This technical report documents stone restoration work performed on the Ord and Weitzel Pedestrian Gate at Arlington National Cemetery. Speweik Preservation conducted conservation of individual stone elements including columns, capitals, bases, and urns. Extensive Dutchman repairs were required on columns that sustained damage from prior deconstruction and transport. The restored stone elements will be reconstructed in their original locations as part of the W91236-21-B-2001 solicitation from the Department of the Army Corps of Engineers Norfolk District. This project will relocate the Ord and Weitzel Gate and Columns near their original site on Ord and Weitzel Drive at Arlington National Cemetery.

View the file

Other files for this federal contract opportunity

Other files attached to Ord & Wietzel Gate Relocation, newest first.
File Type Posted
B.01.02 - Ord and Weitzel Bid Abstract.pdf PDF
Attachment 17 04 30 00 Mason Masonry Construction.pdf PDF
W9123621B2001 0005 Amendment Ord and Weitzel Gate Solicitation.pdf PDF
Attachment 13 Photo Sep 29 12 45 37 PM.pdf PDF
Attachment 5 - Ord and Weitzel Gate Photos .pdf PDF
Attachment 15 - Section 32 31 13.53 Divison 32 - Exterior Improvements.pdf PDF
Attachment 9 - 00 22 13.00 20 (Supplementary Instructions to Offerors).pdf PDF
Attachment 8 - 01 11 00 Summary of Work.pdf PDF
Attachment 16 - 04 30 00 Mass Masonry Wall Construction.pdf PDF
Attachment 14 - GEO Tech Doc - 12 93 00.pdf PDF
Attachment 12 - P1010931.pdf PDF
Attachment 10 - P1010868.pdf PDF
Attachment 7 VB16 137G Ord and Weitzel Area Road Repair Report.pdf PDF
Attachment 6 - 31 63 16 Auger Cast Grout Piles.pdf PDF
Attachment 4 - 01 45 00.00.10 .pdf PDF
W9123621B2001 0004 Amendment Ord and Weitzel Gate Solicitation 08052021.pdf PDF
21-B-2001 Amendment 3.pdf PDF
21-B-2001 Amendment 4.pdf PDF
O and W Gate PreBid Site Survey July 14 2021.pdf PDF
W9123621B2001 0001 Amendment Ord and Weitzel Gate Solicitation.pdf PDF
RTA Submittal Specifications Arlington National Cemetery_1.pdf PDF
Ord Weitzel Spec 04 10 00 - Amendment _001 (003).pdf PDF
RTA Submittal Drawings Ord and Weitzel 2020 0612.pdf PDF
W9123621B2001 Ord and Weitzel Gate Solicitation.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

These technical drawings were prepared as a compilation of the historic stone repairs

Speweik Preservation

(SPC)

performed on specific stone pieces during stone conservation according to the

SOW.

The attenuation of the stone column pieces from the column base block to the top pieces O40 and

W is approximately inches.

This equates to ft.

4-‐1/4” in circumference.

SPC

discovered during our stone conservation operations that a discrepancy in the total height of the monument

Ht.

12-‐0”

Ht.

6’-‐8”

Ht.

21-‐3/4” Ht.

21-‐3/4”

Ht.

32-‐3/4”

Ht.

47-‐1/2”

Ht.

46-‐3/4”

Ht.

50-‐0”

Ht.

50-‐0”

Ht.

50-‐0”

Ht.

12-‐1/4”

Ht.

6’-‐8”

Ht.

11.75” Ht.

11-‐75”

Ht.

43-‐0”

Ht.

46-‐1/2

Ht.

46-‐3/4”

Ht.

12-‐1/4”

Ht.

46-‐3/4”

Ht.

46-‐3/4”

Ht.

45-‐1/2”

Ht.

12-‐0”

ORD-‐WEITZEL

STONE

CONSERVATION

DRAWINGS

WITH

NARRATIVE

exists.

The Weitzel column is shorter by 3-‐1/4”.

This was found in a mathematical error on the height of stone #W31.

The original Architectural Report from the listed the stone drum at a height of 48-‐3/4”.

SPC

and

CASE

Forensics confirmed the #W31 actually measures 45-‐1/2” in height.

The 1970s report states

ORD

is 277” and

WEITZEL

is 277-‐1/4” in height.

Not sure what to think.

Image of the War Department Building before it was dismantled and removed to Arlington

National Cemetery.

Image:

Date Unknown.

The six (6) stone columns and entablature were repurposed into two entrance gates.

One containing two (2) freestanding stone columns crowned with beautiful limestone Urns known as the

ORD-‐WEITZEL

GATE.

The other gate consisting of the four (4) remaining stone columns crowned with an ornate entablature.

It became famously known to honor General

SHERIDAN

GATE

among other Generals of the Civil War.

The gates were constructed in 1879.

These technical drawings were prepared as a compilation of the historic stone repairs

Speweik Preservation

(SPC)

performed on specific stone pieces during stone conservation according to the

SOW.

Two of the stone columns used from the War Department Building from the previous image.

The gate was constructed in 1879.

The date of this image is unknown however it was sometime after when the Generals names were engraved into the stone columns.

This image of Ord-‐Weitzel

Gate shows a lime wash finish as it appeared in the early twentieth century.

It appears from this image that the capitals, pedestals and Urns were not lime washed at the time of this photo.

Note:

The drawings in this report are organized in sequential order of assembly, starting with

General Ord’s Column followed by General Weitzel’s Column.

The drawings are laid out in order from the stylobates to the Urns.

Additional Note:

If a historic stone component is not listed within these drawings it indicates no repairs were necessary.

ORD-‐WEITZEL

STONE

CONSERVATION

DRAWINGS

WITH

NARRATIVE

ORD

STYLOBATE

DUTCHMAN

REPAIR

#33A:

The Stylobate base block required careful removal of a previous cement repair.

The parent Aquia Creek Sandstone was prepared to receive a

Dutchman repair that was harvested from the same Aquia Creek Sandstone from the Weitzel

Column Drum #W44.

The

SPC

stone carver returned the original stone chisel marks as would have been originally found in the finished repair.

The opening shown below the Dutchman represented in red is the original slot that was cut from the historic stone in order to receive the iron gates that once were part of the entrance to the cemetery.

These technical drawings were prepared as a compilation of the historic stone repairs

Speweik Preservation

(SPC)

performed on specific stone pieces during stone conservation according to the

SOW.

ORD

COLUMN

BASE

DUTCHMAN

REPAIR

#34B:

A significant amount of original Aquia Creek

Sandstone was damaged in this Column Base.

The red indicates the size of the Dutchman repair.

SPC

obtained a selected structurally sound piece of harvested stone for this repair due to the consideration of the proximity to the structural loads it may endure in its position within the column.

This piece required the

SPC

masons to reposition the stone and turn it over in order to make the necessary Dutchman repairs.

ORD-‐WEITZEL

STONE

CONSERVATION

DRAWINGS

WITH

NARRATIVE

ORD

COLUMN

DRUM

#39:

SPC

has organized these drawings in order of the reconstruction of the gate.

This stone column drum represents the very first stone, which will set on the column base stone in the reconstruction operations.

The Dutchman repairs were minimal to this first stone.

These technical drawings were prepared as a compilation of the historic stone repairs

Speweik Preservation

(SPC)

performed on specific stone pieces during stone conservation according to the

SOW.

ORD

STONE

#43:

This stone had Dutchman repairs to top only and noted surface delamination, which were carefully removed through European chisel dancing techniques.

Dutchman repair from the original Aquia Creek Sandstone obtained from Weitzel #44 stone drum.

Again, the red marks indicate the location of the Dutchman repair with the dimensions associated to each repair.

ORD-‐WEITZEL

STONE

CONSERVATION

DRAWINGS

WITH

NARRATIVE

GENERAL

ORD

STONE

#42:

This stone had extensive Dutchman repairs to top and bottom edges and noted surface delamination, which were carefully removed through European chisel dancing techniques.

SPC

attempted to save a deep pocket of stone deterioration at the face of the stone near the General Ord’s name, but could not.

Unfortunately, the material substrate was deteriorated to a depth beyond the redressing option.

SPC

opted to carefully prepare and place a

Dutchman repair from the original Aquia Creek Sandstone obtained from Weitzel #44 stone drum.

These technical drawings were prepared as a compilation of the historic stone repairs

Speweik Preservation

(SPC)

performed on specific stone pieces during stone conservation according to the

SOW.

ORD

COLUMN

DRUM

#38:

This Historic Stone drum was damaged during transport and possibly during deconstruction multiple times.

SPC

repaired it using the Dutchman techniques with geometric keys secured with lime putty.

Both the top and bottom of this stone column drum was damaged.

Dimensions can be seen on the red color indicated.

ORD-‐WEITZEL

STONE

CONSERVATION

DRAWINGS

WITH

NARRATIVE

ORD

Column Stone 40:

This stone is the six stone and completes the column.

This stone serves as the base for the capital.

The stone was significantly damaged from previous deconstruction efforts.

As indicated by the red colors a substantial amount of stone was lost during the life of this particular piece.

Fortunately

SPC

was able to harvest the needed stone to make the necessary repairs from the Aquia Creek Sandstone from the Weitzel column drum #44.

These technical drawings were prepared as a compilation of the historic stone repairs

Speweik Preservation

(SPC)

performed on specific stone pieces during stone conservation according to the

SOW.

WEITZEL

COLUMN

DRUM

#30:

This stone was damaged at the top of the unit and required only minimal intervention with a Dutchman Repair.

ORD-‐WEITZEL

STONE

CONSERVATION

DRAWINGS

WITH

NARRATIVE

WEITZEL

STONE

COLUMN

DRUM

#32:

This column drum was located second from the top of the position in the monument.

This may explain why a considerable amount of damage was noted.

SPC

stone carvers carried out careful Dutchman repair techniques to every side of the stone masonry unit both top, bottom and sides.

These technical drawings were prepared as a compilation of the historic stone repairs

Speweik Preservation

(SPC)

performed on specific stone pieces during stone conservation according to the

SOW.

WEITZEL

COLUMN

DRUM

(TOP)

#37:

Stone column drum W was by far the most difficult historic stone to repair.

The significance of the amount of material which was lost required

SPC

stone carvers to come up with a strategy to create a well-‐bonded mechanical key without the use of metal anchors of epoxy or bonding agents other than lime putty.

The use of a Dutchman

European key was used to secure the Dutchman to the parent stone.

The technique used a geometric shape in combination with a dovetail box-‐cut into the stone creating an invisible joint.

ORD-‐WEITZEL

STONE

CONSERVATION

DRAWINGS

WITH

NARRATIVE

ORD

WEITZEL

CAPITALS

#102 and #103:

The stone capitols proved to be the most difficult aspect of the project.

Removing the paint from the stone intricacies was most taxing.

We stabilized the loose pieces, filled cracks and holes, re-‐carved small areas.

SPC

used the ring test to determine the stability of the historic stone.

We are pleased with the results in comparison to what we started with and in comparison to the four that remain for Sheridan.

These technical drawings were prepared as a compilation of the historic stone repairs

Speweik Preservation

(SPC)

performed on specific stone pieces during stone conservation according to the

SOW.

ORD

WEITZEL

PEDESTAL

BASES

#41 #41:

SPC

is please to inform the government that the pedestal bases were in the best possible condition out of all pieces recovered to date.

We were astonished at how well they cleaned up and they did not require one single Dutchman Repair.

ORD-‐WEITZEL

STONE

CONSERVATION

DRAWINGS

WITH

NARRATIVE

ORD

AND

WEITZEL

URNS:

Both urns will be mounted to their original position on the pedestals, after the restoration has taken place to restore the missing architectural details.

During the conservation phase the Urns were pinning together using titanium rods to begin the process of restoring them to their original condition.

SPC

is waiting for a response on proceeding with this restoration effort.