This is a Performance Work Statement (PWS) Revision 1 for agricultural wash and disinfection services for the Utah Army National Guard. The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control to perform military equipment agricultural wash, sanitation, and disinfection services at Camp Williams, Bluffdale, Utah between August 24-27, 2026 (4 days maximum), operating hours 0700-1600 Monday through Thursday as required. Services must be performed on-site with no teleworking authorized, and the contractor must comply with all installation access, security regulations, and force protection requirements.
The primary scope requires agricultural washing and disinfection of 45 pieces of equipment total, consisting of 20-foot MILVAN box ship containers, trailers, generators, and vehicles, with the government reserving the right to vary quantities by ±10 percent. The contractor must apply a 1 percent Virkon-S disinfectant solution to all exterior exposed surfaces, wheels, tracks, undercarriages, and all six sides of containers, maintaining a minimum 10-minute wet contact time and achieving maximum coverage with a 90 percent first inspection pass rate. Utah Army National Guard personnel will conduct initial gross cleaning prior to delivery; the contractor is responsible for final detailed cleaning and surface preparation meeting Army Standards for Sanitation per Armed Forces Pest Management Technical Guide No. 31. The contractor must establish containment for all disinfectant application and wastewater, containerize any accumulated processed water, and dispose of all unused Virkon-S solution and generated wastewaters at licensed facilities in compliance with federal, state, and local environmental regulations. A Utah Department of Agriculture and Food certified pesticide applicator license is required per Utah Pesticide Control Act compliance, and the contractor must provide daily completion logs by equipment serial number and a disposal manifest upon project completion. Army veterinary certified personnel will conduct final inspections, and the acceptable quality level specifies maximum coverage of chemical solutions with a 90 percent first inspection pass rate.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
Revision 1, 30 Jun 26
FOR
Agricultural Wash Services
1.0 General:
1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in paragraph 3.0 as government furnished, to perform military equipment agricultural wash, sanitation, and disinfection services, as defined in this PWS.
1.1.1 Objectives
1.2 Background: All Department of Defense (DOD) sponsored exercise or special mission cargo entering into the United States European Command Area of Responsibility (USEUCOM AOR) will undergo wash down and preclearance at the point of origin. All equipment and cargo destined for any European Union country must be free of all agricultural contaminants such as soil, sand, and dirt; insect infestation; bird or animal by-products; and snails and vegetation prior to packing and shipping. In order to meet these requirements, the equipment going overseas must be treated with a disinfectant using chemicals and protective gear not organic to the Utah Army National Guard.
1.3 The Period of Performance (PoP) shall be no more than 4 days beginning 24 August 2026 and ending no later than 27 August 2026.
1.4 General Information:
1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0700-1600 on Monday through Thursday (as required) except on recognized US holidays or when the government facility/installation is closed due to local or national emergencies, administrative closings, or similar government-directed facility/installation closings. Performance shall be at Camp Williams, Bluffdale, UT. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential. Teleworking is not authorized..
1.4.1.1 RESERVED
1.4.1.2 Unscheduled gate closures by the security forces may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation, including fire, traffic, safety, and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall always carry proper identification with them and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The government reserves the right to direct the removal of an employee from government property or revoke access to government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the contractor from responsibility for total performance of this contract.
1.4.2 RESERVED
1.4.3 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract.
1.4.4 Quality Assurance (QA): The government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).
1.4.5 Installation Access and Security Requirements. Access to the installation will be coordinated with a government representative, as will be identified in the contract. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the government representative or designated government escort. The contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by Department of Defense (DoD), Headquarters Department of Army (HQDA) and/or local policy (see PWS 6.0). Should the Force Protection Condition (FPCON) change, the government may require changes in contractor security matters or processes.
1.4.5.1 RESERVED
1.4.5.1.1 RESERVED
1.4.5.1.2: RESERVED
1.4.5.1.2 RESERVED
1.4.5.1.3 RESERVED
1.4.5.1.4 RESERVED
1.4.5.1.5 RESERVED
1.4.5.1.5.1 RESERVED
1.4.5.1.6 RESERVED
1.4.5.2 RESERVED
1.4.5.3 RESERVED
1.4.5.4 RESERVED
1.4.5.11 RESERVED
1.4.5.12 RESERVED
1.4.5.14 RESERVED.
1.4.6 Physical Security. The contractor shall safeguard all government property provided for contractor use. At the close of each work period, government facilities, equipment and materials shall be secured.
1.4.6.2 RESERVED
1.4.7 Special Qualifications: The contractor shall ensure required application licenses for use of Virkon-S disinfectant in the performance of this contract. This does not include education or other qualifications for the position in which the contractor employee is performing, dress codes, or other information. (NOTE: The government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified, and otherwise qualified to provide services.) Utah pesticide code R68-7-6 requires that a pesticide applicator be certified by the department as a commercial pesticide applicator and that the pesticide applicator comply with FIFRA and title 4, chapter 14 of the Utah Pesticide Control Act.
1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the Contracting Officer (KO) in accordance with FAR 42.5. The KO, government representative and other government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the government views the contractor’s performance and the contractor shall appraise the government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the government. Contractor attendance at these meetings shall be at no additional cost to the government.
1.4.9 Contract Manager (CM): The contractor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the KO to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. Only the KO has the authority to increase the scope or authorize any additional cost to the government. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.4.10 RESERVED
1.4.10.1 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within immediately after an employee’s departure.
1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero-tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking of persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.
1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as deemed necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
2.0 Definitions and Acronyms:
2.1 Definitions:
2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.
2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.5 Physical Security: Actions that prevent the loss or damage of government property.
2.1.6 Quality Assurance: The government procedures to verify that services being performed by the contractor are performed according to acceptable standards.
2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.8 Quality Control: All necessary measures taken by the contractor to ensure that the quality of an end product or service shall meet contract requirements.
2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The government does not have privity of contract with the subcontractor.
2.2 Acronyms:
AEI: Army Enterprise Infostructure AR: Army Regulation AT/OPSEC: Antiterrorism/Operational Security BI: Background Investigation CM: Contract Manager COR: Contracting Officer Representative DA: Department of the Army DD254: Department of Defense Contract Security Classification Specification 8 Ver. October 2022 DFARS: Defense Federal Acquisition Regulation Supplement DoD: Department of Defense DSCA: Defense Counterintelligence and Security Agency FAR: Federal Acquisition Regulation GFP/M/E/S: Government Furnished Property/Material/Equipment/Services HQDA: Headquarters, Department of the Army HSPD: Homeland Security Presidential Directive IA: Information Assurance IS: Information System(s) KO: Contracting Officer NGB: National Guard Bureau OCI: Organizational Conflict of Interest PII: Personally Identifiable Information PIPO: Phase In/Phase Out POC: Point of Contact PRS: Performance Requirements Summary PWS: Performance Work Statement QA: Quality Assurance QASP: Quality Assurance Surveillance Plan QC: Quality Control QCP: Quality Control Program SCR: Service Contract Reporting SSN: Social Security Number TE: Technical Exhibit USD(I): Under Secretary of Defense for Intelligence
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:
3.1 Property: The government will furnish the necessary workspace for the contractor to perform services outlined in this PWS to include ample workspace, water source, and operators for water source equipment if needed.
3.1.1: Workspace will be a designated flat, paved workspace for the contractor to establish containment and conduct wash/disinfection operations.
3.1.2: The water source suitable for the work is identified as standard garden hose.
3.2 Utilities: All utilities in the facility will be available for the contractor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.
4.0 RESERVED
4.1 RESERVED.
5.0 Requirements: The contractor shall:
5.1 Contractor must provide agricultural wash and disinfecting services for the Utah Army National Guard equipment and vehicles located on Camp Williams, UT. This is a non-personal services contract to perform military vehicle and equipment agricultural washing, sanitation, surface preparation, and exterior treatment. The required application of 1% Virkon-S is a component of this service, but the principal purpose is the agricultural cleaning and sanitation process.
•45 pieces total consisting of 20 FT MILVAN Box Ship Containers, trailers, generators, and vehicles. (see attached list). The Government reserves the right to vary the quantity of equipment or vehicles needed to be sanitized by +/- 10% due to operational requirements.
• UTARNG personnel will conduct initial cleaning of the equipment at installation wash racks prior to delivery to the contractor. The government's responsibility is to deliver equipment free of gross contamination (e.g., large clumps of mud, soil, or significant organic debris). The contractor remains responsible for the final, detailed cleaning and surface preparation necessary to meet the "Army Standards for Sanitation" (defined in 5.1.2) and to ensure effective disinfectant application. If the contractor deems a vehicle is not sufficiently pre-cleaned, the contractor shall immediately notify the designated government representative, who will direct the appropriate corrective action.
The Contractor must follow all manufacturer instructions and Safety Data Sheets (SDS) for Virkon-S. This includes ensuring the mixture remains a 1:100 (1%) solution, all personnel utilize required Personal Protective Equipment (PPE), and the minimum 10-minute wet contact time is achieved.
(Caution: Due to the dry, high-altitude environment of Camp Williams, UT, the solution may evaporate rapidly. The Contractor may need to apply a continuous light mist to prevent premature drying before the 10-minute timer is up).
All Virkon-S rinsate runoff will be captured within the contractor-established containment area. Should any processed water (rinsate) accumulate, it shall be containerized by the contractor (pumped into a vacuum truck and suitable tank). This is a conditional, ancillary support function, not the primary service being procured. Any unused Virkon-S solution and all generated wastewaters shall be disposed of by the contractor at a licensed disposal facility in compliance with all local, state, and federal environmental regulations. Fines resulting from non-compliance are the sole responsibility of the contractor.
Contractor will monitor the Virkon dilution process to ensure proper 1% application and will issue a certificate of application upon project completion.
5.1.1 Army personnel will bring the equipment and vehicles to the containment area. The contractor will be responsible for setting up any ramps or other equipment necessary to access undercarriage or bottom of containers during Virkon application and rinse. Military Personnel can re-enter and move equipment after the final inspection is complete. The contractor will be given access to an open flat area to set up the containment area near a water source. The contractor will have access to an electrical outlet at the site.
5.1.2 The contractor must meet the Army standards for sanitation, as defined in the Armed Forces Pest Management Technical Guide No. 31 (TG31) section 7.5. A copy of the TG31 will be attached to the solicitation for further detail and awareness. The TG31 lists multiple acceptable disinfection products; however, Virkon-S is the chosen product due to its proven performance across a wide range of contaminants. Surfaces that must be treated include all exterior exposed surfaces, wheels, tracks, undercarriages, and the exterior and bottoms of containers (all six sides). The contractor shall provide any ramps, heavy-duty container-lifting legs, or other equipment necessary to access the undercarriages of equipment or vehicles for application of the Virkon-S mixture and post application rinse. The equipment and vehicles will be inspected to ensure maximum coverage of the disinfectant solution. The Veterinary Certified personnel will inspect the vehicles prior to completion of project.
5.1.3 The contractor shall keep and submit a daily completion log of sanitization operations by serial number and bumper or container number. The contractor will provide the Utah Army National Guard representative and KO an executed disposal manifest for record. The contractor shall perform daily clean-up without exception. Any areas disturbed by this service shall be returned to the original condition existing prior to the final inspection date.
5.1.4 LOCATION: Camp W.G. Williams, 17800 S Redwood Rd, Bluffdale, UT 84065– The Government representative will coordinate with awardee on exact location and escort requirements for the base.
TECHNICAL EXHIBIT 1
Performance Requirements Summary (PRS) This PRS includes performance objectives the government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).
| Performance Objective |
| Performance Standard |
| Acceptable Quality Levels (AQL) |
| Surveillance Method / By Whom |
Para 5.0-5.1.3 Agricultural Wash Service
| The contractor must apply chemical to all exterior surfaces on the equipment and vehicles to ensure maximum coverage. The contractor must rinse after the application contact period. The contractor must contain and dispose of all wastewaters resulting from application process. |
| Maximum coverage of chemical solutions on exterior surfaces of all equipment with a 90% first inspection pass rate. |
| Army certified personnel will be on site to inspect equipment and vehicles as sanitized by Contractor. Individual will be accompanied by COR |
TECHNICAL EXHIBIT 2
Deliverables Schedule
| PWS Reference / Deliverable Title |
| Frequency |
| Number of Copies |
| Medium/Format |
| Submit To |
| 5.1.3 |
| Daily |
| 1 |
| Electronic Submission |
| Government Representative; KO |
TECHNICAL EXHIBIT 3
Utah Pesticide Control Act Compliance
| Compliance Scope |
| Statutory Definitions |
| Contractor Personnel and Licensing Requirements |
| Product Usage and Label Compliance |
| The Contractor shall comply with all applicable federal, state, and local laws and regulations regarding the application of pesticides. This includes, but is not limited to, the Utah Pesticide Control Act (Utah Code Title 4, Chapter 14) and its associated administrative rules. The Contractor is strictly responsible for obtaining and maintaining all required licenses and permits for the duration of the contract lifecycle. |
| For the purpose of executing this contract safely and legally, the following definitions from the Utah Pesticide Control Act apply to the required disinfection services: |
Pest: Includes any virus, bacteria or other microorganism that injures health and environment.
Pesticide: A substance or mixture of substances intended to prevent, destroy, control, or mitigate any pest. Note: The disinfectant product required under this contract is classified as a pesticide under Utah law.
Certified: An individual who is licensed by the Utah Department of Agriculture and Food (UDAF) to apply for a general-use pesticide for hire or in exchange for compensation.
Pesticide Applicator: An entity that is authorized to do business in Utah and offers pesticide application services to the public or government entities.
The Contractor must strictly adhere to the following certification and licensing requirements mandated by the State of Utah prior to commencing any disinfection operations:
Business: The Contractor must be registered as a Pesticide Applicator Business with the UDAF prior to commencing work. Proof of this registration shall be provided to the Contracting Officer (CO) or Contracting Officer’s Representative (COR) upon request.
Individual Applicator License: All personnel performing the physical act of applying the pesticide/disinfectant for compensation under this contract must be licensed by UDAF as Certified Applicators for general-use pesticides applied for hire.
Supervision & training: The Contractor shall employ at least one licensed Certified Applicator and ensure that all subordinate employees involved in pesticide application comply with the Utah Pesticide Control Act, including all administrative rules for supervision, safety, and training.
The Contractor shall ensure that the application of the specified disinfectant (Virkon-S ) is performed in a manner strictly consistent with its manufacturer label, as required by both federal law (FIFRA) and the Utah Pesticide Control Act.
Warning: Any "misuse," explicitly defined as the use of a pesticide in a manner inconsistent with its labeling, constitutes a violation of law and a material breach of this contract.