PROJECT: Aircraft Maintenance Instructional Building, Fort Eustis, VA. The project includes high bays w ith space for applied instruction classrooms. A supporting tool/equipment storage and issue space, as w ell as laboratories, instructor w ork and counseling areas, and appropriate supporting space to enable automated instruction, and aircraft part and equipment mock-up demonstration space. A ground support equipment storage facility and paved apron hardstand for aircraft support equipment storage and movement is also required.
This procurement is unrestricted
Magnitude of Construction: Betw een $25,000,000.00 and $100,000,000.00
Bid Due Date:
NAICS Code: 236220
*****THIS SOLICITATION CONTAINS DEFINITE RESPONSIBILITY CRITERIA, SEE SECTION 00 21 00*****
DUNS:________________________ Tax ID_______________________ Cage Code:_____________________
Contracting POC: Joy Wright; Email: joy.m.w right@usace.army.mil
X
JOY M WRIGHT 757-201-7145
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
22-Jun-2018
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________600 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________24 Jul 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USA ENGINEER DISTRICT, NORFOLK
803 FRONT STREET
NORFOLK VA 23510-1096
W91236
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
757-201-7183FAX:TEL: TEL: FAX:
W9123618B0018 50
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W9123618B0018
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Aviation Maintenance Training Facility
FFP
Construction of Aviation Maintenance Training Facility, complete as shown on the drawings and as specified, exclusive of CLINs 0002 thru 0006.
FOB: Destination
NET AMT
0002 1 Job All Site Work
FFP
All Site Work, complete as shown and specified within construction limits unless otherwise noted, exclusive of CLINs 0001 and 0003 thru 0006.
0003 1 Job OPTION Multipurpose Room Structure
FFP
OPTION 0001 - Construction of Multipurpose Room Structure, complete as shown on the drawings and as specified, exclusive of CLINs 0001 thru 0002 and 0004 thru 0006.
0004 1 Job OPTION Parking Lot
FFP
OPTION 0002 - Construction of Parking Lot, complete as shown on the drawings and as specified, exclusive of CLINs 0001 thru 0003 and 0005 thru 0006.
0005 1 Job OPTION Building Demo & incidental Site Work
FFP
OPTION 0003 - Building Demolition and incidental Site Work, complete as shown on the drawings and as specified exclusive of CLINs 0001 thru 0004 and 0006
0006 1 Job OPTION Ground Equipment Storage Structure
FFP
OPTION 0004 - Construction of larger Ground Equipment Storage Structure, complete as shown on the drawings and as specified, exclusive of CLINs 0001 thru 0005.
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
0002 N/A N/A N/A N/A
0003 N/A N/A N/A N/A
0004 N/A N/A N/A N/A
0005 N/A N/A N/A N/A
0006 N/A N/A N/A N/A
Section 00 21 00 - Instructions
A. PROJECT DESCRIPTION
The project includes high bays with space for applied instruction classrooms. A supporting tool/equipment storage and issue space, as well as laboratories, instructor work and counseling areas, and appropriate supporting space to enable automated instruction, and aircraft part and equipment mock-up demonstration space. A ground support equipment storage facility and paved apron hardstand for aircraft support equipment storage and movement is also required.
Unique aspects of the project include the following:
1. Four high bay training areas, approximately 89 feet x 189 feet x 40 feet clear height
2. Steel framed construction
3. Heavy hot rolled long span steel roof trusses
4. Bolted truss gusset construction
5. Custom bolted connections
6. Multiple overhead crane systems, 3 - ton minimum per crane
7. Deep foundations
8. Multiple construction crane critical lifts.
B. PROJECT DURATION
Work shall be complete within 600 calendar days from receipt of the Notice to Proceed (NTP).
C. BIDDER QUESTIONS AND COMMENTS
All questions and/or comments should reach the above referenced Contracting Office via ProjNet no later than 14 July 2018, in order that they may be given consideration or actions taken prior to receipt of offers.
Technical inquiries and questions relating to bid procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue. From this page you may view all bidder inquiries or add inquiry. Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
The Solicitation Number is : W91236-18-B-0018 The Bidder Inquiry Key is: 2JX82X-T58J7K
The Bidder Inquiry System will be unavailable for new inquires 7 days prior to bid opening in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
D. BID SUBMISSION
1. Hand-carried Bids/Offers must be delivered to the Contract Specialist or Contracting Officer located at the US Army Corps of Engineers Norfolk District:
803 FRONT STREET
Norfolk, VA 23510-1011 Attn: Contracting Office Joy Wright
Not Later than 2:00 PM EST on Thursday, 24 July 2018. Bids/Offers will only be accepted by contracting personnel. Guards are not authorized to accept Bids/Offers on behalf of the Government.
Norfolk District has a security gate located on Fort Norfolk on Front Street and requires all occupants of the vehicle to have a valid driver’s license for entry. Parking is limited. Firearms are not permitted on the installation. Offerors are cautioned to allow sufficient time for travelling over the causeway or ferry. Neither will constitute Government-caused delay.
2. Mail:
Bids shall specify the following information:
YOUR FIRM’S NAME
FIRM POINT OF CONTACT (POC) NAME
FIRM POC E-MAIL ADDRESS
FIRM POC PHONE NUMBER
Bids shall be submitted to the below address not later than 2:00 PM EST on Thursday, 14 June 2018.
One (1) ORIGINAL AND One (1) ELECTRONIC (DISC) COPY SHALL BE SUBMITTED BY EACH
OFFEROR.
Attn: Contracting Office Joy Wright USACE Norfolk District
803 FRONT STREET
Norfolk, VA 23510-1011
E. BID GUARANTEE
A Bid Guarantee will be required for this solicitation. The penal sum of the bond for the task order will be required as stated in provision 52.228-1, Bid Guarantee. Scanned copy submission of the bid bond is required.
F. BID EVALUATION AND AWARD
The Government will evaluate bids in response to this solicitation based upon the Total Evaluated Price without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government considering only price and the price-related factors specified elsewhere in the solicitation. The Government may reject any or all bids and/or waive informalities or minor irregularities in bids received.
The Government will evaluate offers for award purposes by adding the total price for all optional items to the total price for the basic requirement.
G. AWARD TO RESPONSIBLE OFFEROR
1. DEFINITIVE RESPONSIBILITY CRITERIA
In accordance with FAR 9.104-1, the Contracting Officer will determine responsibility based on the standards defined therein. In addition, the Contracting Officer's responsibility determination also will based on the following Definitive Responsibility Criteria:
1. Whether the low bidder has demonstrated experience on three projects in which lifts of pre-positioned, pre-assembled hardware weighing 30 - 50 tons have been performed using multiple cranes working in unison.
2. Whether the low bidder has demonstrated experience on three projects in which heavy hot-rolled truss sections utilizing large gusset plate connections and high strength pre tensioned bolts.
3. Whether the low bidder has demonstrated experience on three projects in which deep pile foundations were utilized, piles driven deep into the ground and footings for the structural members of the building placed on top of the driven piles.
After bid opening, the apparent low bidder only will be required to submit documentation demonstrating past project experience responsive to the Definitive Responsibility Criteria within 3 days of the bid opening. The prime contractor may submit its past projects as a prime contractor in which the pertinent scope described in the Criteria was a part of the contract even if it was not self-performed by the prime. In addition, the prime contractor may submit projects in which it performed the pertinent scope as a subcontractor.
Finally, the contractor may submit projects of an intended subcontractor, provided that the prime clearly explains what portion of this contract will be performed by the subcontractor AND a letter of commitment signed by the subcontractor is submitted in the Responsibility submissions. A draft letter of commitment is included as an attachment.
H. RESPONSIVENESS OF BIDS (FAR 14.301)
1. To be considered for award, a bid must comply in all material respects with the invitation for bids. Such compliance enables bidders to stand on an equal footing and maintain the integrity of the sealed bidding system.
2. Bids should be filled out, executed, and submitted in accordance with the instructions in the invitation. If a bidder uses its own bid form or a letter to submit a bid, the bid may be considered only if --
3. The bidder accepts all the terms and conditions of the invitation; and
4. Award on the bid would result in a binding contract with terms and conditions that do not vary from the terms and conditions of the invitation.
5 In order for the bidder to be considered responsive the unit price must be filled in and must not past two decimal places.
I. CONTRACTOR PERFORMANCE AND BANKING INFORMATION
1. The below information will be requested of the apparent low offeror. This information is not required to be responsive to the invitation for bid. To efficiently and expeditious award the resultant contract, it is HIGHLY recommended that offerors provide the below information with their offer. If offerors wish to shield this information from public view at the bid opening, the information may be placed in an envelope with the following legend:
PRE-AWARD SURVEY INFORMATION
SOLICITATION NO. W91236-18-B-0018
<YOUR FIRM’S NAME>
a) BANK: Branch/Location Point-of-Contact Telephone Number/Fax Number/Email Address Please contact the bank in advance so they will release the necessary information regarding average balances in your operating accounts, lines of credit and credit history.
b) For DRC “1” - Three Projects in which lifts of pre-positioned, preassembled structural steel weighing 30 - 50 tons have been performed using multiple cranes working in unison:
Project Title/Contract Number Customer Point-of-Contact Telephone Number/Fax Number/ Email address $Value %Complete/Scheduled Completion Date
c) For DRC “2” - Three Projects in which heavy hot-rolled truss sections utilizing large gusset plate connections and high strength pre tensioned bolts:
Project Title/Contract Number Customer Point-of-Contact Telephone Number/Fax Number/ Email address $Value %Complete/Scheduled Completion Date
d) For DRC “3” - Three Projects in which deep pile foundations were utilized:
Project Title/Contract Number Customer Point-of-Contact Telephone Number/Fax Number/ Email address $Value %Complete/Scheduled Completion Date
e) Please do not provide avoluminous listing of your firm’s contracting history.
J. INSPECTION OF THE SITE
Prospective bidders are invited to visit the site of the work in order to acquaint themselves as to site conditions and other problems incident to the prosecution of the work. Arrangements for inspection of the site shall be made through the Office the Area Engineer identified in the clause 52.236-27, entitled "SITE VISIT
(CONSTRUCTION)."
K. EVIDENCE OF AUTHORITY TO SIGN OFFERS
Evidence of the authority of individuals signing offers to submit firm offers on behalf of the offeror is required except where the offer is signed, and shows that it is so signed, by: the President, Vice-President, or Secretary of an incorporated offeror; a partner in the case of a partnership; or the owner in the case of a sole proprietorship. Failure to submit with the offer satisfactory evidence of the authority of all other persons may be cause for rejection of the offer as invalid or nonresponsive.
L. PREAWARD SAFETY CONFERENCE
1. Where an apparent low bidder, in performance of contracts during the previous three-year period, incurred one or more accidents, or where, in the opinion of the Contracting Officer, there is any question regarding this compliance with any safety or accident prevention requirement, such bidder, on request of the Contracting Officer prior to any award under this solicitation, shall attend a conference with representatives of the Contracting Officer to discuss any such accidents or non-compliance, the reason for their occurrence, and measures which will be taken to preclude any recurrence thereof.
2. Information elicited at this conference will be used by the Contracting Officer, in conjunction with other information obtained in a preaward survey, in determining the bidder's responsibility.
3. The items discussed, the preventive measures considered, and any conclusions reached in this conference shall be recorded in minutes of the meeting, which shall be authenticated by the signatures of representatives of the bidder and the Contracting Officer, and any procedures noted therein as agreed upon shall become an obligation of the bidder, along with all other safety and accident prevention requirements of the contract, if award is made to him.
M. INCURRING COSTS
The Government is not liable for any costs incurred by the offeror submitting an offer in response to this solicitation.
N. AGENTS
Offers signed by an Agent must be made in the name of the Principal and must be accompanied by evidence of said Agent’s authority to act on behalf of its Principal.
O. UNBALANCED BIDS
Any offer which is materially unbalanced as to prices for the Base Items and the Optional Items may be rejected as non-responsive or otherwise not considered for award. An unbalanced offer is one which is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
P. UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT OR OTHER PERSONNEL
The contractor shall not accept instructions issued by any person, employed by the U.S. Government or otherwise, other than the Contracting Officer or the Authorized Representative of the Contracting Officer acting within the limits of his/her authority as defined in the Designation of Authority letter. A copy of the Designation of Authority letter will be furnished to the contractor at time of contract award.
Q. TIMBER VALUATION
The contractor shall be responsible for tree clearing and removal in accordance with the plans and specifications, see Section 31 11 00 Clearing and Grubbing Part 3.2 Clearing.
Within 30 days after a Notice to Proceed is given to the contractor, said contractor shall submit a certified check payable in the amount of $1,198.95 to " FAO, USAED Norfolk" for fair market value of timber designated for tree removal on the site. Payment mailed to U.S. Army Corps of Engineers, Norfolk District, Attn: Real Estate Timber Sales, Fort Norfolk, 803 Front Street, Norfolk, VA 23510-1011. The contractor shall have (designated amount of time) from the Notice to Proceed to remove said timber. Ownership of timber transfers upon cutting. Title to the timber sold hereunder shall vest in the Purchaser as and when the Purchaser cuts the timber. The risk of loss shall pass to the Purchaser upon vesting of title. All trees not cut will remain property of the Government.
The check shall be payable to:
"FAO, USAED Norfolk"
R. AT/OPSEC
1. AT Level I Training. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil
2. Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements {FAR clause 52.204-9 or NAF Clause BI.142, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, Should the Force Protection Condition {FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
3. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
4. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2016 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-10 Contract Award--Sealed Bidding JUL 1990 52.214-12 Preparation Of Bids APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-9 Estimate of Percentage of Recovered Material Content for
EPA-Designated Items
MAY 2008
52.236-28 Preparation of Proposals--Construction OCT 1997 252.236-7008 Contract Prices-Bidding Schedules DEC 1991
CLAUSES INCORPORATED BY FULL TEXT
52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
(End of provision)
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
52.214-15 PERIOD FOR ACCEPTANCE OF BIDS (APR 1984)
In compliance with the solicitation, the bidder agrees, if this bid is accepted within 60 calendar days from the date specified in the solicitation for receipt of bids, to furnish any or all items upon which prices are bid at the price set opposite each item, delivered at the designated point(s), within the time specified in the Schedule.
(End of clause)
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including--
(1) Lump sum bidding;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of subparagraphs (1) through (3) above.
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
24.9% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Fort Eustis, VA.
52.225-11 BUY AMERICAN--CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT
2016)
(a) Definitions. As used in this clause--
Caribbean Basin country construction material means a construction material that--
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4)such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Designated country means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);
(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St.
Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
Designated country construction material means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
Least developed country construction material means a construction material that--
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
“Free Trade Agreement country construction material” means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.
“Least developed country construction material” means a construction material that—
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
United States means the 50 States, the District of Columbia, and outlying areas.
WTO GPA country construction material means a construction material that--
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.
(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
[Contracting Officer to list applicable excepted materials or indicate ``none'']
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that--
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) \1\ Item 1:
Foreign construction material Domestic construction material Item 2:
Foreign construction material Domestic construction material \1\ Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $2,000.00, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from U.S. Army Corps of Engineers, Norfolk District, 803 Front Street, Norfolk, VA 23501.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-- 03 July 2018 at 10:00 A.M. (EST)
Base access information by 28 Jun at 12 noon. Spreadsheet (provided by attachment) needs to be completed for each participant.
Information shall be provided to the following email addresses:
R.R.Blackwell@usace.army.mil
Jonathan.A.Jones@usace.army.mil
Joy.M.Wright@usace.army.mil
(c) Participants will meet at--
The corner of Marshall Ave and Madison Ave. There is an existing asphalt parking lot that will provide adequate parking.
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://farsite.hill.af.mil www.acquisition.gov/far
252.236-7006 COST LIMITATION (JAN 1997)
(a)Certain items in this solicitation are subject to statutory cost limitations. The limitations are stated in the Schedule.
(b)An offer which does not state separate prices for the items identified in the Schedule as subject to a cost limitation may be considered nonresponsive.
(c)Prices stated in offers for items subject to cost limitations shall include an appropriate apportionment of all costs, direct and indirect, overhead, and profit.
(d) Offers may be rejected which--
(1)Are materially unbalanced for the purpose of bringing items within cost limitations; or
(2)Exceed the cost limitations, unless the limitations have been waived by the Government prior to award.
Section 00 45 00 - Representations and Certifications
52.203-11 Certification And Disclosure Regarding Payments To
Influence Certain Federal Transactions
SEP 2007
52.204-5 Women-Owned Business (Other Than Small Business) OCT 2014 52.204-17 Ownership or Control of Offeror JUL 2016 52.214-27 Price Reduction for Defective Certified Cost or Pricing Data -
Modifications - Sealed Bidding
AUG 2011
52.222-56 Certification Regarding Trafficking in Persons Compliance Plan.
MAR 2015
52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.
OCT 2015
252.203-7005 Representation Relating to Compensation of Former DoD Officials
NOV 2011
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $36,500,000.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
( ) Paragraph (d) applies.
( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.