CSV) format.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
L2COSGAH
Cross-Out
L2COSGAH
Cross-Out
CESPK FORM 450 1 SEP 92 (Edition of Apr 84 will be used) FormFlow 2.2, ver 1
DATE
CONTRACTOR EQUIPMENT DATA SHEET
(Data to be furnished by Contractor for all equipment to be used on modifications as required under the Special Provisions of the Contract.)
CONTRACTOR CONTRACTNUMBER
1. EQUIPMENT DESCRIPTION
2. MODELAND SERIES
3. YEAR PURCHASED
4. PURCHASEPRICEAT YEAR PURCHASED
5. LIST PRICE,YEAR OF MANUFACTURE
6. YEAR MANUFACTURED
7. EQUIPMENT HORSEPOWER
8. CARRIERHORSEPOWER
9. FUELTYPE
10. SHIPPINGWEIGHT
11. TIRESIZE: FRONT-
DRIVE- TRAI
LING-
REMARKS:
01 32 01 - 1
01 - GENERAL REQUIREMENTS SECTION
01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 CONTRACTOR SCHEDULING REPRESENTATIVE QUALIFICATIONS
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.1.1 Approved Project Schedule
3.1.2 Schedule Status Reports
3.1.3 Default Terms
3.2 BASIS FOR PAYMENT AND COST LOADING
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Critical Path Method
3.3.2 Level of Detail Required
3.3.2.1 Activity Durations
3.3.2.2 Design and Permit Activities
3.3.2.3 Procurement Activities
3.3.2.4 Mandatory Tasks
3.3.2.5 Government Activities
3.3.2.6 Contracts with multiple buildings/facilities
3.3.2.7 Activity Responsibility Coding (RESP)
3.3.2.8 Activity Work Area Coding
3.3.2.9 Contract Changes/Requests for Equitable Adjustment (REA)
Coding (MODF)
3.3.2.10 Contract Line Item (CLIN) Coding (BIDI)
3.3.2.11 Phase of Work Coding (PHAS)
3.3.2.12 Category of Work Coding (CATW)
3.3.2.13 Definable Features of Work Coding (FOW1, FOW2, FOW3)
3.3.3 Scheduled Project Completion and Activity Calendars
3.3.3.1 Project Start Date
3.3.3.2 Schedule Constraints and Open Ended Logic
3.3.3.3 Early Project Completion
3.3.4 Interim Completion Dates
3.3.4.1 Design phase
3.3.4.2 Start Phase
3.3.4.3 End Phase
3.3.4.4 Phase "X" Hammock
3.3.5 Default Progress Data Disallowed
3.3.6 Out-of-Sequence Progress
01 32 01 - 2
3.3.7 Negative Lags and Start to Finish Relationships
3.3.8 Calculation Mode
3.3.9 Milestones
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary NAS Project Schedule Submission
3.4.2 Initial NAS Project Schedule Submission
3.4.3 Design Package Schedule Submission
3.4.4 Periodic Schedule Updates
3.4.5 Standard Activity Coding Dictionary
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CDs
3.5.2 Narrative Report
3.5.3 Approved Changes Verification
3.5.4 Schedule Reports
3.5.4.1 Activity Report
3.5.4.2 Logic Report
3.5.4.3 Total Float Report
3.5.4.4 Earnings Report by CLIN
3.5.4.5 Activity Resource Loading
3.5.5 Network Diagram
3.5.5.1 Continuous Flow
3.5.5.2 Project Milestone Dates
3.5.5.3 Critical Path
3.5.5.4 Banding
3.5.5.5 S-Curves
3.6 PERIODIC SCHEDULE UPDATE MEETINGS
3.6.1 Update Submission Following Progress Meeting
3.6.2 Status of Activities
3.6.2.1 Start and Finish Dates
3.6.2.2 Remaining Duration
3.6.2.3 Percent Complete
3.6.2.4 Logic Changes
3.6.2.5 Other Changes
3.7 REQUESTS FOR TIME EXTENSIONS
3.7.1 Justification of Delay
3.7.2 Submission Requirements
3.7.3 Additional Submission Requirements
3.8 DIRECTED CHANGES
3.9 WEEKLY PROGRESS MEETINGS
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
01 32 01 - 3
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ECB 2005-10 (2005) Scheduling Requirements for Testing of Mechanical Systems in Construction
Contracts
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G
Bar Chart Schedule
Schedule Status Report
Design Package Schedule; G
Initial NAS Project Schedule
Preliminary NAS Project Schedule; G
Periodic Schedule Updates
Data CDs
Justification of Delay
Proposed Schedule Revisions; G
1.3 CONTRACTOR SCHEDULING REPRESENTATIVE QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation and submittal of the entire Network Analysis Systems (NAS) project schedule including all items specified below and revisions to the schedule or supplemental completion schedules, and all required updating
(activity status) and preparation of reports, as applicable or directed by the Contracting Officer. The authorized scheduling representative shall be approved by the Contracting Officer based on a resume indicating as a minimum, formal training from a software vendor or 5 years’ experience in working with NAS schedules.
01 32 01 - 4
Not Used
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.
Designers, Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. The schedule must be a forward planning as well as a project monitoring tool.
3.1.1 Approved Project Schedule
Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
3.1.2 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. The government will use the NAS Project Schedule to evaluate the contractor's progress for timely completion, plan for Quality Assurance verification of the work and evaluate the effects of a proposed modification on the contract duration (critical path activities). If, in the opinion of the
Contracting Officer, the Contractor falls behind the approved schedule, the
Contractor shall take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the
Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.3 Default Terms
Failure of the Contractor to comply with the requirements of the
Contracting Officer shall be grounds for a determination by the Contracting
Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract.
Upon making this determination, the Contracting Officer may terminate the
Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
3.2 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each
01 32 01 - 5 update period and therefore the amount of each progress payment. Lack of an approved schedule update or qualified scheduling personnel will result in an inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The computer software system utilized to produce and update the NAS Project
Schedule shall be capable of meeting all requirements of this specification. Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule. Scheduling software that meets the activity coding structure defined in the Standard
Data Exchange Format (SDEF) in ER 1-1-11 are Primavera Project Planner (P6) by Primavera, and Open Plan by Deltek. The Contractor shall provide to the
Government a complete input listing for the selected software. Manual methods used to produce any required information shall require prior approval by the Contracting Officer. The Contracting Officer intends to use P6, which is compatible with RMS.
Should the contractor utilize software that is different than that utilized by the Contracting Officer, based on the software utilized by the contractor for the preparation of the NAS schedule, the contractor shall provide a copy of the software and a license to the Administrative
Contracting Officer at the Government field office until final payment.
The software and license shall be returned to the contractor. The
Contractor shall submit a copy of the user's manual outlining the selected
CPM computer program's mathematical analysis capabilities, details, functions and operation.
3.3.1 Critical Path Method
Use the Critical Path Method (CPM) of network calculation to generate the
Project Schedule. Prepare the Project Schedule using the Precedence
Diagram Method (PDM).
3.3.2 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The
Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2.1 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have Original Durations
(OD) greater than 20 work days or 30 calendar days. Durations shall be in workdays. Procurement activities are defined herein.
01 32 01 - 6
3.3.2.2 Design and Permit Activities
Include design and permit activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. This shall be at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work. The schedule shall include review and correction periods associated with each item.
3.3.2.3 Procurement Activities
The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
3.3.2.4 Mandatory Tasks
Include and properly schedule the following mandatory tasks:
a. Submission, review and acceptance of design packages.
b. Submission of mechanical/electrical/information systems layout drawings.
c. Submission and approval of O & M manuals.
d. Submission and approval of as-built drawings.
e. Submission and approval of 1354 data and installed equipment lists.
f. Submission and approval of testing and air balance (TAB).
g. Submission of TAB specialist design review report.
h. Submission and approval of fire protection specialist.
i. Submission and approval of testing and balancing of HVAC plus commissioning plans and data. Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with ECB 2005-10.
j. Air and water balancing.
k. HVAC commissioning.
l. Controls testing plan submission.
m. Controls testing.
n. Performance Verification testing.
o. Other systems testing, if required.
p. Contractor's pre-final inspection.
01 32 01 - 7
q. Correction of punchlist from Contractor's pre-final inspection.
r. Government's pre-final inspection.
s. Correction of punch list from Government's pre-final inspection.
t. Final inspection.
3.3.2.5 Government Activities
Show government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, review and verification that design submittals are in accordance with the RFP inspections, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment
(GFE) and Notice to Proceed (NTP) for phasing requirements. Government approval of shop drawings activities should be shown with the duration at least the minimum allowed by the contract. The contractor's failure to provide reasonable durations in its schedule for Government activities does not establish or change the Government's review or approval path periods and the durations established for Government's activities are subject to approval by the Contracting Officer.
Allow 30 calendar day’s total duration prior to current contract completion date for the following activities. Refer to specification
Section 01 45 00 QUALITY CONTROL. Include and properly schedule the following critical tasks:
a. Submission of Contractor Quality Control (CQC) for all mechanical/electrical/information systems tests.
b. Government QA for all mechanical systems acceptance/operational tests.
b. Government QA for all electrical systems acceptance/operational tests.
c. CQC completion inspection of the entire project.
d. Contractor works off CQC punchlist.
e. Prefinal inspection performed when the facility is completed such that it can be used for it intended function, as determined by the
Contracting Officer.
f. Contractor works off prefinal punchlist.
g. Final/acceptance inspection of the entire project.
h. Contractor works off final punchlist.
3.3.2.6 Contracts with multiple buildings/facilities
Prepare a separate detailed NAS schedule for each building/facility indicating its critical path for specified interim completion dates or critical milestone date. The master NAS schedule shall indicate the interface/lag/link between buildings/facilities to maximize/level the labor and other resources. The master schedule critical path must be indicated through the various buildings/facilities and total duration equal to the contract duration.
01 32 01 - 8
3.3.2.7 Activity Responsibility Coding (RESP)
Assign responsibility Code for all activities to the Prime Contractor, Subcontractor or Government agency responsible for performing the activity. Activities coded with a Government Responsibility code include, but are not limited to: government approvals, government design reviews, environmental permit approvals by State regulators, Government Furnished
Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements. Code all activities not coded with a Government Responsibility Code to the Prime
Contractor or Subcontractor responsible to perform the work. Activities shall not have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record); ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and
GOVT (for USACE). Unacceptable code values are abbreviations of the names of subcontractors.
3.3.2.8 Activity Work Area Coding
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities shall not have more than one Work Area Code. Not all activities are required to be Work Area coded. A lack of Work Area coding will indicate the activity is not resource or space constrained.
3.3.2.9 Contract Changes/Requests for Equitable Adjustment (REA) Coding
(MODF)
Assign Activity code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by the
Contracting Officer, with a Contract Changes/REA Code. Key all Code values to the Government's modification numbering system. Any activity or sequence of activities added to the schedule as a result of alleged constructive changes made by the government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer.
Assign Activity codes for these activities with a Contract Changes/REA
Code. Key the code values to the Contractor's numbering system. Approval to add these activities does not necessarily mean the government accepts responsibility and therefore liability for such activities and any associated impacts to the schedule, but rather the government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. Such activities shall not be Responsibility Coded to the government unless approved. An activity shall not have more than one Contract Changes/REA Code.
3.3.2.10 Contract Line Item (CLIN) Coding (BIDI)
Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs. An activity shall not contain more than one CLIN
Item Code. CLIN Item code all activities, even when an activity is not cost loaded.
01 32 01 - 9
3.3.2.11 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities based upon the phase of work in which the activity occurs. Code activities to either a Design Phase or a
Construction Phase. Code fast track design and construction phases proposed by the Contractor to allow filtering and organizing the schedule by fast track design and construction packages. If the contract specifies construction phasing with separately defined performance periods, identify a Construction Phase Code to allow filtering and organizing the schedule accordingly. Each activity shall be identified with a single project phase and have only one Phase of Work code.
3.3.2.12 Category of Work Coding (CATW)
Assign Category of Work Code to all Activities based upon the category of work to which the activity belongs. Category of Work Code must include, but is not limited to: design, design submittal, design reviews, review conferences, permits, construction submittal approvals, Acceptance, Procurement, Fabrication, Delivery, Weather Sensitive Installation, Non-Weather Sensitive Installation, Start-Up, Test and Turnover. Assign a
Category of Work Code to each activity. Each activity shall have only one
Category of Work Code.
3.3.2.13 Definable Features of Work Coding (FOW1, FOW2, FOW3)
Assign a Definable Feature of Work Code to appropriate activities based on the definable feature of work to which the activity belongs. Definable
Feature of Work is defined in Specification Section 01 45 00 QUALITY
CONTROL. An activity shall not have more than one Definable Feature of
Work Code. Not all activities are required to be Definable Feature of Work
Coded.
3.3.3 Scheduled Project Completion and Activity Calendars
The schedule interval shall extend from NTP date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is acknowledged by the
Contractor. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7 day calendar when the contract assigns calendar day durations for the activity such as a
Government Acceptance activity. If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non-work periods identified including weekends and holidays. Assign the Category of Work Code - Weather
Sensitive Installation to those activities that are weather sensitive.
Original durations must account for anticipated normal adverse weather.
The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the Contractor intends to perform work during those periods.
3.3.3.1 Project Start Date
The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called "Start Project"(or NTP). The "Start Project" activity shall have an "ES" constraint date equal to the date that the NTP was acknowledged, and a zero day duration.
01 32 01 - 10
3.3.3.2 Schedule Constraints and Open Ended Logic
Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have an "LF" constraint date equal to the contract completion date for the project, and with a zero day duration or by using the "project must finish by" date in the scheduling software. The schedule shall have no constrained dates other than those specified in the contract. The use of artificial float constraints such as "zero fee float" or "zero total float" are typically prohibited. There shall only be 2 open ended activities:
Start Project (or NTP) with no predecessor logic and End Project with no successor logic.
3.3.3.3 Early Project Completion
In the event the Preliminary or Initial NAS Project Schedule calculates an early completion date of the last activity prior to the contract completion date, the Contractor shall identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government will not approve an early completion schedule with zero float on the longest path. The
Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.
3.3.4 Interim Completion Dates
Constrain contractually specified interim completion dates to show negative float when the calculated early finish date of the last activity in that phase is later than the specified interim completion date.
3.3.4.1 Design phase
The contractor shall include the following design phase activities in the composite design and construction NAS Project schedule. The duration of each of these activities must be the duration as included in the contract award.
Pre-work conference within 5 days after NTP
Design Charrette (Preliminary Design) within 7 days after NTP
Design Charrette (Preliminary Design) within 7 days after NTP
Submittal of preliminary design (60%)
Design review conference of Preliminary design
Submittal of Final design (95%)
Design review conference of Final design
Submittal of Corrected Final design (100%)
01 32 01 - 11
Design review conference of Corrected Final design
Design Complete
3.3.4.2 Start Phase
Include as the first activity for a project phase an activity called "Start
Phase X" where "X" refers to the phase of work. The "Start Phase X" activity shall have an "ES" constraint date equal to the date on which the
NTP was acknowledged, and a zero day duration.
3.3.4.3 End Phase
Include as the last activity for a project phase an activity called "End
Phase X" where "X" refers to the phase of work. The "End Phase X" activity shall have an "LF" constraint date equal to the specified completion date for that phase and a zero day duration.
3.3.4.4 Phase "X" Hammock
Include a hammock type activity for each project phase called "Phase X" where "X" refers to the phase of work. The "Phase X" hammock activity shall be logically tied to the earliest and latest activities in the phase.
3.3.5 Default Progress Data Disallowed
Do not automatically update Actual Start and Finish dates with default mechanisms that may be included in the scheduling software. Activity
Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process shall match those dates provided from Contractor Quality Control
Reports. Failure of the Contractor to document the AS and AF dates on the
Daily Quality Control report for every in-progress or completed activity, and failure to ensure that the data contained on the Daily Quality Control reports is the sole basis for schedule updating shall result in the disapproval of the Contractor's updated schedule and the inability of the
Contracting Officer to evaluate Contractor progress for payment purposes.
Updating of the percent complete and the remaining duration of any activity shall be independent functions. Disable program features which calculate one of these parameters from the other.
3.3.6 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate all out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Correct out of sequence progress that continues for more than two update cycles by logic revision, as approved by the Contracting Officer.
3.3.7 Negative Lags and Start to Finish Relationships
Lag durations contained in the project schedule shall not have a negative value. Do not use Start to Finish (SF) relationships.
3.3.8 Calculation Mode
Schedule calculations shall retain the logic between predecessors and successors even when the successor activity starts and the predecessor
01 32 01 - 12 activity has not finished. Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") will not be allowed.
3.3.9 Milestones
The schedule must include milestone activities for each significant project event including but not limited to: milestone activities for each fast track design package released for construction; design complete;
foundation/substructure construction complete; superstructure construction complete; building dry-in or enclosure complete to allow the initiation of finish activities; permanent power complete; and building systems commissioning complete.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. Provide a bar chart schedule for the first 30 calendar days of the contract at the Pre-construction conference. The data CD, reports, and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS.
3.4.1 Preliminary NAS Project Schedule Submission
Submit the Preliminary NAS Project Schedule, defining the Contractor's planned operations for the first 90 calendar days for approval within 30 calendar days after the NTP is acknowledged. The approved Preliminary NAS
Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. Completely cost load the Preliminary NAS Project
Schedule to balance the contract award CLINS shown on the Price Schedule.
Detail it for the first 90 calendar days. It may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as previously specified. The Preliminary
NAS Project Schedule forms the basis for the Initial NAS Project Schedule specified herein and must include all of the required Plan and Program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection
Plan) as well as design activities, the planned submissions of all early design packages, permitting activities, design review conference activities and other non-construction activities intended to occur within the first 90 calendar days. Schedule any construction activities planned for the first
90 calendar days after NTP. Constrain planned construction activities by
Government acceptance of the associated design package(s) and all other specified Program and Plan approvals. Activity code any activities that are summary in nature after the first 90 calendar days with Responsibility
Code (RESP) and Feature of Work code (FOW1, FOW2, FOW3).
3.4.2 Initial NAS Project Schedule Submission
Submit the Initial NAS Project Schedule for approval…