This document provides specifications for project and safety signs required under a federal construction contract. The contract involves replacing the central hydraulic system at Pike Island Locks and Dam, including new hydraulic power units, stainless steel piping, and control systems. Six precast buildings will house the new hydraulic power units and electrical equipment. Signage must be installed within 15 days per specifications for a project identification sign and safety performance sign made of treated wood, vinyl decals on plywood, and updated daily. The contractor must furnish, install, maintain and remove all signs and complete hydraulic system demolition and replacement work while minimizing lock closures to maintain waterway traffic flow.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pike Island-Hydraulic System Replacement
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 50 10.00 08
PROJECT AND SAFETY SIGNS
PART 1 GENERAL
1.1 SUMMARY
1.2 APPLICABLE PUBLICATIONS
1.3 PAYMENT
1.4 1.4 CONSTRUCTION PROJECT SIGNS
1.4.1 Project Identification Sign
1.4.2 Safety Performance Sign
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Wood
2.1.2 Sign Face
2.1.3 Fasteners
PART 3 EXECUTION
3.1 INSTALLATION
3.2 MAINTENANCE
-- End of Section Table of Contents --
SECTION 01 50 10.00 08 Page 1 100% CERTIFIED FINAL (HTC) – W911WN23B8005 Amendment 0002
SECTION 01 50 10.00 08
PROJECT AND SAFETY SIGNS
PART 1 GENERAL
1.1 SUMMARY
The work covered by this Section consists of fabricating, erecting and maintaining the Project Identification and Safety Performance signs. The signs shall be installed within 15 calendar days after Notice to Proceed and shall be maintained in good condition throughout the construction period. All items will remain the property of the Contractor and shall be removed at the end of the contract.
1.2 APPLICABLE PUBLICATIONS
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 310-1-6a (2006) Sign Standards Manual, Volume 1
1.3 PAYMENT
No separate or direct payment will be made for the items listed in this Section, and such work will be considered as a subsidiary obligation of the Contractor.
1.4 1.4 CONSTRUCTION PROJECT SIGNS
Construction project signs shall be coordinated with the Contracting Officer or designated representative. The signs shall include one Project Identification Sign and one Safety Performance Sign. The layout of all signs shall be in accordance with the standards specified in EP 310-1-6a , (Part 16 attached), the attached Project and Safety Sign Standards, and the requirements specified herein. Relevant portions of the manual are attached.
1.4.1 Project Identification Sign
One project identification sign constructed in accordance with EP 310-1-6a , Section 16., except the layout of the sign shall be as shown on the attached sample Bipartisan Infrastructure Law (BIL) Project Sign Requirements. The following information shall be used for the Project Identification Sign:
Corps relationship to project:
Design and Construction Supervised by:
Division/District
Pittsburgh District
One to three line title to describe work
SECTION 01 50 10.00 08 Page 2
Pike Island Hydraulic System Replacement
One to two line identification of project or name of sponsoring department:
One to five line identification of prime contractors - this information is optional.
1.4.2 Safety Performance Sign
One safety performance sign constructed in accordance with EP 310-1-6a , Section 16. The project title shall be as specified in paragraph Project Identification Sign.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Wood
Wood material for the posts shall be preservative treated, structural grade Douglas Fir or No. 1 Southern Pine, or better. All other wood members shall be of well seasoned, kiln dried, clear redwood, bald cypress, red cedar, Douglas fir, spruce, tulip poplar, or white pine. The lumber materials shall be free of splits, wane, and loose knots or pitch pockets. All members of the sign shall be fastened with screws or bolts of type, size, number, and spacing to provide rigid construction and neat appearance. If the vertical supports system does not rigidly support the sign due to local soil conditions and/or wind loading additional bracing of the sign supports shall be provided. This additional bracing shall be composed of 2" x 4" bracing bolted to the inside face of each 4" x 4" support post and firmly anchored to the ground behind the sign. This additional bracing is not required to be treated lumber. Two-inch x four-inch struts shall be installed between the 4" x 4" support posts to reinforce the top and bottom edges of the sign panels.
2.1.2 Sign Face
The sign faces shall be electronically printed on white non-reflective vinyl decals four mils thick. The sign face decals shall be mounted on panels of 3/4" thick high density overlay exterior plywood with single-sided vinyl facing. The entire circumference of the sign panels will be sealed and protected with white vinyl trim cap. A protective overlaminate film shall be applied over the sign face decals capable of minimizing the deteriorating effects of ultraviolet radiation and providing additional protection against weathering and application of graffiti. The BIL symbol is shown on the attached BIL Emblem Guide.
2.1.3 Fasteners
All bolts shall be 0.375" diameter and 4" long Allen head bolts, threaded to match T-nuts.
SECTION 01 50 10.00 08 Page 3
PART 3 EXECUTION
3.1 INSTALLATION
The Contractor shall affix the panels to the posts with the Allen head bolts prior to erection of the signs, including drilling counter-sunk
0.375 inch diameter holes in the posts to match the T-nut locations. The Contractor shall take all precautions necessary to protect the faces of the signs from damage during assembly and construction. The signs shall be installed upon commencement of the work under this contract. The location in which each sign is to be installed shall be cleared and leveled to facilitate the installation of, and provide easy visual contact with, the signs. Installation and positioning of the sign plate and posts shall be as indicated on EP 310-1-6a , Part 16, attached. Excavation and backfilling of the holes for posts and installation of the posts, braces, and stakes shall be such that signs are installed plumb and level.
3.2 MAINTENANCE
The Contractor shall maintain the signs in good condition and the sign site in a neat condition throughout the construction period. The safety performance record shall be updated daily.
-- End of Section --
SECTION 01 50 10.00 08 Page 4
| 01 50 10.00 08 - PROJECT AND SAFETY SIGNS |
| 01 50 10.00 08 - PROJECT AND SAFETY SIGNS |
| PART 1 GENERAL |
| 1.1 SUMMARY |
| 1.2 APPLICABLE PUBLICATIONS |
| 1.3 PAYMENT |
| 1.4 1.4 CONSTRUCTION PROJECT SIGNS |
| 1.4.1 Project Identification Sign |
| 1.4.2 Safety Performance Sign |
| PART 2 PRODUCTS |
| 2.1 MATERIALS |
| 2.1.1 Wood |
| 2.1.2 Sign Face |
| 2.1.3 Fasteners |
| PART 3 EXECUTION |
| 3.1 INSTALLATION |
| 3.2 MAINTENANCE |