This document provides details on permits and approvals required for the Howards Bay Remedial Dredging project, as well as information on the related federal contract opportunity solicitation. Key permits including those from the US Army Corps of Engineers, Wisconsin Department of Natural Resources, City of Superior, and others have been issued or are anticipated to be obtained after award. The solicitation seeks firms to provide construction services including dredging approximately 52,000 cubic yards of material from the Federal Navigation Channel and placing in a Government Furnished Disposal Facility. Additional work includes environmental dredging of around 80,000 cubic yards of contaminated sediment for disposal in the Wisconsin Point Landfill, dewatering and stabilizing dredged material, confirmation sampling, air and turbidity monitoring, collecting and treating return water, capping and grading of the landfill, and placing residuals cover material. The contract value is estimated between $10-25 million. The NAICS code is 562910 and the solicitation is set aside for small business with a response due date not provided. The Detroit District of the Army Corps of Engineers issued the firm-fixed price invitation for bid.
View the file
Other files for this federal contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF ANTICIPATED PERMITS / APPROVALS (not necessarily inclusive of all required permits and approvals)
ISSUED/
COMPLIANCE
MET
PERMITS / APPROVALS FOR
HOWARDS BAY GLLA
SEDIMENT DREDGING
COMPLIANCE DATE OR
REASON FOR EXEMPTION
REASON FOR POST-
AWARD COMPLIANCE (if applicable)
Exempt
National Environmental Policy Act (NEPA)
USEPA is exempt from NEPA under Section 511(c) of the Clean Water Act (CWA) for projects under the Great Lakes Water Quality Agreement (GLWQA) in Section 118(c) of the CWA using Great Lakes Restoration Initiative (GLRl) funds.
Y
USACE Section 10/404 Issued 14 February 2020 as USACE Nationwide Permit #38.
Wisconsin Point Landfill not included as is outside Regulatory 10/404 jurisdiction being above
OHWM.
WDNR Public Waters Permit (requires Public Notice) under Wisconsin Chapter 30
Issued 24 January 2020
WDNR Clean Water Act 401 Water Quality Certification
Is part ot the Chapter 30 permit (row 4 above)
Y Wisconsin Department of Administration, Coastal Zone Managemen Act (CZMA)
Is part ot the Chapter 30 permit (row 4 above).
Y WDNR Landfill Plan Modification
Issued 23 March 2020 post award City of Superior, Post- Construction Stormwater Management: Fraser Site
TBD
Applications require details from Contractor's Stormwater/ Erosion Control Plan. Permit has 30-business-day review.
post award
City of Superior, Post- Construction Stormwater Management: Wisconsin Point Landfill
TBD
post award
WDNR Chapter 30 permit;
WPDES Construction Site Storm Water Runoff General Permit Notice of Intent (NOI) for Land Disturbing Activity: Fraser Site
TBD
Applications require details from Contractor's Stormwater/ Erosion Control Plan. Has 14-day review period.
WDNR Chapter 30 permit;
WPDES Construction Site Storm Water Runoff General Permit Notice of Intent (NOI) for Land Disturbing Activity:
Wisconsin Point Landfill
City of Superior, Approval for discharge of wastewater to city sanitary sewer.
Contractor to apply within 30-days of Notice to Proceed.
The application requires contractor- specific dewatering and filtration plan details.
DNR approval of contractor’s wastewater pretreatment system
ISSUED/
COMPLIANCE
MET
PERMITS / APPROVALS FOR
HOWARDS BAY GLLA
SEDIMENT DREDGING
COMPLIANCE DATE OR
REASON FOR EXEMPTION
REASON FOR POST-
AWARD COMPLIANCE (if applicable)
Notification Required
WDNR Air Permit Project exempt per J. Graham July 2017 discussion with S. Lindem (WDNR). Only requirement is to provide S. Lindem project start notification.
Executive Order 11988, Floodplain Management
Project complies as there is no practicalble alternative to work in the floodplain for the GLLA dredging/ material processing.
Wisconsin Point Landfill is indicated as floodplain, but current elevations are above 100-year flood elevation.
Invasive Species Transportation--Minnesota TBD Routine permits, not necessary for contract award.
City of Superior is obtaining these permits. post award
Invasive Species Transportation--Wisconsin TBD
Y Threatened & Endangered Species
Complies as all Federal species are "No Effect." No state species known in project area of effect.
Bald Eagle Nest Protection Act USFWS concurred with protective measures 03 March 2020 (avoid dreding within 660 feet of nest before 15 August if nest occupied)
State Historic Preservation Office (SHPO) Section 106
SHPO concurred 25 October 2017
Y Tribal Coordination Section
106. Only one Tribal response, Fon du Lac.
Sec 106 consultation finalized by USEPA letter to Tribe dated 01
April 2020
Removal of suitable material from Erie Pier CDF for growth medium at Wisconsin Point Landfill.
USACE Memorandum documenting compliance signed 17
April 2020