W9123621B2001 0004 Amendment Ord and Weitzel Gate Solicitation 08052021.pdf

PDF 431 KB Posted

Attached to
Ord & Wietzel Gate Relocation
Solicitation number
W9123621B2001
Issued by

About this file

This document is a government file containing an amendment to a federal contract solicitation and related questions and answers. The solicitation is for the reconstruction of the Ord & Weitzel pedestrian gate and columns at Arlington National Cemetery near their original location. The project involves restoring individual stone column elements and reconstructing them on new niche walls and bases to form the new gate entryway. The amendment provides responses to contractor questions, updated specifications and documents, and the latest Davis-Bacon wage determinations. Eligible contractors must submit bids in response to solicitation number W91236-21-B-2001 for the gate relocation construction work at Arlington National Cemetery by the specified deadline. The Department of the Army Corps of Engineers Engineering District in Norfolk is the contracting agency for this project.

View the file

Other files

File Type Posted
B.01.02 - Ord and Weitzel Bid Abstract.pdf PDF
W9123621B2001 0005 Amendment Ord and Weitzel Gate Solicitation.pdf PDF
Attachment 17 04 30 00 Mason Masonry Construction.pdf PDF
Attachment 14 - GEO Tech Doc - 12 93 00.pdf PDF
Attachment 12 - P1010931.pdf PDF
Attachment 13 Photo Sep 29 12 45 37 PM.pdf PDF
Attachment 5 - Ord and Weitzel Gate Photos .pdf PDF
Attachment 11- Stone Mason Report.pdf PDF
Attachment 16 - 04 30 00 Mass Masonry Wall Construction.pdf PDF
Attachment 15 - Section 32 31 13.53 Divison 32 - Exterior Improvements.pdf PDF
Attachment 4 - 01 45 00.00.10 .pdf PDF
Attachment 9 - 00 22 13.00 20 (Supplementary Instructions to Offerors).pdf PDF
Attachment 10 - P1010868.pdf PDF
Attachment 6 - 31 63 16 Auger Cast Grout Piles.pdf PDF
Attachment 7 VB16 137G Ord and Weitzel Area Road Repair Report.pdf PDF
Attachment 8 - 01 11 00 Summary of Work.pdf PDF
21-B-2001 Amendment 3.pdf PDF
21-B-2001 Amendment 4.pdf PDF
O and W Gate PreBid Site Survey July 14 2021.pdf PDF
W9123621B2001 0001 Amendment Ord and Weitzel Gate Solicitation.pdf PDF
Ord Weitzel Spec 04 10 00 - Amendment _001 (003).pdf PDF
RTA Submittal Specifications Arlington National Cemetery_1.pdf PDF
W9123621B2001 Ord and Weitzel Gate Solicitation.pdf PDF
RTA Submittal Drawings Ord and Weitzel 2020 0612.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to accomplish the follow ing:

1. To provide the responses to ProjNet questions

2. Provide updated technical documents in correspondence to the ProjNet questions and respoonses (denoted in red text).

3. To include most recent Wage Rates.

All other terms and conditions remain unchanged

1. CONTRACT ID CODE PAGE OF PAGES

J 1 14

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Aug-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9123621B2001

X 9B. DATED (SEE ITEM 11)

17-Jun-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Aug-2021

CODE

USACE, NORFOLK DISTRICT OFFICE

CONTRACTING OFFICE

803 FRONT STREET

NORFOLK VA 23510-1011

W91236 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123621B2001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 4

Amendment 0004 is issued to provide the following:

1. To provide responses to ProjNet questions.

2. To provided updated technical documents in correspondence to the ProjNet questions and responses.

3. To include updated Wage Rates.

All other terms and conditions remain unchanged.

Attachments:

The following attachments are incorporated into this amendment:

Attachment 4 – 01 45 00.00.10 Quality Control, 10 pages (Amendment 4) Attachment 5 – O and W Access Gate Photos, 3 pages (Amendment 4) Attachment 6 - 31 63 16 (Auger Cast Grout Piles), 9 pages.pdf (Amendment 4) Attachment 7 - VB16-137G Ord & Weitzel Area Road Repair Report dated Aug 16, 2016, 120 pages (Amendment 4) Attachment 8 - 01 11 00 Summary of Work,.pdf, 4 pages (Amendment 4) Attachment 9 - 00 22 13.00 20 (Supplementary Instructions to Offerors).pdf, 2 pages (Amendment 4) Attachment 10 - P1010868.pdf, 1 page (Amendment 4) Attachment 11 – Stone Mason Report.pdf, 16 Pages (Amendment 4) Attachment 12 - P1010931.pdf dated 2 August 2021, 1 page (Amendment 4) Attachment 13 - Photo Sep 29, 12 45 37 PM.pdf dated 2 August 2021, 1 page (Amendment 4) Attachment 14 – GEO Tech Doc 12 93 00.pdf, 10 pages (Amendment 4) Attachment 15 - Section 32 31 13.53 Divison 32 Exterior Improvements.pdf dated April 2021, 20 pages (Amendment 4)

ProjNet Inquiries:

ID 9302639

In the RFP it states "The below information will be requested of the apparent low bidder. This information is required to be responsive to the Invitation for Bid. To efficiently and expeditious award the resultant contract, it is required that bidders provide the below information with their bid: 1) current commitments and expected dates of completion, 2)one signed bank reference, 3)and the latest three complete fiscal year financial statements for the prime contractor."

Are all bidders required to submit those three items with their proposal? Is just the apparent lower bidder required to provide those three items during award?

Government Response

Please see amendment 0001 which provided additional clarification for the pre award survey information.

ID 9323852

Drawing S101A and specification section 316316 call for the auger cast grout piles to support the gate columns.

Please let us know if we can use the alternate DSD Pile System as the propose and delegate design piles, which will meet and/or exceed the structural support requirements.

Government Response

Deviation from the specifications and design drawings is not permitted during the bidding process. Changes can be discussed after the bidding phase during construction.

ID 9323857

Drawing CU101 shows 15" RCP with new two storm structures. Please confirm those items are new work. If so, please provide their utility profiles.

Government Response

The profiles for both new 15" RCP pipes is shown on Sheet C-202.

ID 9323861

Drawing CU101 shows new 4" PVC WIFI conduit with handholes. However, drawing E101B does not indicate the 4" PVC WIFI conduit as new work. It only notes the new work for the communications conduit with junction box at the guard house. Which drawing is correct?

The 4" PVC WIFI conduit behind the new curb shown on CU101 is correctly labeled as new work.

ID 9325252

Drawing C101 to C105 show sod and topsoil in various locations. Drawing L101 and L102 only a few locations of sod placement. Please let us know which drawing to follow for sod installation.

Government Response

Drawings C101 to C105 show the locations of sod along Custis walk and around the guard house. Drawings L101 and L102 show sod installation around the guard house in the same locations as C101 but include landscape details.

Drawings L101 and L102 are to be used when installing sod north of Ord & Weitzel Drive around the guard house.

ID 9327837

Custis Walk Heavy Duty Concrete Paving Section - 4" Asphalt Stabilized Open-Graded Material Section 32 11 0 Table 1 (VDOT) is missing from the specification. It is not listed in the VDOT Roads and Bridges Specification either. Please advise as to the material design specifications.

Government Response

The 4" Open-Graded Material in Detail C5 is to be in accordance with VDOT Section 313 that is referenced in Specification 32 11 23.23 that includes Table 1. All Open-Graded Material shall meet these requirements. In addition, the contractor shall undercut and compact the subgrade a minimum of 14" below the heavy duty concrete paving section.

ID 9329500

These pages seem to be an already submitted and approved SWPPP. Please confirm that the contractor will need to provide an additional SWPPP to be filed with the State of VA under ANC's existing General Use Permit.

Government Response

The contractor is required to prepare and submit an additional SWPPP.

ID 9329711

Confirm the Government is requiring three full days of unscheduled shutdown to be included in the project schedule and manpower requirements onsite

The contractor is to allow for 3 days in which work will be prohibitive as specified.

ID 9329713

Confirm a full-time project manager will be required to be onsite at least 24 hours a week or three full business days.

Government Response

A project manager is required to be on site 3 days a week as specified.

ID 9329715

Confirm any tree or root trimming will be performed by the KTR and a certified Arborist and not by ANC.

Government Response

Correct, any tree or root trimming will be performed by the contractor and a certified arborist. An ANC arborist shall be present during this work.

ID 9329717

Confirm Spoils can be stored on the KTR laydown area as shown on CD101 and as directed on G-003 Note 16.

Government Response

Spoils may be placed in laydown areas but must not be stored higher than the protective fence.

ID 9329719

Confirm the 8ft high fence is to be a wood slatted fence painted green-

The 8-foot temporary construction fence is to have wood slats.

ID 9329720

Confirm no power is available for the KTR for a trailer onsite.

Confirmed no power is available for the KTR for a trailer onsite.

ID 9329721

Confirm Storm Water Piping ( RCP) Lines shall be tested for leakage by low pressure air or water testing or exfiltration tests, as appropriate, prior to completing backfill at all utility lines installed by the KTR this includes all piping sizes.

Government Response

Correct, storm drain pipes shall be tested as specified.

ID 9329722

Confirm Cracks with a width greater than 0.01 inches. An engineer must evaluate all pipes with cracks with a width greater than 0.01 inches but less than 0.10 inches to determine if any remediation or repair is required.

Government Response

Correct, and engineer shall evaluate cracks as specified.

ID 9329723

Confirm vibration monitoring by a professional engineer is not required but he following requirement is: Care shall be used with operating the compactors near existing structures and graves to avoid transmission of the vibrations that could cause settlement damage. The vibratory roller shall remain at least 25 feet away from existing structures and graves. These areas shall be compacted with small, hand-operated compaction equipment.

Correct, vibration monitoring is not required and the contractor shall take care in using compaction equipment as specified.

ID 9331281

Please reference Section 31 00 00.00 51, 3.11.1 and 3.11.2. If unsuitable subgrade conditions are found and undercutting and replacement with structural fill is required (up to 18"), please confirm this would be compensable extra work.

Government Response

The 18" undercut and replacement with structural fill is required under all new roadway pavement and is not considered extra work.

ID 9331298

Please confirm the contractor is furnishing the Carter Bluestone as described in Section 04 30 00.

Government Response

Contractor shall furnish Carter Bluestone.

ID 9331305

Please confirm where the stockpile of Government furnished Red Sandstone is located per 04 20 00, 2.2.2.2.b.

Government Response

Stockpile of Red Seneca Stone is located in the Section 77 lay down yard.

ID 9331317

Please confirm a Design Quality Manager as listed in Section 01 45 00.00 10, paragraph 3.4.1 is not required sine this is not a design-build project.

Government Response

Confirmed, a Design Quality Manager is not required. See attached specification.

ID 9331322

Is temporary fencing or barrier required around the plaza sidewalk work area even though there is minimal excavation being performed?

Fencing is required to keep unauthorized people from the site as specified.

ID 9331332

Please reference Section 01 11 00, 1.5. This section discusses a 14 day notice and also impacts of 10 minutes to 4 hours. Could you please provide some additional clarification with the meaning of "two calendar days where excavation and subsurface activity abeyance shall be imposed" and "Contractor shall allow for a maximum of three calendar days where construction activity is determined prohibitive."

Government Response

(a) The 2 calendar days refers to the contractor notice to USACE, that they are about to begin excavation. This completely, separate, from the 2 weeks needed to get an ANC excavation permit approved, once submitted (01 11 00, 1.8).

(b) Referring to temporary suspension of construction activities that may occur, within a given day, due a funeral or special event nearby the construction site. Suspension could be a little as 10 minutes, or as much as be 4 hours.

Assume an aggregate of 3 days for this type of delay.

ID 9331340

Is the contractor responsible for mowing and turf edging during the one year warranty period described n 32 05

33.00 51?

The contractor is responsible for mowing, edging, and maintenance until final acceptance by the Government.

ID 9331652

Is all reinforcing steel required to be galvanized per 03 20 00.00 10, 2.3.1?

Reinforcing steel need not be galvanized.

ID 9331653

Is there a cost for Common Card Access, badging and background checks?

Government Response

For temporary badging and background checks there should be no cost to the contractor, but call the JBMHH Visitor Control Center to confirm at: 703-696-0186/0185

ID 9331656

Please confirm the new 10" waterline shown on Sheet C-507 is the 16" waterline with steel casing.

Government Response

Correct, the 10" waterline shown on C-507 is the new 16" water line with steel casing.

ID 9331657

It appears the 6" waterline shown on Sheet C-507 becomes abandon once relocated per CU102. Does that section of abandon line remain in place or does it need to be removed?

Government Response

The abandoned sections of the 6" water line do not need to be removed unless in conflict with the new work.

ID 9331658

Please confirm that a test panel is not required per 03 11 13.00 10, 1.3 as there is no exposed structural concrete.

Test panel is not required.

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been added by full text:

WAGE RATES, JULY 2021

"General Decision Number: VA20210013 07/23/2021

Superseded General Decision Number: VA20200013 State: Virginia Construction Type: Building

County: Arlington County in Virginia. Includes the independent city of Alexandria*

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/01/2021 1 01/08/2021 2 04/23/2021 3 05/07/2021 4 05/28/2021 5 06/04/2021 6 07/23/2021

ASBE0024-006 04/01/2021

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR - MECHANICAL (Duct, Pipe & Mechanical System Insulation)......................$ 39.27 18.67+a

a. PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the day after Thanksgiving and Christmas Day provided the employee works the regular workday before and after the paid holiday.

ASBE0024-009 04/01/2021

Rates Fringes

FIRESTOPPER......................$ 29.41 8.73+a

Includes the application of materials or devices within or around penetrations and openings in all rated wall or floor assemblies, in order to prevent the pasage of fire, smoke of other gases. The application includes all components involved in creating the rated barrier at perimeter slab edges and exterior cavities, the head of gypsum board or concrete walls, joints between rated wall or floor components, sealing of penetrating items and blank openings.

a. PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the day after Thanksgiving and Christmas Day provided the employee works the regular work day before and after the paid holiday.

BOIL0045-003 01/01/2017

Rates Fringes

BOILERMAKER......................$ 32.72 25.26

BRVA0001-008 05/02/2021

Rates Fringes

BRICKLAYER.......................$ 34.00 12.59

BRVA0001-009 05/02/2021

Rates Fringes

MASON - STONE....................$ 40.81 19.43

BRVA0001-011 05/02/2021

Rates Fringes

MARBLE FINISHER..................$ 25.81 11.55

* ELEC0026-003 06/07/2021

Rates Fringes

ELECTRICIAN (Includes Low Voltage Wiring and Installation of Alarms and Sound and Communication Systems).........................$ 49.00 20.26

IRON0005-010 06/01/2021

Rates Fringes

IRONWORKER.......................$ 33.90 24.19

PAIN0051-034 06/01/2020

Rates Fringes

GLAZIER..........................$ 28.02 12.55

PAIN0051-035 06/01/2020

Rates Fringes

PAINTER

Brush, Roller and Spray.....$ 25.05 11.17

PAIN0051-036 06/01/2020

Rates Fringes

DRYWALL FINISHER/TAPER...........$ 25.05 11.17

PLUM0005-014 08/01/2020

Rates Fringes

PLUMBER..........................$ 44.92 19.91+a a.PAID HOLIDAYS: New Year's Day, Martin Luther King's Birthday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day and the day after Thanksgiving and Christmas Day.

PLUM0602-016 08/01/2020

Rates Fringes

PIPEFITTER (Includes HVAC Pipe, Unit and Temperature Controls Installations)..........$ 44.14 22.64+a

a. PAID HOLIDAYS: New Year's Day, Martin Luther King's Birthday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day and the day after Thanksgiving and Christmas Day.

SFVA0669-006 04/01/2021

Rates Fringes

SPRINKLER FITTER (Fire Sprinklers)......................$ 36.95 24.12

SHEE0100-004 11/01/2020

Rates Fringes

SHEET METAL WORKER (Includes HVAC Duct Installation)..........$ 42.67 21.33+a

a. PAID HOLIDAYS: New Year's Day, Martin Luther King's Birthday, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and Christmas Day

SUVA2013-025 01/11/2016

Rates Fringes

BRICK POINTER/CAULKER/CLEANER....$ 19.68 0.00

CARPENTER, Includes Acoustical Ceiling Installation, Drywall Hanging, and Form Work...........$ 23.36 5.20

CEMENT MASON/CONCRETE FINISHER...$ 21.94 3.36

FLOOR LAYER: SOFT FLOORS........$ 18.75 0.00

IRONWORKER, REINFORCING..........$ 27.46 8.71

LABORER: Common or General, including brick mason tending and cement mason tending.........$ 15.55 2.44

LABORER: Pipelayer..............$ 16.81 4.26

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 23.50 4.50

OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 18.95 4.03

OPERATOR: Bulldozer.............$ 21.99 4.98

OPERATOR: Crane.................$ 30.45 4.14

OPERATOR: Forklift..............$ 21.56 7.57

OPERATOR: Loader................$ 22.26 3.57

OPERATOR: Roller................$ 16.25 4.88

ROOFER...........................$ 15.83 3.06

TILE FINISHER....................$ 23.40 0.00

TILE SETTER......................$ 27.80 10.25

TRUCK DRIVER: Dump Truck........$ 19.22 2.58

WATERPROOFER.....................$ 21.75 1.57

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH- 0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including request for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

The following have been modified:

ATTACHMENTS

1. RTA Submittal Ord and Weitzel 2020 0612 dated June 12, 2020, 64 pages

2. RTA Submittal Specifications Arlington National Cemetery dated June 12, 2020, 1021 pages

3. Ord Weitzel Spec 04 10 00 – Amendment #001 dated 11/15 16 pages

4. Attachment 4 – 01 45 00.00.10 Quality Control, 10 pages (Amendment 4)

5. Attachment 5 – O and W Access Gate Photos, 3 pages (Amendment 4)

6. Attachment 6 - 31 63 16 (Auger Cast Grout Piles), 9 pages.pdf (Amendment 4)

7. Attachment 7 - VB16-137G Ord & Weitzel Area Road Repair Report dated Aug 16, 2016, 120 pages

(Amendment 4)

8. Attachment 8 - 01 11 00 Summary of Work,.pdf, 4 pages (Amendment 4)

9. Attachment 9 - 00 22 13.00 20 (Supplementary Instructions to Offerors).pdf, 2 pages (Amendment 4)

10. Attachment 10 - P1010868.pdf, 1 page (Amendment 4)

11. Attachment 11 – Stone Mason Report.pdf, 16 Pages (Amendment 4)

12. Attachment 12 - P1010931.pdf dated 2 August 2021, 1 page (Amendment 4)

13. Attachment 13 - Photo Sep 29, 12 45 37 PM.pdf dated 2 August 2021, 1 page (Amendment 4)

14. Attachment 14 – GEO Tech Doc 12 93 00.pdf, 10 pages (Amendment 4)

15. Attachment 15 - Section 32 31 13.53 Divison 32 Exterior Improvements.pdf dated April 2021, 20 pages

(Amendment 4)

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title File Drawing No.

16. RTA Submittal Ord and Weitzel 2020 0612 dated June 12, 2020, 64 pages

17. RTA Submittal Specifications Arlington National Cemetery dated June 12, 2020, 1021 pages

18. Ord Weitzel Spec 04 10 00 – Amendment #001 dated 11/15 16 pages

19. Attachment 4 – 01 45 00.00.10 Quality Control, 10 pages (Amendment 4)

20. Attachment 5 – O and W Access Gate Photos, 3 pages (Amendment 4)

21. Attachment 6 - 31 63 16 (Auger Cast Grout Piles), 9 pages.pdf (Amendment 4)

22. Attachment 7 - VB16-137G Ord & Weitzel Area Road Repair Report dated Aug 16, 2016, 120 pages

(Amendment 4)

23. Attachment 8 - 01 11 00 Summary of Work,.pdf, 4 pages (Amendment 4)

24. Attachment 9 - 00 22 13.00 20 (Supplementary Instructions to Offerors).pdf, 2 pages (Amendment 4)

25. Attachment 10 - P1010868.pdf, 1 page (Amendment 4)

26. Attachment 11 – Stone Mason Report.pdf, 16 Pages (Amendment 4)

27. Attachment 12 - P1010931.pdf dated 2 August 2021, 1 page (Amendment 4)

28. Attachment 13 - Photo Sep 29, 12 45 37 PM.pdf dated 2 August 2021, 1 page (Amendment 4)

29. Attachment 14 – GEO Tech Doc 12 93 00.pdf, 10 pages (Amendment 4)

30. Attachment 15 - Section 32 31 13.53 Divison 32 Exterior Improvements.pdf dated April 2021, 20 pages

(Amendment 4)

(End of clause)

The following have been deleted:

WAGE RATES

(End of Summary of Changes)

File details come from the government source that posted it. Updated .