Appendix_5A_Environmental_requirements_Water_Pipeline.pdf

PDF 3 MB Posted

Attached to
Base-wide Underground Water Distribution and base-wide roadway paving and repair at work site.
Solicitation number
W91238-18-R-0002
Issued by

About this file

Appendix 5A Environmental Req Water

View the file

Other files

File Type Posted
DIVISION_1_TO_33_TECHNICAL_SPECIFICATIONSrev1.pdf PDF
Atch_1_REVSOW_7_MAR_18.pdf PDF
Appendix_5A_Environmental_Requirements_waterpipe_v2.pdf PDF
Amendment_0002_W91238-18-R-0002.pdf PDF
Wage_Determination_dated_2_Mar_2018.pdf PDF
Appendix_19A_-_Concrete_Pavement_Detail.pdf PDF
Appendix_25_As_Built_Whse_29_Soil_Boring.pdf PDF
Appendix_31__Land_Location_Control_2014.pdf PDF
Appendix_32__Map_Test_of_Excav_Soil.pdf PDF
Appendix_11-_Updated_Water_Lines_Replacement_ALL.pdf PDF
Appendix_29_Geotechnical_Invest_WH_58.pdf PDF
Appendix_11A-_Updated_Water_Line_Phasing_Plan_revised.pdf PDF
Appendix_26__As_Built_Whse28Sht_8_Soil_Logs.pdf PDF
Appendix_11B_Updated_Water_Lines_Replmt_Pave_Rep.pdf PDF
Atch_1_REVSOW_15_FEB_18.pdf PDF
Appendix_28_Boring_logs_Whse_57.pdf PDF
Appendix_30_Boring_Logs_WH_59.pdf PDF
Appendix_27_Boring_Logs_Whse_56.pdf PDF
Appendix_14__UFC_3_230_01_Water_Storage_Trans.pdf PDF
Amendment_0001_.pdf PDF
Atch_3_REV_Wage_Determ.pdf PDF
W9123818R0002_Site_Visit_Log_Sheet.pdf PDF
Atch_3_WDetermination.pdf PDF
Atch_6_Appendixes_zip_file.pdf PDF
Atch_1_SOW_.pdf PDF
SF1442_Solicitation.pdf PDF
Appendix_24_-_Construction_and_Demolition_Debris_Worksheet.xlsx XLSX spreadsheet
Atch_2_Supplemental_Req.pdf PDF
Appendix_4_-DesignRoadFlexibleCBR_2.xls XLS spreadsheet
Appendix_10A_-Domestic_Water_Valve_Depths_DLA_tracy.xlsx XLSX spreadsheet
Appendix_5_-Environmental_requirements_Paving.pdf PDF
Atch_4_Spec_Div_1_thru__33_Tech_Spec.pdf PDF
Att_5_Base_Access_Req.xlsx XLSX spreadsheet
Appendix_4_-Paving_Design_Calculations.xls XLS spreadsheet
Synopsis_Tracy18R0002_.doc DOC document
Synopsis_(Presolicitation).doc DOC document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ENVIRONMENTAL CHECKLIST

Project proponent completes all sections. Please print clearly or type. Submit to Environmental Office for review.

Any questions Call: 839-4129 Environmental Chief

Section 1: General Information Project#

Project Title:

Phone:

Phone:

Phone:

Dept:

Date:

Proponent/Department:

Proj. Mgr:

Prepared by:

Section 2: Project Site Information

Planned Start Date: Planned Completion Date:

Purpose of the project (include any description of operations, functions, and activities associated with the project which will change or occur due to the project):

Sharpe TracyProject Location

Environmental Checklist Page 1 of 4 3 Dec 2012

Describe the location and area of the proposed project:

Total Acreage Developed: Acres Disturbed:

Total Length of Trench:

Excavation Area & Depth:

Trench Depth:

Acres Paved:

Describe the size and staging location of soil borrow/stock piles:

Describe where excess soil/ fill material will be disposed?:

Describe laydown areas, locations and duration of use:

Section 3: General Project Questions (Check positive responses.)

Is the project a new facility?

Has the project area been mapped, labeled, or distinguished?

Is additional future development or phases planned?

Provide additional project location data not requested elsewhere:

Section 4: Specific Project Questions (Check positive responses.)

Dewatering of a construction site?

Facility renovation or alteration?

Building demolition, renovation, or retrofit?

Installation of electrical equipment, e.g. transformers, switches or capacitors?

Equipment alteration or relocation?

Placement of new equipment?

Installation, repair or removal of fuel storage tanks?

Routine use of fuels or oils?

New fuel storage or distribution facilities?

New heating units or boilers?

Emergency generators or other stationary internal combustion engines?

New sources of air emissions (e.g. paint booths, blasting operations)?

New drinking water services?

Water for fire protection?

Generation or Disposal of domestic wastewater (e.g. rinsewater, washdowns, pressure washing, etc.)?

Concrete?

Involve Solid wastes such as:

Asphalt?

Topsoil?

Electrical equipment?

Recyclable materials (e.g. steel, cardboard, wood, etc.)?

Increase in outfall water or untreated runoff entering Storm water system?

Asbestos or Asbestos containing building materials?

Involve disturbance or use of Hazardous substances such as:

Mercury?

PCBs?

Lead Based Paint?

Other?

Cleaners or solvents?

Excavation, trenching, or disturbance of soils?

Disturbance of any threatened or endangered species (e.g. Burrowing Owl, etc.)?

Loud and/or sustained noise above 70dB?

Environmental Checklist Page 3 of 4 3 Dec 2012

Hazardous material storage required?

Involve use or storage of Hazardous materials:

Storage of HM more than 55 gal?

Will there be temporary or permanant storage of HM?

Installation or alteration of potable water backflow prevention devices?

Would this proposal cause any concerns from the neighbors (e.g. dust, noise, view)?

NEPA Required

Project Title:

REC/SCS EA EIS None

Additional Project Requirements

EMS Inspection HM inventory update

Air Emissions Permits

Haz Waste Site Specific Training

Est. Completion Time and Notes

Project Location Sharpe Tracy

Storm water permits

Meetings and Coordination

Site Visit Requested Prior to Construction Site Visit Requested During Construction

Contractually required Environmental Protection Plan? Review Specific Environmental Requirements with Contractor?

Additional Environmental Requirements/ comments:

Project #

Prepared by: Phone:Date:

ENVIRONMENTAL REQUIREMENTS

General Conformity Calculations

Section 106/NHPA Land Use Controls notification

This page to be completed and returned by the Environmental Department

Environmental Checklist Page 4 of 4 21 Mar 2013

Hazardous Waste Disposal

ENVIRONMENTAL CHECKLIST

Project proponent completes all sections. Please print clearly or type. Submit to Environmental Office for review.

Any questions Call: 839-4129 Environmental Chief Section 1: General Information Section 2: Project Site Information Purpose of the project (include any description of operations, functions, and activities associated with the project which will change or occur due to the project):

Project Location Environmental Checklist Page 1 of 4 3 Dec 2012 ..\My Pictures\dlalogo.jpg Describe the location and area of the proposed project:

Describe the size and staging location of soil borrow/stock piles:

Describe where excess soil/ fill material will be disposed?:

Describe laydown areas, locations and duration of use:

Section 3: General Project Questions (Check positive responses.)

Provide additional project location data not requested elsewhere:

Section 4: Specific Project Questions (Check positive responses.)

Involve Solid wastes such as:

Involve disturbance or use of Hazardous substances such as:

Environmental Checklist Page 3 of 4 3 Dec 2012 Involve use or storage of Hazardous materials:

NEPA Required Additional Project Requirements Project Location Meetings and Coordination ..\My Pictures\dlalogo.jpg

ENVIRONMENTAL REQUIREMENTS

This page to be completed and returned by the Environmental Department Environmental Checklist Page 4 of 4 21 Mar 2013 8.2.1.4029.1.523496.503679

TextField1: P.2014.01055
TextField1: Replace Main Water Distribution System Piping
TextField1: P.2014.01055
TextField2: Replace Main Water Distribution System Piping
TextField12:
TextField3: 4525
TextField3: DS-FJI
TextField3: 4525
DateTimeField1: 2014-05-21
DateTimeField1: November 2014
DateTimeField1: Feb 28, 2016
DateTimeField1: 2014-05-21
TextField4: Tuan Nguyen
TextField4: Tuan Nguyen
CheckBox5: 0
CheckBox5: 1
CheckBox5: 0
CheckBox5: 0
CheckBox5: 0
CheckBox5: 1
CheckBox5: 0
CheckBox5: 0
CheckBox5: 0
CheckBox5: 0
CheckBox5: 0
CheckBox5: 1
CheckBox5: 0
CheckBox5: 1
CheckBox5: 1
CheckBox5: 1
CheckBox5: 1
CheckBox5: 1
CheckBox5: 0
CheckBox5: 0
CheckBox5: 0
CheckBox5: 0
CheckBox5: 1
CheckBox5: 0
TextField6: Repair by replacement approximately 50,000 LF of underground AC and DI pipes of the existing depot main domestic water distribution system with new PVC pipes including valves and valve boxes.
TextField7: 5-8'
TextField8: TBD
TextField9: Off Site
TextField10: Will be assigned at the Precon in needed
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 1
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 1
CheckBox1: 1
CheckBox1: 1
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 1
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 1
CheckBox1: 0
CheckBox1: 1
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
CheckBox1: 0
TextField11: 1. NEPA Categorical Exclusion 32CFR Part 651 Appendix B section II (g) (1).

2. A storm water permit is required. Storm water Permit Registration Documents (PRDs) must be provided to the environmental office for review and submission to the State. Contractor will have to register on the State's storm water site and be linked to the pending Notice of Intent (NOI) to then complete the required application. The contractor is responsible for paying all fees to the State.

3. Some areas of this project may be located on "Land Use Control" areas. Any waste soil generated from these areas of excavation or trenching may not be relocated on site. It must be analyzed for the appropriate contaminants for that location (likely pesticides and/or metals). It must then be disposed of appropriately as it may well be hazardous waste. Consult the Master Plan Land Use Control map.

4. Contractor must adhere to the attached General Environmental Controls

TextField5: Tracy Site