Attachment 8 - 01 11 00 Summary of Work.pdf

PDF 15 KB Posted

Attached to
Ord & Wietzel Gate Relocation Federal contract opportunity
Solicitation number
W9123621B2001
Issued by
Department of the Army Corps of Engineers Engineering District Norfolk

About this file

This document provides the scope of work for a construction project at Arlington National Cemetery. The project will reconstruct the Ord and Weitzel Gate and Columns and associated site work. Specific tasks include removing and replacing pavement, curbs, and utilities; constructing a new concrete walkway; and grading and landscaping. The work must be performed with minimal disruption to cemetery operations and ceremonies. The performance period is 362 calendar days, with construction taking place over 242 days following a 60-day submittal period. The Department of the Army Corps of Engineers is the contracting agency for this project located at Arlington National Cemetery.

View the file

Other files for this federal contract opportunity

Other files attached to Ord & Wietzel Gate Relocation, newest first.
File Type Posted
B.01.02 - Ord and Weitzel Bid Abstract.pdf PDF
W9123621B2001 0005 Amendment Ord and Weitzel Gate Solicitation.pdf PDF
Attachment 17 04 30 00 Mason Masonry Construction.pdf PDF
Attachment 16 - 04 30 00 Mass Masonry Wall Construction.pdf PDF
Attachment 14 - GEO Tech Doc - 12 93 00.pdf PDF
Attachment 12 - P1010931.pdf PDF
Attachment 11- Stone Mason Report.pdf PDF
Attachment 10 - P1010868.pdf PDF
Attachment 7 VB16 137G Ord and Weitzel Area Road Repair Report.pdf PDF
Attachment 6 - 31 63 16 Auger Cast Grout Piles.pdf PDF
Attachment 4 - 01 45 00.00.10 .pdf PDF
W9123621B2001 0004 Amendment Ord and Weitzel Gate Solicitation 08052021.pdf PDF
Attachment 15 - Section 32 31 13.53 Divison 32 - Exterior Improvements.pdf PDF
Attachment 9 - 00 22 13.00 20 (Supplementary Instructions to Offerors).pdf PDF
Attachment 13 Photo Sep 29 12 45 37 PM.pdf PDF
Attachment 5 - Ord and Weitzel Gate Photos .pdf PDF
21-B-2001 Amendment 3.pdf PDF
21-B-2001 Amendment 4.pdf PDF
O and W Gate PreBid Site Survey July 14 2021.pdf PDF
W9123621B2001 0001 Amendment Ord and Weitzel Gate Solicitation.pdf PDF
W9123621B2001 Ord and Weitzel Gate Solicitation.pdf PDF
RTA Submittal Drawings Ord and Weitzel 2020 0612.pdf PDF
Ord Weitzel Spec 04 10 00 - Amendment _001 (003).pdf PDF
RTA Submittal Specifications Arlington National Cemetery_1.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ord and Weitzel Gate Reconstruction Arlington National Cemetery Task Order: W91236-14-0028-21

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM E2114 (2008) Standard Terminology for Sustainability Relative to the Performance of Buildings

1.2 DEFINITIONS

Definitions pertaining to sustainable development are as defined in ASTM E2114, and Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS, and as specified.

a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.

b. "Sustainability" is the balance of environmental, economic, and societal considerations.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Upon receipt of Government Furnished Equipment, the Contractor shall submit records in accordance with paragraph entitled, "Government Furnished Property," of this section.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

1.4.1 BACKGROUND

Arlington National Cemetery is our nation's most sacred shrine and the final resting place for our most revered military and civilian leaders.

The Cemetery receives millions of visitors each year - including visits from the President of the United States, other heads of state, family members of the deceased, and millions of tourists from around the world.

SECTION 01 11 00 Page 1

Six thousand or more funerals are conducted yearly - in addition to over 2,000 other ceremonies, such as commemorations, wreath ceremonies, and head-of-state visits. These ceremonies and funerals often receive the intense focus of the press and other media. Because of Arlington's special significance and the attention it receives, strict adherence to these specifications is essential. Failure to meet specifications will have a negative impact on our nation's image and will not be tolerated. The successful Contractor forms a true partnership with the federal government to ensure those who served our nation are properly honored.

This project will help ANC to continue to meet the mission of laying to rest those who have served our nation with dignity and honor, treating their families with respect and compassion, and connecting guests to the rich tapestry of the cemetery's living history, while maintaining these hallowed grounds befitting the sacrifice of all those who rest here in quiet repose.

1.4.2 Project Description

The project will reconstruct the Ord & Weitzel Gate and Columns, along with associated pedestrian paving, landscaping, and construction of a guard house. The work also includes grading, asphalt pavement, aggregate base, drainage improvements, curb and gutter, utility relocations and other related work. The existing pavement and curbs will be removed and new curb and gutter set in a similar offset and elevation as indicated on the cross sections. Utility relocations include relocating existing water mains, yard hydrants and installing new drinking fountains. The existing asphalt pavement along custis walk will be removed and a concrete walk constructed.

1.5 WORK RESCHEDULING

There are restrictions set in place for this project to ensure minimal interference with funerals and ceremonies that take place every year at the facility. Reference section 01 30 00.10, paragraph 1.9.10 for all non-work days.

Contracting Officer reserves the right to change these restrictions at any time during the period of performance. The Government will notify the Contractor of pending changes within 14 calendar days before a restriction is changed, except that the government will provide notification within two calendar days where excavation and subsurface activity abeyance shall be imposed.

Contractor shall allow for a maximum of three calendar days where construction activity is determined prohibitive. In most instances requiring work rescheduling the time periods will range from 10 minutes to 4 hour delay.

1.6 OCCUPANCY OF PREMISES

The site area around the construction site will be occupied during performance of work under this Contract.

Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, use of approaches, and egress from the site.

SECTION 01 11 00 Page 2

a. See Attachment "CONTRACT REQUIREMENTS PACKAGE ANTITERRORISM/OPERATIONS SECURITY REVIEW COVER SHEET" for ANC security draft of the Antiterrorism/Operations Security Review.

1.7 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

c. Remove all temporary construction access/egress elements and return any alterations made during the construction period to provide temporary construction access/egress elements to pre-existing condition.

1.7.1 Damage to Government Property, Injuries, or Death

At the Government's discretion, the Contractor shall either repair or replace property, or reimburse the Government for property damage. The Contractor shall be aware that Government property - beyond standard structures and equipment - also includes headstones, monuments, floral decorations placed by visitors and next of kin, trees, beds, and turf (for example, wounded trees, scalped turf, new or existing sod as well as headstones, shall be repaired or replaced at no additional cost to the Government).

1.8 LOCATION OF UNDERGROUND FACILITIES

Obtain digging permits prior to start of excavation by contacting the Contracting Officer 14 calendar days in advance. A completed Miss Utility locate is required, prior to receiving a dig permit. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground, or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.8.1 Notification Prior to Excavation

Notify the Contracting Officer at least 48 hours prior to starting excavation work. Contractor is responsible for marking all utilities not marked by Miss Utility.

1.9 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

The Contractor shall safeguard all Government property provided for Contractor use during the course of the contract. At the close of each

SECTION 01 11 00 Page 3 work period, Government facilities, equipment, and materials furnished shall be secured.

1.10 PERIOD OF PERFORMANCE

The period of performance shall be 362 calendar days from the issuance of notice to proceed. The period of performance is based upon the construction durations provided below for each construction phase including adverse weather as outlined in Section 01 30 00.10.

Preconstruction Submittals - and Shop Drawing Reviews - 60 Days Construction Duration - 242 Days Close out and punch list items - 60 Days

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 4

File details come from the government source that posted it. Updated .