W56MES53289095
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
FY16 Poe Embedded Anchorage Replacement
This amendment is issued to make changes to the procedures and the specifications sections. The response date is extended to 14 June 2016. Reference changes on the follow ing pages.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Jun-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911XK-16-R-0003
X 9B. DATED (SEE ITEM 11)
10-May-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Jun-2016
CODE
CONTRACTING BRANCH
USACE DETROIT DISTRICT
477 MICHIGAN AVENUE, 7TH FLOOR
DETROIT MI 48226-4523
W911XK 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911XK-16-R-0003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 03
PROCEDURES
6.1.2 FACTOR 1, SUBFACTOR 2: TECHNICAL APPROACH SUMMARY
-.1 Submittal for Evaluation
Delete:
The Offeror shall submit a narrative (not to exceed two pages) describing the overall technical approach to the contract work.
ADD:
The Offeror shall submit a narrative (not to exceed two pages) describing the overall technical approach to the contract work (Base and Options).
Paragraph 6.1.4 FACTOR 1, SUBFACTOR 4: QUALIFICATIONS OF KEY TEAM MEMBERS -1.;
Prime Contractor paragraph:
Delete first sentence:
The Project Manager, Site Superintendent, Site Safety and Health Officer (SSHO), Dive Supervisor and Contractor’s Quality Control System Manager must be employed by the Prime Contractor.
Replace with the following two sentences:
The Project Manager, Site Superintendent, Site Safety and Health Officer (SSHO), and Contractor’s Quality Control System Manager must be employed by the Prime Contractor. The Dive Team, including its supervisor, shall be employed by the Prime Contractor or shall be a first tier subcontractor.
-2.: Evaluation Criteria paragraph: After the last sentence add:
Proposals where the Dive Team and its supervisor are employees of the Prime Contractor will be considered a strength. Proposals where the Dive Team Supervisor has previous experience diving on USACE projects will be considered a strength.
Paragraph 6.1.4 FACTOR 1, SUBFACTOR 4: QUALIFICATIONS OF KEY TEAM MEMBERS -1.;
Contractor’s Quality Control System Manager Paragraph:
W911XK-16-R-0003
Delete :The CQC System Manager must be a graduate in construction management or engineering, with a minimum of 5 years of construction experience in three or more of the Factor 1, Subfactor 1 construction areas and meet the qualifications criteria of Section 01 45 00.00 10, paragraph 3.4.2. The CQC System Manager shall meet experience requirements for Factor 1, Subfactor 1 construction area 1.
Replace with the following:
"The CQC System Manager must meet the qualifications criteria of Section 01 45 00.00 10, paragraph 3.5.2."
Changes To The Specifications
1. Delete 35 50 56 MITER GATE ANCHORAGES REMOVAL AND INSTALLATION Add revised 35 50 56 MITER GATE ANCHORAGES REMOVAL AND INSTALLATION AMENDMENT 0003 2 JUNE 2016. See attached.
2. Delete 01 35 13 SPECIAL PROJECT PROCEDURES Add revised 01 35 13 SPECIAL PROJECT PROCEDURES AMENDMENT 0003 2 JUNE 2016. See attached.
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 09-Jun-2016 02:00 PM to 14-Jun-2016 02:00 PM.
(End of Summary of Changes)