W911XK-16-R-0003_FY16_Poe_Gate_Embedded_Anchorage_Replacement.pdf

PDF 408 KB Posted

Attached to
FY16 POE LOCK EMBEDDED GATE ANCHORAGE REPLACMENT
Solicitation number
W911XK-16-R-0003
Issued by

About this file

Solicitation

View the file

Other files

File Type Posted
W911XK-16-R-0003-0004_FY16_Poe_Gate_Embedded_Anchorages.pdf PDF
35_50_56_AMENDMENT_0003_2_JUNE_2016.pdf PDF
W911XK-16-R-0003-0003_FY16_Poe_Gate_Embedded_Anchorages.pdf PDF
01_35_13_AMENDMENT_0003_2_JUNE_2016.pdf PDF
Revised_Exhibit_B-_Key_Personnel_Information_ _Consent_Form_.pdf PDF
Revised_Exhibit_A--Performance_Relevancy.pdf PDF
Revised_EXHIBIT_E-_Small_Business_Participation_Plan_(Form).pdf PDF
01_22_00.00_10_amendment_0002_20may2016.pdf PDF
31_00_00_amendment_0002_20may2016.pdf PDF
01_45_00.10_10_amendment_0002_20may2016.pdf PDF
Amendment_0002_shts.pdf PDF
SLYF16_C-101_18_May_2016.pdf PDF
32_13_13.06_amendment_0002_20may2016.pdf PDF
32_11_16_amendment_0002_20may2016.pdf PDF
W911XK-16-R-0003-0002.pdf PDF
Site_Visit_Sign-in_Sheet--W911XK-16-R-0003_.pdf PDF
FY16_Poe_Lock_Embedded_Anchorage_Replacement_Pre-Proposal_Meeting_Presentation.pdf PDF
W911XK-16-R-0003-0001_FY16_Poe_Gate_Embedded_Anchorage_Replacement.pdf PDF
Poe_MG_Anchorage_Replace_RTA_Specs.pdf PDF
Reference_Drawings_Ready_to_Advertise.pdf PDF
EXHIBIT_E-_Small_Business_Participation_Plan_(Form).pdf PDF
Exhibit_A--Performance_Relevancy.pdf PDF
Exhibit_C_-_Past_Performance_Reference_Questionnaire_revised_17_March_2016.pdf PDF
EXHIBIT_D_-_Requirements_of_the_Small_Business_Subcontracting_Plan.pdf PDF
Exhibit_B-_Key_Personnel_Information_ _Consent_Form_.pdf PDF
Poe_MG_Anchorage_Replace_RTA_Plans.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W56MES53289095

FY16 Poe Gate Embedded Anchorage Replacement

This project is solicited as an unrestricted procurement.

The North American Industrial Classif ication System (NAICS) code is 237990, w hich has a small business size standard of $36.5 Million in average annual receipts.

The estimated price of construction ranges betw een $5 Million and $10 Million.

A Preproposal Conference w ill be held via w eb and teleconference on 17 May 2016 at 12:30 pm Eastern. The formal site visit w ill immediately follow the Preproposal Conference. Reference FAR clause 52.236-27 Alt 1 for details pertaining to the site visit.

NOTE: Block 11 contains full information for determining the performance period. The contractor is cautioned NOT to make any additions, deletions or other modif ication to this block. Reference FAR clause 52.211-10 for performance period.

CARLETTE WILLIAMS 313.226.2683

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

10-May-2016

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________7 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________09 Jun 2016 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

CONTRACTING BRANCH

USACE DETROIT DISTRICT

477 MICHIGAN AVENUE, 7TH FLOOR

DETROIT MI 48226-4523

W911XK

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: (313) 226-6819 TEL: FAX:

W911XK-16-R-0003 71

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W911XK-16-R-0003

Section 00010 - Solicitation Contract Form

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

IGF::OT::IGF

FFP

FY16 Poe Embedded Anchorage Replacement--PROJECT NO.: 153619

--FOR ACCOUNTING PURPOSES ONLY--

FOB: Destination

MILSTRIP: W56MES53289095

PURCHASE REQUEST NUMBER: W56MES53289095

NET AMT

PRICE SCHEDULE

Item Description Quantity Unit of

Measure Unit Price Total

0001 Bonds 1 JA $____________ $____________

0002 Fabricate Embedded Anchorages for Gate 1 1 JA $____________

0003 Install Embedded Anchorages at Gate 1 1 JA $____________

0004 Fabricate Embedded Anchorages for Gate 3 1 JA $____________

0005 Install Embedded Anchorages at Gate 3 1 JA $____________

0006 Anchor Demonstration Test 1 JA $____________

Total Amount of Base Items

Option

Fabricate Embedded Anchorage for Gate 2 1 JA $____________

Option

Install Embedded Anchorage at Gate 2 1 JA $____________

Total Amount of all Items

SCOPE OF WORK

FY16 Poe Lock Embedded Gate Anchorage Replacement Scope of Work

The scope of the project includes, but is not limited to, the installation of new embedded gate anchorages behind the existing gate anchors and the connection to the lock gate leaf at the Poe Lock which is part of the Soo Locks Complex in Sault Ste. Marie, Michigan. The Poe Lock is a 110 feet wide by 1200 feet long navigation lock which allows vessels to safely transit the 21 foot in drop in water elevation between Lake Superior and the lower Great Lakes. The scope includes installation of new primary and secondary embedded anchorages at Gates 1, 2 and 3. The embedded gate anchorages distribute the top reaction of the leaf into the concrete lock wall. Each gate leaf is supported by two embedded anchorages, a primary and secondary embedded anchorage. The embedded anchorages are positioned adjacent to the top of the gate leaf, below the surface of the concrete lock wall.

Installation will require removal of concrete to install steel anchorage frames, drilling of concrete cores to accommodate concrete anchors, installation of steel anchorage frames and tensioned concrete anchors, and placement of new concrete. The contract will also include fabrication of steel embedded anchorage frames and anchor rods. Fabricated elements will consist of fracture critical members and applicable steel specifications. The top of the existing embedded anchorage will be removed to accommodate the connection of the new embedded anchorage to the existing gate leaf, the bottom portion of the existing embedded anchorage shall be abandoned in place. Contract award is expected in summer 2016. Steel fabrication shall begin in summer 2016. Concrete removal shall begin in summer/fall 2016, and placement of components of the new embedded anchorages including anchor demonstration test, will be allowed during the navigation season (25 March – 15 January). Time is of the essence for the project. The schedule for working within the lock area for this project is rigid and is limited to the timeframe when winter lock closure takes place for lock maintenance (17 January 2017 thru 19 March 2017). This will include final installation of the anchorage and connection to the lock gate. Project delays that cause the project to extend past the required completion date would adversely impact the commercial navigation industry and time extensions will not be granted.

It is critical that all the gates in the contract are turned over to the government in functioning condition no later than 19 March 2017. For the gates to be considered functional, they must operate as originally designed. Weather conditions during the winter shut down at the Soo Locks are very harsh with low temperatures, heavy snow, and high winds.

The schedule for the project (as described in specification section 01 32 01.00 10) will be proposed by the contractor and, when accepted by the government, becomes part of the contract. The contractor's failure to meet the contract schedule milestones could result in unilateral direction from the government that alters the schedule to ensure that the gate is in functioning condition no later than 19 March 2017.

Security requirements:

a. All personnel employed by the contractor in the performance of the services specified in this contract or any representative of the Contractor entering the work area shall conform and comply with all applicable U.S. Army Corps of Engineers, facility access, security policies and procedures. (Provided by government representative). All personnel and vehicles are subject to search upon entry, exit and within the confines of the facility.

b. Pre-screening of contractor candidates via E-verify Program: The Contractor must pre‐screen candidates using the E‐verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that all contractors working on the site have two valid forms of Government issued identification prior to entering the information in E-Verify. The vendor must ensure the correct information is entered into the E‐verify system. A verification sheet for each verified/eligible contractor candidate must be provided to the COR no later than 3 business days after the initial contract award. (The purpose of using E-Verify is to ensure all contractors are U.S. citizens or documented foreign citizens with authority to work in the United States of America). The COR will forward the verification sheets to the USACE, Detroit District Security Office for validation.

c. Clearance of Personnel: All Contractor and Sub-Contractor employees are required to have a National Agency Check (Fingerprint Check) with favorable adjudication prior to their being able to enter the work site. The Contractor will be responsible for working with the COR to submit all required paperwork for each employee to the Security Office prior to initiation of the background investigation.

The contractor may complete Government furnished fingerprint cards at a local police station for each employee that will be working at the project location. The cost for the fingerprinting is the responsibility of the contractor. The completed fingerprint cards shall be provided to the Security Office.

The preferred method recommended by the Government, at no cost to the contractor, is to complete an electronic fingerprint submission with the Soo Locks Facility Security Officer (FSO). FSO Point of contact is Mr. Michael Panik at 906-635-3470

The contractor should anticipate the fingerprint cards to take approximately 24 days and the electronic finger prints to take approximately 8 business days for adjudication. These are estimates only, actual times may vary.

d. Exceptions to Background Investigation: All exceptions will be reviewed and authorized after a thorough review by the Detroit District Security office on a case by case basis.

e. Security Checks ‐ All contract employees must carry valid Government issued picture identification at all times.

They must show I.D. upon request by both Security and Government personnel. The Contractor's employees must enter the site through the main security checkpoint unless otherwise approved by the Contracting Officer. The Contractor's employees will be subject to such additional checks as may be deemed necessary to ensure that no violation of security rules has occurred.

f. Security Access List - The contractor shall be required to maintain a list of personnel needing access to the site.

The list shall be updated at least weekly or each time a change is made. The template for the list will be provided to the contractor at the Pre-construction conference. The list shall be submitted prior to 1400 at least 24 hours prior to an individual requiring site access.

g. Facility Access: 24 hour per day 7 day a week access to the facility is through the unmanned automatic parking lot gate (Gate 4 Foot of Ashmun St.). Gates 15, 13, 10, and 7 are open generally 0600-1800 7 days a week between May and September. Gate 9 is generally open 0600-1800 7 days a week year round. The front door of the warehouse is generally open 0600-1800 Monday – Friday excluding Federal Holidays. There are numerous other automatic gates that the contractor may be required to pass through in order to reach the work area. Gate Access through any of the gates listed above are subject to change.

Access through any non-automated gates or Gate 15, 13, 10, 7 and 9 outside of established hours must be coordinated in advance with the COR so the Government can coordinate with the Security Contractor. The government will not provide guard escort services for the contractor.

All automatic entrances require personnel to be in possession of a FIPS 201 compliant identification card.

CAC, PIV, TWIC, etc. Contractor employees may be required to know the PIN number for their FIPS 201 compliant identification card to access certain areas of the facility. The Government can only reset PINs on CAC cards. The Government will not issue CAC cards to contractor personnel.

h. Exclusion or Expulsion from the Site ‐ A negative background investigation (NAC) may result in the exclusion or expulsion of Contractor employees from the site as determined by the Detroit District, Chief, Security & Law Enforcement. Additionally any failure to observe the security rules will also result in the potential exclusion or expulsion of Contractor employees from the site. Exclusion or expulsion of an employee resulting from a negative background investigation (NAC) or the failure of an employee to observe the security rules shall not be subject to the Disputes clause and shall not result in an increase in the contract amount.

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 N/A N/A N/A Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

0001 15-JUL-2017 1 LOGISTICS-TRANSPORTATION BR

DETROIT DISTRICT, USAED

P.O. BOX 1027

DETROIT, MI 48231-1027

FOB: Destination

H770T00

Section 00100 - Bidding Schedule/Instructions to Bidders

NOTES TO OFFERORS

1 NOTE

1.1 EVALUATION: The Government intends to award a firm-fixed price contract as a result of this Request for Proposal (RFP). The acquisition and source selection are being conducted in accordance with the Federal Acquisition Regulation (FAR) Part 15. Award will be made to the proposal determined to be the best value to the Government based on the evaluation criteria outlined in this solicitation.

1.2 The Army will procure this project through a technical and price competition in accordance with the provisions set forth in this RFP. When a contract is awarded, it will be a "Firm Fixed Price” contract.

1.3 POST-AWARD CONFERENCE: The contractor agrees to attend any post-award conference(s) convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5.

1.4 Prices must be submitted on all individual line items of the Price Schedule. Otherwise, the Offer may be considered non-compliant and may be rejected.

1.5 The “JOB” line items in the Price Schedule are not “Estimated Quantity” line items and are not subject to FAR 52.211-18 Variation in Estimated Quantity.

1.6 Contract Clause 52.232-27, “Prompt Payment for Construction Contracts” requires that the name and address of the contractor official, to whom payment is to be sent, be the same as that in the contract or in a proper Notice of Assignment.

1.7 The Contracting Officer who signs the contract will be the Principal Contracting Officer for the contract.

However, any Contracting Officer assigned to the Detroit District, contracting within their authority, may take formal action on the contract when the Principal Contracting Officer is unavailable and the action needs to be taken.

1.8 Amounts and prices shall be indicated in either words or figures, NOT BOTH.

1.9 Payment of Electronic Funds Transfer (EFT) is the mandatory method of payment. The Contractor’s attention is directed to Contract Clause 52.232-33 “Mandatory Information for Electronic Funds Transfer.”

1.10 The Government will review all submitted Price Schedules for any unbalancing of the items. Any submitted Price Schedule determined to be unbalanced may be considered unacceptable and may cause the Offeror to be ineligible for award.

1.11 The Offeror shall furnish all plant, labor, material (excluding any Government furnished material that is detailed within this RFP) equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in this solicitation, to include all attachments thereto.

1.12 PLEASE NOTE: Submit solicitation inquiries in accordance with the instructions. Inquires MUST be received no later than five (5) business days prior to proposal due date.

1.13 The contractor shall submit as-builts.

1.14 EVALUATION OF OFFERORS: OFFERORS MUST SUBMIT A PROPOSAL ON ALL LINE ITEMS

IN THE PRICE SCHEDULE. THE GOVERNMENT WILL MAKE ONE (1) AWARD TO THE OFFEROR WITH

THE BEST VALUE TO THE GOVERNMENT USING THE “TRADE OFF PROCESS” IN ACCORDANCE

WITH FAR SECTION 15.101-1 ENTITLED “TRADE OFF PROCESS”.

INSTRUCTIONS TO OFFERORS

1 INQUIRIES

Bidders shall not include identifying information in any submitted inquiry.

***Please Note: Offerors shall only submit one question per inquiry. Inquiries containing multiple questions may be rejected.

1.1 Prospective Offerors should submit questions concerning this Request for Proposal via Bidder Inquiry in ProjNet at www.projnet.org/projnet.

1.1.1 To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into the system. To self-register, go to the aforementioned web page and click on the BID tab.

Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your email address, and then click login. Fill in all required information and click create user.

Verify that information on next screen is correct and click continue.

1.1.2 From this page, you may view all bidder inquiries or add inquiry.

1.1.3 Offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

The Solicitation Number is: W911XK-16-R-0003 The Bidder Inquiry Key is: C3VK7J-H2A9QP

1.2 The Bidder Inquiry System will be unavailable for new inquires 5 business days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary.

1.3 Offerors are requested to review the solicitation in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

1.4 The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

1.5 Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

2 TELEGRAPHIC BIDS/OFFERS

2.1 TELEGRAPHIC BIDS/OFFERS ARE NOT ACCEPTABLE

2.1.1 Any telegram to modify or withdraw a bid/offer sent to this office must be physically delivered to the office designated for receipt of bid/offer by the date and time set for bid opening/receipt of proposals.

No one from this office will be dispatched to the local telegraph office to pick up any telegram for any reason.

3 FACSIMILE BIDS/OFFERS

3.1 Facsimile bids/offers, modifications thereto, or cancellations of bid/offers will not be accepted.

4 SAFETY REQUIREMENTS

4.1 The successful contractor to this Request for Proposals will be required to comply with all pertinent provisions of the latest version of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation. EM 385-1-1 and its changes are available at http://www.usace.army.mil by selecting “Safety and Occupational Health” followed by “EM 385-1-1”. The Contractor must also comply with Occupational Safety and Health Act (OSHA) standards. OSHA standards are subject to change. It is the Contractor's responsibility to maintain familiarity with current OSHA standards.

5 DIRECTIONS FOR SUBMITTING OFFERS

5.1 Envelopes/packages containing offers must be sealed, marked and addressed as follows:

5.1.1 MARK ENVELOPES/PACKAGES:

Solicitation No. W911XK-16-R-0003 Closing Date: Reference SF 1442 box 13A Closing Time: 2:00 PM Eastern

5.1.2 ADDRESS ENVELOPES/PACKAGES TO:

Department of the Army U. S. Army Corps of Engineers, Detroit District ATTN: Contracting Branch C/O: Carlette Williams 477 Michigan Avenue, Floor 7 Detroit, Michigan 48226

5.1.3 Hand carried offers must be delivered to: Detroit District. Due to Security precautions, all Corps of Engineers visitors are now required to be screened upon entry of the McNamara Federal Building. Therefore, please allow sufficient time for turning in your proposal.

-- End of Section -

PROCEDURES

1 INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFEROR

1.1 Introduction:

Your firm is invited to submit a proposal in response to this Request for Proposal (RFP) for the “Poe Lock Gate Primary and Secondary Anchorage Removal and Replacement.” Prepare the proposal for evaluation in accordance with the solicitation. The Government will evaluate the performance capability proposals in accordance with the criteria described herein.

1.2 Project Description:

The United States Army Corps of Engineers’ (USACE) Poe Lock miter gate structure is located at the Soo Locks in Sault Ste. Marie, Michigan.

The successful contractor shall remove and replace eight (8) lock gate anchorages, four (4) primary and four (4) secondary at lock gates 1 and 3. Contract options may be awarded for an additional two primary and two secondary anchorages at Gate 2.

2 PROPOSAL COMPOSITION AND SUBMISSION

2.1 General Requirements: Submit your proposal in three (3) parts: Volume I - Technical (Factor 1 Technical Capability, and Factor 2 Past Performance), Volume II - Price (Factor 3 Price, and Pro Forma Information) and Volume III – Small Business Participation (Factor 4 Small Business Participation and Factor 5 Small Business Utilization). Submit each in a separate envelope or package with the type of proposal (i.e., technical or price) clearly printed on the outside of the envelope or package.

2.2 Proposals must set forth full, accurate, and complete information as required by this RFP. Absence of information demonstrates the lack of support for an evaluation factor. Proposals shall contain only data essential for evaluation of proposals to expedite both the RFP proposal preparation and evaluation. Data submitted must reflect the Offeror’s interpretation of criteria contained in the RFP. Proposals are to be on 8-1/2 x 11-inch paper, to the maximum extent practicable, and submitted in standard letter (8-1/2 x 11-inch) hardback loose-leaf binders. Contents of binders shall be appropriately tabbed and labeled corresponding to the proposal table of contents, affording ease of identification. The proposal shall not exceed the limit for each volume, with a font size no smaller than 10 point. Should the proposal exceed the limit, there will be an evaluation of the contents of ONLY to the maximum limit of each volume. In addition to the hard copies of the proposal, Offerors must submit an electronic version on a CD-ROM or DVD-ROM disc. Electronic copies shall have the same volume and file structure as the hard copies, and shall be in PDF file format. ONLY CD-ROM or DVD-ROM media will be accepted. Floppy discs, USB drives, etc. are not permitted. The Gantt Chart as required in Factor 3 shall be folded and inserted into the pocket of the loose-leaf binder.

Volume Title Printed Copies Digital

Copies Maximum Pages

1‐ Technical & Past Performance

Original + 7 copies 2 125

2‐ Price Original + 7 copies 2 N/A

3‐ Small Business Participation Original + 7 copies 2 25

Note: Subcontracting Plans are exempt from page count.

2.3 Number pages consecutively. There shall be no consideration of information incorporated by reference or reiteration of the RFP. Proposal presentation shall be in a manner which allows it to “STAND ALONE” without need for evaluators to reference other documents. It is allowable to combine arrangements, layout plans, and notes on single sheets in order to simplify presentation, so long as there is maintenance of clarity. Elaborate brochures or other presentation materials beyond those sufficient to present complete and effective responses are unnecessary and may give the appearance of an Offeror’s lack of cost-consciousness. Elaborate artwork, expensive paper and bindings, and expensive/extensive visual and other presentation aids are neither necessary nor wanted.

2.4 Penalty for making false statements in proposals is prescribed in 18 U.S.C. 1001.

2.5 Marking Proposals - Identifying Proprietary Technical Data & Privileged or Confidential Commercial or Financial Data: To protect trade secrets, privileged or confidential commercial or financial information incorporated in the proposal, each page, including each line or paragraph thereof, containing such information must be specifically marked to identify such data and the cover sheet must be marked with the following notice:

NOTICE:

The data contained in Page(s) ____ of ____ in the proposal have been submitted in confidence and contain trade secrets and/or privileged or confidential commercial or financial information. Such data shall be used or disclosed for evaluation purposes, provided, if a contract is awarded to the Offeror as a result, or in connection with the submission of this proposal, the Government shall have the right to use or disclose the data herein to the extent provided in the contract.

2.6 The restriction does not limit the Government’s right to use or disclose data obtained without restriction from any source, including the Offeror, and references to the aforementioned notice should be placed on each page to which the notice applies. The Government assumes no liability for disclosure or use of unmarked data and may use or disclose such data for any purpose.

2.7 Release of Information: After receipt of proposals, no source selection information will be available to any Offeror until contract award. This includes, but is not limited to, the relative standing of the Offeror’s proposal or the number or identity of the participating Offerors.

2.8 Proposal Expenses and Pre-Contract Costs: The Government is in no way responsible for costs incurred in the preparation and submission of a proposal or for any other costs incurred prior to the execution of a formal contract.

2.9 Technical Proposal Format: At a minimum, each copy of the technical proposal should follow the general format specified below. Number pages from beginning to end. Do not repeat numbering for new sections. The technical proposal should include 1) a cover letter, 2) a table of contents, and 3) required technical data. A description of each is as follows:

2.9.1 Cover Letter: The technical proposal cover letter, printed on the prime Offeror’s letterhead, shall be the first page of the technical proposal. It shall be signed by an officer of the company and must contain the following:

Solicitation number;

Name, address, telephone, facsimile numbers and e-mail address of the Offeror;

Names, titles, telephone and facsimile numbers and e-mail addresses of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this solicitation;

Names, title, and signature of the person authorized to sign the proposal;

A statement that the offer is acceptable for a period of 90 calendar days from the date of submission;

If necessary, a section entitled “Deviations.” This section is to include all deviations from the minimum RFP requirements, and, in the event of the submittal of a Final Proposal Revision, all changes made to their original proposal. Such deviations must include specific explanations concerning their nature, as well as why the Offeror thinks that they are necessary or appropriate.

Deviations are not necessarily substitutions and must not result in an Offeror’s proposal that does not meet minimum RFP criteria;

If necessary, a section entitled “Identification of Items Exceeding RFP Requirements.” This section must include a list including all items in excess of the minimum RFP requirements, and, if required to submit a Final Proposal, all changes made to their original proposal that exceed RFP minimum requirements. Such items exceeding RFP requirements must include specific explanations concerning their nature, as well as why the Offeror thinks that they are necessary or appropriate;

Acknowledgement of all amendments by number and date of issue (likewise, acknowledge all amendments on any proposal revisions.)

2.9.2 Table of Contents: The Table of Contents shall list all sections contained in the technical proposal. Provide a separate section for each evaluation criterion. Any additions or revisions to the proposal shall include an updated Table of Contents for each set.

2.9.3 Technical Data: The Technical Data section shall consist of all information furnished in accordance with the RFP requirements, including technical specifications and referenced regulations. This section shall be specific and complete, demonstrating a thorough understanding of the requirements. It shall include, where applicable, diagrams and/or charts. It shall include complete explanations of procedures and proposed programs, as well as the demonstration of the merit of the offered technical approach. It shall demonstrate all criteria requirements. It shall be an orderly, specific, and complete document in every detail.

2.9.4 Format and Contents of the Proposal/List of Tabs: The original and all copies of Volume I - Technical Proposal will be appropriately labeled as such. Each set shall be organized using the tabs specified in the chart below.

TAB CONTENTS OF VOLUME I - TECHNICAL PROPOSAL

TAB #1

FACTOR 1: Technical Capability (Experience and Organization) SUBFACTOR 1: Relevant Experience in Key Construction Areas SUBFACTOR 2: Technical Approach Summary SUBFACTOR 3: Proposed Contract Duration and Preliminary Schedule SUBFACTOR 4: Qualifications of Key Team Members

TAB #2

FACTOR 2: Past Performance

3 SELECTION PROCEDURES

3.1 Technical Evaluation: There will be an evaluation of technical proposals for conformance with the minimum RFP criteria to determine if the proposal is technically acceptable. While there is intent to keep the Offeror’s pre-award proposal effort to a minimum, proposals must provide adequate detail for evaluators to determine if the proposal is technically acceptable.

3.2 There will be an evaluation of all technical proposals by a Source Selection Evaluation Board (SSEB).

The SSEB’s duty is the assignment of a fair, unbiased technical rating for each proposal based solely on the merits of the proposal. Proposals that do not conform to the terms and conditions contained in the RFP or those that include stipulations or qualifying conditions unacceptable to the Government are not eligible for award.

There will be no consideration of pricing data during the technical evaluation.

3.3 Selection without Discussions: It is the intent of the Government to make selections based upon initial offers, without further discussions or additional information. Therefore, submit your proposal on the most favorable terms from a price and technical standpoint. Do not assume you will have an opportunity to clarify, discuss or revise your proposal. If selections are not possible from initial offers, discussions will be conducted as follows:

3.4 Competitive Range: The Contracting Officer may establish a competitive range comprised of all of the highest rated technical proposals. The range may be further reduced for purposes of efficiency, i.e., the Contracting Officer determines that the number of most highly rated proposals that might otherwise be included in the competitive range exceeds the number at which an efficient competition can be conducted.

3.5 Discussions: The Government intends to make a selection without discussions. However, there may be written or oral (i.e., telephonic) discussions with all Offerors in the competitive range. As a result, Offerors may be asked to revise their initial offers. If an Offeror's proposal is eliminated or otherwise removed from the competitive range during discussions, further revisions to that Offeror's proposal will neither be accepted nor considered.

Discussions will culminate in a request for Final Proposal Revisions, the date and time of which will be common to all Offerors.

3.6 After discussions and the subsequent receipt of final proposal revisions, the SSEB will evaluate supplemental information provided by offers, adjust previously assigned technical ratings, and provide a recommendation to the Contracting Officer. The Contracting Officer will consider the SSEB’s findings and perform a best- value analysis.

4 DEBRIEFINGS

Post-award: In accordance with FAR 15.506, Unsuccessful Offerors may request a post-award debriefing within three (3) days after the date on which the Offeror received notification of contract award. There will be no point-by-point comparisons with other Offerors’ proposals and debriefings will not reveal any information that is not releasable under the Freedom of Information Act (FOIA).

5 EVALUATION CRITERIA

5.1 Factor 1 will be evaluated using a Combined Technical/Risk Rating. The combined technical/risk rating includes consideration of risk in conjunction with the strengths, weaknesses, significant weaknesses, uncertainties, and deficiencies in determining technical ratings. Combined technical/risk evaluations shall utilize the combined technical/risk ratings shown below:

Combined Technical/Risk Ratings Method

Color Rating Description

Blue Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.

Purple Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.

Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.

Red Unacceptable Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.

5.2 Factor 2, will be evaluated using the Past Performance Relevancy Ratings and the Performance Confidence Assessments shown below:

Past Performance Relevancy Ratings Adjectival Rating Description Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

Performance Confidence Assessments Rating Method

Adjectival Rating Description

Substantial Confidence Based on the Offeror’s recent/relevant performance record, the Government has a high expectation that the Offeror will successfully perform the required effort.

Satisfactory Confidence Based on the Offeror’s recent/relevant performance record, the Government has a reasonable expectation that the Offeror will successfully perform the required effort.

Neutral Confidence No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

The offeror may not be evaluated favorably or unfavorably on the factor of past performance.

Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.

Small Business Rating Method Small Business Acceptable/Unacceptable Ratings

Adjectival Rating Description

Acceptable Proposal indicates an adequate approach and understanding of small business objectives.

Unacceptable Proposal does not meet small business objectives.

5.3 The Offeror’s conformance with the specified format and submission requirements will be considered during the technical evaluation. Material omission(s) may cause the technical proposal to be rejected as unacceptable.

5.4 The Offeror’s adherence to prescribed page and formatting limitations prescribed will be strictly adhered to and enforced. Information submitted which exceeds the specified limit will NOT be evaluated. For example, the Government will not evaluate excess information. If four pages are submitted in response to an item with a three page limitation, the information of the fourth page will not be evaluated.

5.5 Proposals will be reviewed for compliance with the technical specifications. Non-compliance with the technical specifications will be considered a deficiency and an Unacceptable rating will be assigned.

5.6 Order of Importance

This is a Best Value solicitation. During evaluation, Factor 1 Technical Capability and Factor 2- Past Performance, Factor 4- Small Business Participation and Factor 5 Small Business Utilization when combined are significantly more important than price. Factor 1-Technical Capability will be considered of higher importance than Factor 2- Past Performance. Factor 2 will be considered of higher importance than Factor 4- Small Business Participation and Factor 5- Small Business Utilization, which are equal. The Past performance, Small Business Participation and Small Business Utilization Factors, when combined, are more important than the cost/ price factor. To receive consideration for award, a rating of no less than “Acceptable” must be achieved for the Technical factor (to include all subfactors).

5.6.1 Factors and Subfactors to be evaluated.

FACTOR 1: Technical Capability (Experience and Organization) SUBFACTOR 1: Relevant Experience in Key Construction Areas SUBFACTOR 2: Technical Approach Summary SUBFACTOR 3: Proposed Contract Duration and Preliminary Schedule

SUBFACTOR 4: Qualification of Key Team Members

All subfactors are equal.

FACTOR 2: Past Performance: Each Offeror’s past performance will be reviewed to determine relevancy and confidence assessment.

FACTOR 3: Price and Pro Forma Information: The resulting award will be a Firm Fixed Price type contract. A Bid Bond required.

Factor 4: Small Business Participation: The extent of Small Business Participation will be evaluated for unrestricted acquisitions. This solicitation is solicited as unrestricted.

Factor 5: Small Business Utilization: Past Performance of Utilization of small Business Concerns.

Subcontracting Plan is required for large businesses only.

6 LIST OF EVALUATION FACTORS, SUB-FACTORS AND SPECIFIC TECHNICAL

EVALUATION CRITERIA

6.1 FACTOR 1: TECHNICAL CAPABILITY (EXPERIENCE AND ORGANIZATION)

The Experience and Organization evaluation will consider such things as an Offeror’s previous relevant experience with similar projects, the qualifications and organization of key team members, and other considerations as described in the sub-factors and elements. If the Offeror does not assume all roles in this contract, then the Offeror must clearly demonstrate that its major subcontractors have the relevant technical experience for the role they are assuming of the scope and complexity required in the Specifications. The sub-factors are described below:

6.1.1 FACTOR 1, SUBFACTOR 1: RELEVANT EXPERIENCE IN KEY

CONSTRUCTION AREAS

-.1 Submittal for Evaluation:

If the prime contractor proposes self-performing the onsite construction, ensure the proposal is clear which work the Offeror will be performing. If the prime contractor proposes to subcontract some or all of the onsite construction the Offerer must submit a Letter of Commitment from the subcontractor with the proposal. If the prime contractor proposes to use a subcontractor for the steel fabrication, the Offerer must submit relevant past experience working with the subcontractor that demonstrates successful completion of a similar project in size and complexity.

The Offeror shall demonstrate relevant experience by providing project examples of relevant work performed in the key construction areas. Submit projects that are at least 50% construction progress completed or completed and turned over no longer than ten (10) years preceding the date of this Solicitation. Submitted projects must have been performed by the Offeror as either the prime contractor or major subcontractor to be considered relevant. Any project that was less than $1,500,000 will not be considered relevant. If any firm has multiple functions or divisions, limit the project examples to those performed by the division or unit submitting the offer or by the team member. Limit each project description to 1 page.

An Offeror shall provide evidence of experience on at least three but no more than five construction projects performed in the United States. The submitted projects must demonstrate relevant work experience in the following key areas:

1. The Offeror’s ability to develop and adhere to a detailed construction sequencing schedule.

2. The Offeror’s and Steel Fabrication subcontractor’s previous work experience with fracture critical welding in conformance with American Welding Society (AWS) D1.5.

3. The Offeror’s previous work experience with AISC certified steel fabricators.

4. The Offeror’s previous work experience with working in sub-zero temperatures.

5. The Offeror’s previous work in a fully operational facility with adjacent traffic (auto or ship).

6. The Offeror’s previous work in existing lock facilities, specifically jacking/lifting lock gates.

7. The Offeror’s previous work involving working with a dive team.

In addition to the project examples, the Offeror may provide a supplemental narrative (not project lists), not to exceed two pages, explaining how any corporate experience that is not directly related to the specific projects above is applicable to this project and how the Government will benefit.

The above information is limited to projects that are well underway or that have been completed and turned over no longer than the past ten years preceding the date of this solicitation.

The Government reserves the right to verify the experience record of cited projects or other recent projects by reviewing the Government Contractor Performance Assessment Reporting System (CPARS), or other Government appraisal systems or to interview owners or references. The Government may check any or all cited references to verify supplied information.

The contractor shall also provide a copy of the steel fabricator subcontractor’s current certification that they meet AISC Certification, Certified Bridge Fabricator - Advanced (ABR).

-.2 Evaluation Criteria The Government will evaluate whether the proposal demonstrates relevant experience performed in all of the key construction areas, as evidenced in at least three projects but no more than five completed by the prime contractor, within the last ten years or currently underway and at least 50 percent complete. Projects submitted by the Offeror must clearly identify which of the key construction areas are represented in the work; a minimum of five (5) out of the seven (7) construction areas described above must be demonstrated in each of the submitted projects. Additionally, areas 1 through 4 must be demonstrated in the combined submitted projects. The projects must be of similar scope to this project and be valued at least $1,500,000.

Proposals where a contractor has two or more projects where each project demonstrates experience in ALL seven (7) key construction areas will also be considered a strength in the proposal.

Proposals where the steel fabricator subcontractor’s certification does not meet AISC Certification, Certified Bridge Fabricator - Advanced (ABR) or if the certification has expired will be removed from consideration.

6.1.2 FACTOR 1, SUBFACTOR 2: TECHNICAL APPROACH SUMMARY

-.1 Submittal for Evaluation The Offeror shall submit a narrative (not to exceed two pages) describing the overall technical approach to the contract work. The narrative shall include the following:

1) Gate jacking/shoring/diving procedure. Procedure shall include sequence of work and all shoring work necessary to support the lock gates during construction.

2) Work processes description and how work will prevent impacts to all lock operations.

3) Describe how divers plan to enter the water, depth of the deepest dive and a list of dive equipment.

-.2 Evaluation Criteria

1) A narrative that is realistic and demonstrates an understanding of the work requirements, reduces risk to lock gate damage, reduces the risk of diving operations by eliminating decompression dives and having medical treatment equipment on site and reduces interruptions of lock operations will be considered a strength.

6.1.3 FACTOR 1, SUBFACTOR 3: PROPOSED CONTRACT DURATION AND

PROPOSED SCHEDULE

-.1 Submittal for Evaluation Submit a proposed summary level schedule for construction. Schedules shall consist of a GANTT Chart on a single American National Standard Institute (ANSI) D sheet. Font size shall be a minimum of 8 and legible. The proposed schedule will, after contract award, be replaced with a final schedule as required by Section 01 32 01.00 10 Project Schedule. However, the activities listed as binding below are required to stay as proposed. The schedules shall be task oriented, indicating the number of calendar days, after Notice to Proceed, by which milestones are to be achieved. Offeror may use a critical path or other method of his choice; however, schedules shall be graphically represented. The proposed project schedule shall reflect the proposed contract duration. The proposed schedule shall include at a minimum the following construction activities:

Contract Award Date Notice To Proceed Work plan complete and approved Mobilization (Describe equipment) Shop Drawings Submitted and Approved Steel Anchorage Frames Fabrication Complete Initial Concrete Demolition Complete New Anchor Frames Installed Work on the Final Installation of Lock Anchorages Permitted (17 January 2017– this is a binding date) Final Existing Anchorage Demolition Complete Pin Plate Installation Complete and Control Dimensions Submitted Concrete Placement Complete Lever Arm and Link Bars Installed Anchorages completed, Miter Gate Tested, and Accepted by the Government (19 March

2017 – this is a binding date) Demobilization Contract Completion Date

It is the Offeror’s responsibility to identify the sequencing of the above listed construction activities. The construction schedule shall be of sufficient detail to identify by trade the work that is to be completed along with the duration of the above listed activities.

Constraints: Offeror must demonstrate the capability and flexibility to plan and schedule the complete project to meet the proposed contract completion period. Clearly identify any constraints on the schedules presented (e.g., labor or material availability, weather, etc.).

Clearly indicate the anticipated overall critical path activities on the schedule.

Offerer shall also provide a 1 page narrative outlining any scheduling assumptions, risks, logistical challenges, or any other information that the Offeror deems to be critical to understanding the proposed schedule.

-.2 Evaluation Criteria Proposed Schedule: The Government will evaluate the proposed schedule for reasonableness.