SCOPE_OF_WORK_DOOR_ALARMS_BLDG_3035-AMO-18-2628.docx
DOCX document 22 KB Posted
- Attached to
- OPTION - CCTV System
- Solicitation number
- W911SF-18-T-1567
- Issued by
-
Department of the Army
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Safe_and_Secure_Site_Vist_Questions_and_answers_9_11_18_v2.docx | DOCX document | |
| Safe_and_Secure_Building_Equipment.xlsx | XLSX spreadsheet | |
| Site_Visit.pdf | ||
| Floor_Plan_3005_and_3015.pdf | ||
| CCTV_MAINTENANCE-FINAL-AMO-18-2628.docx | DOCX document | |
| Equipment_Move_Harmony_Church.pdf | ||
| Floor_plan_CCTV.pdf | ||
| Floor_plan_harmony_church_and_sand_hill_buildings.pdf | ||
| Floor_Plan_3405_3425_3245.pdf | ||
| 3_SCOPE_OF_WORK_DOOR_ALARMS_BLDG_5_23_15_6_AUG_18_-AMO-18-2628-AMO-18-2628.docx | DOCX document | |
| SURVIELLANCE_SYSTEM_UPGRADE_AND_SPECIFICATION_FOR_BLDG_3245_CCTV-AMO-18-2628.docx | DOCX document | |
| START_SHIP_FINAL_032618-AMO-18-2628.docx | DOCX document | |
| Site_Visit.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESCRIPTION OF PROJECT
Contractor shall install new Coronell door alarm panels and rewire the existing systems to meet requirements for Safe and Secure guidelines established in TRADOC Reg 350-6.
And install another monitor with like and kind on the wall at The CQ area
Sand Hill Building:
Control panel will be installed on the first floor at the CQ desk.
WORK REQUIREMENTS
Part 1 Alarm System:
a) The Contractor shall install one cornell 32 zone control panel and one digital key pad with sounder and LED display at the company CQ desk on the first floor.
b) The Contractor shall install twenty cable runs from the ten existing control panel cabinets located in each bay to the new control panel installed on the first floor CQ desk.
c) The contractor shall check the existing door switches and wiring to insure they are present and in working condition.
d) The contractor shall remove any surface mounted switches that are present in some of the buildings and replace them with recessed magnetic switches.
e) The master panel shall be flush mounted; the faceplate shall be made of anodized aluminum and shall accommodate the specific number of zone circuits.
f) The alarm panel shall have a steady green LED to indicate unarmed status; steady red LED for armed status.
g) The alarm panel shall indicate a flashing red LED and intermittent tone for alarm condition. An alarm shall sound upon opening of any door in the armed status. Indicators shall be red and green LEDS. The Controls shall have a tone mute push button switch, accessible on the faceplate and pushbutton zone control switches.
h) This project shall be inclusive of labor, and any modifications needed to complete the work requirements in accordance with the manufacturers, local, state and/or federal specifications.
i) The Contractor shall verify all project conditions prior to submission of the offer.
j) The Contractor shall install all components, devices, connections etc. in complete accordance with code requirements, manufacturer’s recommendations and procedures.
k) It shall be understood that these work requirements represent the work performed by this Contractor in view of total project requirements. Omissions from these requirements or the interpretation of details of work which are evidently necessary to carry out the intent of the total project, or which are customarily performed, shall not relieve the Contractor from performing said work.
l) The Contractor shall provide and install the entire system including connections, wiring etc., as to secure a complete and functional system.
m) The Contractor shall coordinate with the project coordinator to access the area and location of devices before the work is performed.
Part 2 – Products:
a) All materials shall be furnished complete with all necessary fittings, couplings, connectors, supports, devices, etc., as required for a complete installation.
b) Cornell Master Panel Model A-3200) (32 zone with BB series back box.
c) Power requirements: 12VDC
d) Mounting: Flush
e) Wiring: #22 AWG minimum
Part 3 – Monitor:
1.The contractor shall install another monitor on the wall beside the existing with like and kind to divide the camera viewing grids so the viewing pictures are larger.
2. The contractor shall mount the new monitor to the wall using same mounting method as existing.
3. The contractor shall set up new monitor and insure the pictures are focused and legible.