OSUT_1_12_24_13_Roller_Window_Shades.pdf

PDF 55 KB Posted

Attached to
Armor OSUT 1 Federal contract opportunity
Solicitation number
W911SF-19-R-0018
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Benning

About this file

Shades

View the file

Other files for this federal contract opportunity

Other files attached to Armor OSUT 1, newest first.
File Type Posted
ARMOR_OSUT_1_-_5_Pre_Award_Addendum_1.pdf PDF
Attachment_4_Performance_Assessment_Questionnaire.pdf PDF
OSUT_1_31_31_16_Soil_Treatment_for_Subt_Termites_Control.pdf PDF
W911SF-19-R-0018-0002,_ARMOR_OSUT_1,_Amend_0002.pdf PDF
OSUT_1_07_27_26_Fluid_Applied_Air_and_Moisture_Barrier.pdf PDF
OSUT_1_08_71_00_Door_Hardware.pdf PDF
OSUT_1_10_14_02_Interior_Signage.pdf PDF
OSUT_1_01_57_20_Environmental_Protection.pdf PDF
OSUT_1_31_11_00_Clearing_and_Grubbing.pdf PDF
OSUT_1_01_78_23_Operation_an_Maintenace_Data.pdf PDF
OSUT_1_23_07_00_Thermal_Insulation_for_Mechanical_Systems.pdf PDF
OSUT_1_32_31_13_High-Security_Chain_Link_Fences.pdf PDF
OSUT_1_04_21_13_13_Nonbearing_Masonry_Veneer_Steel_Stud_Walls.pdf PDF
OSUT_1_07_42_13_Metal_Wall_Panels.pdf PDF
OSUT_1_08_81_00_Glazing.pdf PDF
OSUT_1_23_37_13_Diffusers,_Registers,_and_Grills.pdf PDF
OSUT_1_04_20_00B_Masonry.pdf PDF
OSUT_1_C2_Facility_Combined.pdf PDF
OSUT_1_07_61_14_Steel_Standing_Seam_Roofing.pdf PDF
OSUT_1_Covered_Mess_Combined.pdf PDF
OSUT_1_03_31_00.00_10_Cast-In-Place_Sturctural_Concrete.pdf PDF
OSUT_1_23_82_02_Unitary_Heating_and_Cooling_Equip.pdf PDF
OSUT_1_07_21_16_Mineral_Fiber_Blanket_Insulation.pdf PDF
OSUT_1_09_90_00_Paints_and_Coatings.pdf PDF
OSUT_1_44026_Stevon_Booker_Oscar_14_Nad_83_Site_Plan_Mod.pdf PDF
OSUT_1_09_51_00_Acoustical_Ceilings.pdf PDF
OSUT_1_32_01_19_Field_Molded_Sealants_for_Sealing_Jts_In_Rigid_Pavg.pdf PDF
OSUT_1_01_35_29_Safety_and_Occupational_Health_Requirements.pdf PDF
OSUT_1_23_00_00_Air_Supply_Venti_and_Exhaust_Sys.pdf PDF
OSUT_1_08_33_13.00_10_Metal_Rolling_Counter_Doors.pdf PDF
OSUT_1_12_48_13_13_Entrance_Floor_Mats.pdf PDF
OSUT_1_01_33_00_Submittal_Procedure.pdf PDF
OSUT_1_10_44_16_Fire_Extinguisher_Cabinets.pdf PDF
OSUT_1_23_23_00_Refrigerant_Piping.pdf PDF
OSUT_1_07_25_00_Building_Air_Barrier_System.pdf PDF
OSUT_1_03_20_01_00_10_Concrete_Reinforement.pdf PDF
OSUT_1_06_61_16_Solid_Polymer_Fabrication.pdf PDF
OSUT_1_06_20_00_Finish_Carpentry.pdf PDF
OSUT_1_01_42_00_Sources_for_Referencece_Publications.pdf PDF
OSUT_1_UFGS_22_00_00_Plumbing,_General_Purpose.pdf PDF
OSUT_1_08_91_00_Metal_Wall_Louvers.pdf PDF
OSUT_1_Latrine_Combined.pdf PDF
OSUT_1_UFGS_22_07_19_Plumbing_Piping_Insulation.pdf PDF
AR_OSUT__1_General_Requirements.pdf PDF
Statement_of_Work_-_CTA_Covered_Bleachers.pdf PDF
Statement_of_Work_-_Covered_Mess.pdf PDF
Statement_of_Work_-_Latrine_(flushable)_and_leach_field.pdf PDF
Statement_of_Work_-_OSCAR_15.pdf PDF
SOW_Cover_Sheet_-_Warner_Range.pdf PDF
Statement_of_Work_-_OSCAR_14.pdf PDF
Show all 50

Armor OSUT 1 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OUST-AR RANGE PROJECTS FY19

SECTION 12 24 13

ROLLER WINDOW SHADES

02/10

PART 1 GENERAL

1.1 GENERAL REQUIREMENTS

Provide roller window shades, complete with necessary brackets, fittings, and hardware as located in the drawings. Mount and operate equipment in accordance with manufacturer's instructions. Windows to receive a shade shall be completely covered.

a. Submit drawings showing plans, elevations, sections, product details, installation details, operational clearances, wiring diagrams and relationship to adjacent work. Include the use of same room designations as indicated on the drawings.

b. Provide manufacturer's data composed of catalog cuts, brochures, product information, and operating and maintenance instructions on each product to be used. Include styles, profiles and features.

c. Furnish samples of each type and color of roller shade fabric and roller shade channel. Shade material shall be minimum6 by 6 inch in size. Mark face of material to indicate interior faces.

d. Mock up: Install shade in area designated by Contracting Officer. Do not proceed with remaining work until the Contracting Officer approves workmanship and operation. Re-work mock-up as required to produce acceptable work. The approved shade can be used in installation.

e. Submit fire resistance data, flame spread and smoke contribution data.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM G 21 (1996; R 2002) Determining Resistance of Synthetic Polymeric Materials to Fungi

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 701 (2010) Fire Tests for Flame Propagation of Textiles and Films

UNDERWRITERS LABORATORIES (UL)

UL 325 (2002; Rev thru Dec 2009) Door, Drapery, Gate, Louver, and Window Operators and Systems

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES

SD-02 Shop Drawings

Installation; G

SD-03 Product Data

Window Shades; G

SD-04 Samples

Window Shades; G

SD-06 Test Reports

Window Shades

SD-08 Manufacturer's Instructions

Window Shades

SD-10 Operation and Maintenance Data

Window Shades

1.4 QUALITY ASSURANCE

1.4.1 Qualifications

1.4.1.1 Manufacturer's Qualifications

Obtain motor-controlled roller shades through one source from a single manufacturer with a minimum of twenty years experience and minimum of three projects of similar scope and size in manufacturing products comparable to those specified in this section.

1.4.1.2 Installer's Qualifications

Installer trained and certified by the manufacturer with a minimum of ten years experience in installing products comparable to those specified in this section.

1.4.2 Flammability Requirements

Passes in accordance with NFPA 701 small and large-scale vertical burn.

Materials tested shall be identical to products proposed for use.

1.4.3 Electrical Requirements

NFPA Article 100 listed and labeled in accordance with UL 325 or other testing agency acceptable to authorities having jurisdiction, marked for intended use, and tested as a system. Individual testing of components will no be acceptable in lieu of system testing.

1.4.4 Anti-Microbial Requirements

'No Growth' per ASTM G 21 results for fungi ATCC9642, ATCC 9644, ATCC9645.

1.4.5 (not used)

1.5 DELIVERY, STORAGE, AND HANDLING

Deliver components to the jobsite in the manufacturer's original packaging with the brand or company name, item identification, and project reference clearly marked. Store components in a dry location that is adequately ventilated and free from dust, water, or other contaminants and has easy access for inspection and handling. Store materials flat in a clean dry area with temperature maintained above 50 degrees F. Do not open containers until needed for installation unless verification inspection is required.

1.6 WARRANTY

Provide 10 year minimum limited warranty.

PART 2 PRODUCTS

2.1 WINDOW SHADES

Roller tube shall operate smoothly and be of sufficient diameter and thickness to prevent excessive deflection. Provide brackets that are appropriate for inside mount. The shade cloth shall meet the performance described in NFPA 701, small scale test. Treat steel features for corrosion resistance.

2.1.2 Room Darkening Shades

Provide room darkening (black-out) window shades designed to eliminate all visible light gaps when shades are fully closed, and conform with the following:

Basis of Design: Mecho/5 and ThermoVeil Series 0700 as manufactured by MechoShade Systems, Inc., or equal. Provide complete with blackout channels.

a. Roller tube shall be aluminum, controlled by crank operated gear box with steel rods. Provide shop fabricated light traps, consisting of a head box to house the shade roller, and U-shaped channels to serve as guides for the shade along the sides and to receive the bottom edge of the shade along the sill.

b. Provide light trap made of sheet steel having a minimum thickness of 22 gauge or anodized, extruded, aluminum. The legs of the channels shall be not less than 1-3/4 inches long and separated by the minimum distance that will permit free operation of the shade. Edges of light trap coming into contact with the shade cloth shall be smooth pile light seal. The exposed face of the head box shall be hinged or removable for access to the shade roller. The interior or unexposed surfaces of the light trap shall have a finish coat of flat black enamel. The exposed portions of the light trap shall have a factory-applied priming coat of gray paint.

c. Cloth shall be of type for blackout purposes. Make the shade from a single piece of opaque single-fabric blackout material. When not finished with a selvage, the vertical edges of the shade shall be bound or hemmed using a high-grade thread. Make needle holes lightproof by applying a suitable filler.

d. Fit the bottom edge of the shade with a steel operating bar. Shades will engage positively with bottom rail through operating bar or chain pull. Paint bars with flat black enamel. Make pull cords of No. 4 braided nylon or beaded chain having not less than 175 pounds breaking strength.

2.2 COLOR

Provide color, pattern and texture for metal and shade fabric as indicated on the drawings. Color listed is not intended to limit the selection of equal colors from other manufacturers.

PART 3 EXECUTION

3.1 FIELD MEASUREMENTS

After becoming familiar with details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy before performing the work.

3.3 INSTALLATION

Perform installation in accordance with the approved detail drawings and manufacturer's installation instructions. Install units level, plumb, secure, and at proper height and location relative to window units.

Provide and install supplementary or miscellaneous items in total, including clips, brackets, or anchorages incidental to or necessary for a sound, secure, and complete installation. Do not start installation until completion of room painting and finishing operations.

3.4 CLEAN-UP

Upon completion of the installation, clean window treatments and adjust them for form and appearance and proper operating condition. Repair or replace damaged units as directed by the Contracting Officer. Isolate metal parts from direct contact with concrete, mortar, or dissimilar metals. Ensure shades installed in recessed pockets can be removed without disturbing the pocket. The entire shade, when retracted, shall be contained inside the pocket. For shades installed outside the jambs and mullions, overlap each jamb and mullion 0.75 inch or more when the jamb and mullion sizes permit. Include all hardware, brackets, anchors, fasteners, and accessories necessary for a complete, finished installation.

-- End of Section --