Tracy Kitchen Remodel bldg 100 and 16 2098
SECTION 21 21 03.00 10
WET CHEMICAL FIRE EXTINGUISHING SYSTEM
02/09
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 17A (2013) Standard for Wet Chemical Extinguishing Systems
NFPA 96 (2014) Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations
UNDERWRITERS LABORATORIES (UL)
UL Fire Prot Dir (2012) Fire Protection Equipment Directory
1.2 SYSTEM DESCRIPTION
1.2.1 General
Protect cooking equipment items including the exhaust hood, grease filter, and exhaust duct serving the item by preengineered wet chemical fire extinguishing system. System shall be installed with all accessories necessary for system to operate in accordance with manufacturer's instructions and as specified herein.
1.2.2 Design and instllation Requirements
System application, design, and installation shall comply with NFPA 17A and NFPA 96, except as follows:
a. System components shalmustlisted in UL Fire Prot Dir or approved by FM APP GUIDE for use with wet chemical fire extinguishing systems.
c. Interpret reference to the "authority having jurisdiction" to mean the Contracting Officer.
d. The use of grease extractors does not eliminate the requirement that duct systems, grease removal devices, and hoods be protected by the wet chemical extinguishing system.
SECTION 21 21 03.00 10 Page 1
1.2.3 System Controls
Each system shall be actuated by fusible link and by a remote manual actuation station connected to the extinguishing system release mechanism by cable. Remote manual actuation stations shall be located along the path of egress and shall automatically actuate the building fire alarm system.
The system controls shall automatically shut off fuel flow and electrical power to the protected appliances and other appliances located under the ventilating system protected by the extinguishing system upon system actuation. All cables used shall be stainless steel with corner pulleys employing stainless steel ball bearings at all corners. All cable and wiring shall be enclosed in conduit.
1.2.4 Existing Building Fire Alarm Control Panel
The existing building fire alarm control panel location is shown on electrical sheet E103.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Installation Drawings; G, DO
SD-03 Product Data
Similar Services
Standard Products; G
Preliminary Tests; G
Final Acceptance Tests; G
Field Training
SD-06 Test Reports
Preliminary Tests
Final Acceptance Tests
SD-07 Certificates
Installation Technician; G
Installation Drawings; G, DO
SD-10 Operation and Maintenance Data
Operation and Maintenance Instructions; G
SECTION 21 21 03.00 10 Page 2
1.4 QUALITY CONTROL
Submit a statement demonstrating successful completion of similar services on at least five projects of similar size and scope, at least 2 weeks before submittal of other items required by this section.
1.4.1 Coordination of Trades
Each system shall be coordinated with the equipment, hood, and exhaust ducts that it protects along with other construction in order to eliminate any interference.
1.4.2 Installation Technician
The installation technician shall have been trained by the system manufacturer for system installation, operation, and maintenance.
Concurrent with statement of similar services, submit manufacturer's certification of installation technician.
1.4.3 Installation Drawings
Provide installation drawings prepared by a representative of the manufacturer to ensure compliance with the requirements listed herein and with all manufacturer's requirements and recommendations. Submit drawings consisting of system layout including assembly and installation details and electrical connection diagrams; piping layout showing pipe sizes, lengths, and supports. Drawings shall include any information required to demonstrate that the system has been coordinated and will function as intended and shall show system relationship to items it protects and clearances required for operation and maintenance. Submit manufacturer's certification of the drawings. Drawings shall also include conduit, cables, manual actuation stations and fusible links. Include detail drawings for the following items:
a. Storage containers and mounting brackets
b. Fusible links, cables, conduit, corner pulleys, and link mounting frames/brackets
c. Release mechanisms
d. Valves
e. Discharge nozzles
f. Piping components
g. Remote manual actuation stations
h. Fuel and power shutoff
i. Alarms, alarm devices, alarm interface(s), control panels
1.5 DELIVERY, STORAGE, AND HANDLING
Protect equipment delivered and placed in storage from the weather, humidity and temperature variations, dirt and dust, or other contaminants.
SECTION 21 21 03.00 10 Page 3
PART 2 PRODUCTS
2.1 STANDARD PRODUCTS
a. Provide system components which are the standard products of a manufacturer regularly engaged in the manufacturing of products that are of similar material, design and workmanship and that have been in satisfactory commercial or industrial use for 2 years before bid opening. The 2-year experience shall include installations of systems under similar circumstances and of similar size. Systems shall be supported by a service organization.
b. Submit manufacturer's catalog data. The data shall be highlighted to show model, size, options, etc., that are intended for consideration and shall be adequate to demonstrate compliance with contract requirements.
c. Locate identification signs at each remote manual actuation station.
Signs shall be fabricated of rigid plastic, red in color, with engraved white letters that are a minimum 0.25 inches in height. Each sign shall be engraved with "Fire Extinguishing System" and with a brief description of the equipment protected.
d. Replace the fire alarm panel zone identification label with a new label of similar construction which indicates the equipment is connected to the zone module. Discharge of the extinguishing system shall actuate the fire alarm control panel in the same manner as other actuating devices. Extinguishing system wiring shall be supervised in the same manner as other devices connected to the fire alarm system.
2.2 PIPING COMPONENTS
2.2.1 Pipe and Fittings
Pipe and fittings shall be Schedule 40 stainless steel. Stainless steel tubing may be used in accordance with manufacturer's recommendations.
Galvanized pipe shall not be used.
2.2.2 Nozzles
Nozzles shall be stainless steel and shall be equipped with an integral strainer to prevent matter inside the distribution piping from clogging the nozzle orifice. Each nozzle orifice shall be provided with a seal to protect the nozzle from clogging by grease or other obstructions. This seal shall detach upon actuation.
2.3 WET CHEMICAL
The wet chemical shall not have an adverse effect on stainless steel during exposure periods of up to 24 hours.
PART 3 EXECUTION
3.1 INSTALLATION
Installation shall be performed by the installation technician in accordance with system manufacturer's instructions. Ductwork access doors shall be provided where indicated and at any items requiring service and inspection, including nozzles and fusible links. Ductwork access doors
SECTION 21 21 03.00 10 Page 4 shall be in accordance with Section 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEM.
3.2 PRELIMINARY TESTS
Submit proposed test procedures for preliminary test, at least 2 weeks before the start of related testing. System diagrams that show system layout and typed condensed normal and emergency operating procedures, methods for checking the system for normal, safe operation, and procedures for manual actuation shall be framed under glass or laminated plastic.
After approval, these items shall be posted where directed. After installation has been completed, each system shall be actuated by both fusible link and by remote actuation station to demonstrate proper function of all components, including alarms and fuel flow and power shut off.
Actuation by fusible link shall be in a manner approved by the system manufacturer. Test containers, pressurized with either nitrogen or air to normal system operating pressure and of the same size as actual operating containers shall be discharged into system. The seals shall release as during normal actuation. After each discharge, the nozzles shall be removed, disassembled, and strainers shall be cleaned. System piping shall be inspected and cleaned as necessary. All functions of system operation shall be verified, including switches, shutdown of fuel and power to appliances protected by the system or served by the same ventilation system, uniform delivery of air or nitrogen, and activation of alarms.
Nozzle seals/covers shall be replaced after the preliminary tests are complete. In the event portions of the tests are unsuccessful, repairs shall be made and the entire test repeated until successful. Submit test report for the preliminary tests in booklet form, upon completion of testing. Report shall document test results including repairs and adjustments made, and final test results.
3.3 FINAL ACCEPTANCE TESTS
Submit proposed test procedures for final acceptance test, at least 2 weeks before the start of related testing and proposed test schedule for acceptance test, at least 2 weeks before the start of related testing.
System shall be actuated by both fusible link and remote manual actuation station and all system functions shall be verified as described in Paragraph PRELIMINARY TESTS using test containers specified for preliminary tests . Each nozzle shall be provided with a plastic container, hose, and hose fitting to capture all wet chemical discharged. All tests or checks recommended by the manufacturer shall also be performed. In the event portions of the tests are unsuccessful, repairs shall be made and the entire test repeated until successful. Nozzle seals/covers shall be replaced after the final acceptance tests are complete. The system shall be returned to normal operating condition after the completion of testing and wet chemical containers expended shall be recharged and verified leak tight. Extinguishing system and equipment and duct protected by the extinguishing shall be cleaned after completion of testing. Any damage shall be repaired by the Contractor. The weight of each storage container shall be recorded before final acceptance test and after test has been completed and containers recharged. Submit test report for the final acceptance tests in booklet form, upon completion of testing. Report shall document test results including repairs and adjustments made, and final test results. The weight of each storage container shall be recorded before final acceptance test and after test has been completed and containers recharged.
SECTION 21 21 03.00 10 Page 5
3.4 FIELD TRAINING
Submit proposed schedule for field training, at least 2 weeks before the start of related training. Conduct a training course for operating and maintenance personnel as designated by the Contracting Officer. Training shall be provided for a period of 6 hours of normal working time and shall start after the system is functionally complete and after the Final Acceptance Test. The field instruction shall cover all of the items contained in the approved Operation and Maintenance Instructions. Submit 4 manuals listing step-by-step procedures required for system actuation (automatic and manual), recharging, and routine maintenance, at least 2 weeks before field training. The manuals shall include the manufacturer's name, model number, parts list, list of tools and parts that should be kept in stock by the owner for routine maintenance including the name of a local supplier, simplified wiring and control diagrams, troubleshooting guide, and recommended service organization (including address and telephone number). Service organization shall be capable of providing 4 hour onsite response to a service call on an emergency basis.
-- End of Section --