Refuse_Questions_-0004.pdf

PDF 58 KB Posted

Attached to
Fort Benning Refuse
Solicitation number
W911SF-16-B-0006
Issued by

View the file

Other files

File Type Posted
W911SF-16-B-0006-0012.pdf PDF
W911SF-16-B-0006_Follow_Up_Questions_II.pdf PDF
W911SF-16-B-0006_Conformed_8June18.pdf PDF
W911SF-16-B-0006-0011.pdf PDF
W911SF-16-B-0006_Conformed_7June18.pdf PDF
W911SF-16-B-0006_Follow_Up_Questions.pdf PDF
W911SF-16-B-0006_Questions.pdf PDF
W911SF-16-B-0006_Conformed_1June18.pdf PDF
W911SF-16-B-0006-0010.pdf PDF
W911SF-16-B-0006-0009.pdf PDF
W911SF-16-B-0006_Conformed.pdf PDF
W911SF-16-B-0006_Conformed.pdf PDF
W911SF-16-B-0006-0009.pdf PDF
Technical_Exhibit__1.pdf PDF
Technical_Exhibit__2.pdf PDF
Technical_Exhibit__3.xlsx XLSX spreadsheet
W911SF-16-B-0006-0008.pdf PDF
W911SF-16-B-0006-0007.pdf PDF
W911SF-16-B-0006-0006.pdf PDF
W911SF-16-B-0006-0005.pdf PDF
PWS_Summary_of_Changes_2Nov17.pdf PDF
W911SF-16-B-0006-0004.pdf PDF
Technical_Exhibit_(Revised).xlsx XLSX spreadsheet
MDI_CBA.pdf PDF
W911SF-16-B-0006_Conformed.pdf PDF
Questions_Answered,_16-B-0006-0002,_Fort_Benning,_DPW,_Refuse,_wdr,_26Jun17.pdf PDF
W911SF-16-B-0006-0002.pdf PDF
W911SF-16-B-0006_Conformed.pdf PDF
J A_Redacted _16-D-0003 _Fort_Benning _DPW _Refuse _wdr _19Sep16.pdf PDF
W911SF16B00060001BenningRefuse.docx DOCX document
Solicitation _W911SF-16-B-0006_Fort_Benning _DPW _Refuse_Recycle_Collection_29Jul16.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911SF‐16‐B‐0006‐0004

Fort Benning Refuse Questions

1. PWS 1.7 states “Hours of Operation: The Contractor is responsible for conducting business, between the hours of 0700-1800, Monday through Friday except Federal holidays or when the Government facility is closed.” CLIN 0006 requires 6xwk pickup. Please revise times to include Saturday.

Answer: Time and days will be corrected to include Saturday in the Performance Work Statement (PWS).

2. PWS 1.17.1 Project Manager and 1.17.2 Contract Manager seem to be referring to the same person. Please confirm that these sections are referring to the same person and that two people to do the same job are not needed. Please omit one of these from the PWS.

Answer: Paragraph 1.17.2 has been removed from the PWS.

3. PART 3 GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND

SERVICES: Is the contractor given any Government furnished property on this contract?

Answer: This contract does not include any Government furnished property

(GFP).

4. TE-3: Schedule is not accurate, and does not depict the current service levels at Ft Benning. This schedule is back from the contractor in 2004. Please provide a revised TE that will match the CLIN schedule and that will match the frequencies that the CLIN schedule depicts; e.g. CLIN 002 has 220 8 YDS that go 2 x week. These aren’t listed in TE -3. Which containers go 2 x wk? 1 x wk? 3 x wk? 6 wk?

Answer: Technical Exhibit 1 (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

5. TE-3: Schedule is not accurate, and does not depict the current service levels at Ft Benning. Where are the 4x wk and 5 x wk 8 CY containers? Why are these not listed on the TE and CLIN schedule?

Answer: Technical Exhibit 1 (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

6. TE-3: Container quantities do not match current inventory level at Fort Benning, and is from the contract in 2004. Please revise as the 8 CY total is more than two times current inventory level and locations are incorrect, 8CY OCC total is more than 160 more than current level and location levels are incorrect, 35 CY Compactor total is more than double current inventory level and locations are incorrect, 20 CY total is close to current level but locations are incorrect, and 40CY total is close to current inventory level but locations are incorrect.

Answer: Technical Exhibit 1 (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

7. PWS 5.1. states” The Contractor shall be required to manage all wastes generated. The Contractor shall determine the most efficient collection frequency container type, size, and container location to meet the requirements of this PWS.

Historical data on container types and schedules on services is provided in TE-3.” This statement is contradictory to the CLIN schedule that should follow TE-3. As of right now, TE-3 does not have a frequencies listed beside the container locations. These must match in order to bid this contact because otherwise you do not know what container locations go at which frequencies. If you are billing by a certain frequency (1 wk , 2 x 3 wk, etc.) then you have to know which container goes with what frequency.

Answer: Technical Exhibit (TE) 1 has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

8. TE-3: The Roll-off CLINS and Compactor CLINS do not match the inventory in TE 3 and the frequencies are not listed in TE-3. These need to match in order to determine what containers would be viewed as extra collections in CLINS 0019, 0021, 0023.

Answer: Technical Exhibit (TE) 1 has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

9. TE-3: An example of the TE 3 being incorrect is that Bldg 4000 has no containers listed. It currently has several containers.

Answer: Technical Exhibit (TE) 1 has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

10. Overall Bid: If the Government wants to have collections done by the pickup, we suggest the FEL and RO/Compactors respectively, be billed by a total aggregate of pickups, or eaches, following an established, correct container collection schedule, and not broken out by different container frequencies. This would greatly help the Government in tracking container collections. Regardless the CLIN structure, the collection schedule has to match CLIN structure otherwise this contract cannot be bid.

Answer: Collection schedule that is on the solicitation will stay as written. The revised (TE) 1 has collection frequency which allows it to match CLIN structure.

11. Please provide the applicable wage determination for this bid opportunity? Or most current collection bargaining agreement (CBA)?

Answer: The current Collective Bargaining Agreement (CBA) is provided. See attachment

12. Will the government provide, as an exhibit to this solicitation, a copy of Mark Dunning agency level protest dated 25 August 2016?

Answer: The agency level protest submitted by Mark Dunning dated 25 August 2016 will not be provided.

13. What is the status of the IGSA between Fort Benning and the City of Columbus for post wide recycling collection services?

Answer: The status of the IGSA has not been determined, recycle is currently a part of this contract but subject to removal when an agreement has been reached between both parties.

14. What are the details of the bridge contract in which the government is currently operating under the for the existing refuse collection contract performance? Please provide the terms and total amount of the bridge contract amount?

Answer: This information has no bearing on the current solicitation, so it will not be provided.

15. Will the government enact or make any type of age requirement for metal dumpsters and/or roll off containers required to perform this contract? Since this procurement is an invitation for bid – cost is basically the top criteria forward– without some requirement of equipment age the price competitiveness of other bidders will be severely impacted. As a point of reference – Fort Polk had recently required the use of NEW dumpsters on its recently awarded refuse contract. In addition, Fort Bliss provides (as GFE) all dumpsters and roll off containers for it respective and similar refuse collection contract. Any consideration of this request will be greatly appreciated.

Answer: All containers must be serviceable in accordance with (IAW) the standards in the PWS.

16. Section 5.1.8.1.1 – To make the reimbursed tipping fees more easily managed by both parties, would the government considered adding a separate line item into the Clin schedule to keep this expense separate and tractable during the term of the contract?

Answer: No, a separate line will not be considered. CLIN schedule will stay as it is currently listed for tipping fees.

17. Please provide TE A in excel format.

Answer: Technical Exhibit (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

18. Please provide SF 1449 CLIN price schedule in excel.

Answer: Price schedule will not be provided in Excel format.

19. Does the Government provide a place on Ft Benning for the contractor to store extra equipment and park the trucks when not in use for this contract?

Answer: A lay down area can be leased to contractors by the DPW Master Planning and Real Property department.

20. Could the Government please provide the correct number of 8CYD refuse cans? In Technical Exhibit A when you add the cans up it comes to 686 cans the total shows 1299 and in the CLINS it has approximately 650 cans.

Answer: Technical Exhibit (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

21. Could the Government please provide the correct number of 8CYD recycle cans?

In Technical Exhibit A when you add the cans up it comes to 178 cans the total shows 345 and in the CLINS it has approximately 350 cans.

Answer: Technical Exhibit (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

22. Could the government please provide the correct number of 20CYD cans? In Technical Exhibit A when you add the cans up it comes to 24 cans the total shows 46 and in the CLINS it has approximately 74 cans.

Answer: Technical Exhibit (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

23. Could the government please provide the correct number of 40CYD recycle cans?

In Technical Exhibit A when you add the cans up it comes to 5 cans the total shows 10 and in the CLINS it has approximately 60 cans.

Answer: Technical Exhibit (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

24. Does the Government provide a place on Ft Benning for the contractor to store extra equipment and park the trucks when not in use for this contract?

Answer: A lay down area can be leased to contractors by the DPW Master Planning and Real Property department.

25. The compactors listed do not need to go 6 x wk. Furthermore, there are too many compactors listed on the route sheet and not enough listed in the CLIN structure to provide adequate servicing. There is also no mention of the (4) Cardboard Only compactors. Please revise.

Answer: Technical Exhibit (TE) has been revised and added as an attachment.

26. There are currently over 200 8 CY Cardboard only containers on Post. The bid sheet only allows for collections of 64 containers (Note: CLIN structure does not list any containers that go 1 x wk), and the route sheet calls for 345 containers. Please revise.

Answer: Technical Exhibit (TE) has been revised and added as an attachment.

27. Currently, we are needing around (45) 20/40 CY per month in order to assist with the ever changing temporary roll-off work around post. The solicitation is silent on the number of containers needed in order to support this effort. Please consider adding these extra requirements in order to level the playing field for all contractors bidding on this requirement.

Answer: The solicitation will stay as written.

28. The PWS is silent in regards to the current effort required to collect and dispose of scrap metal. The current average of scrap metal collections is around 10-15 per month, and requires several 20 CY containers to accomplish this effort. Furthermore, the PWS does not state if the scrap metal proceeds is to be kept by the contractor or reimbursed to the Government. Please advise.

Answer: See Paragraph 5.1.3.2 of the PWS.

29. PWS Part 1 Section1.21 1.6.4 Contractors Manpower Reporting Numbering is out of order, Will the Government please correct the numbering sequence?

Answer: Numbering sequence corrected to 1.21.

30. PWS Part 5 Section 5.1.3 states "Contractor shall be entitled to compensation for removal of its recycle containers in accordance with the contract price established in the Contract Line Item established for that purpose (CLIN XXX)." Would the Government please clarify CLIN XXX?

Answer: That statement has been removed from the solicitation. See conformed copy of the solicitation for paragraph 5.1.3.

31. PWS Part 5 Section 5.1 states "Historical data on container types and schedules on services is provided in TE-3." Is this statement referring to Technical Exhibit A in PWS Part 6 or is there additional information that will be provided to contractors?

Answer: Technical Exhibit (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

32. This solicitation includes FAR clause 52.212-1 INSTRUCTIONS TO OFFERORS-- COMMERCIAL ITEMS (OCT 2015) and FAR clause 52.214-5 SUBMISSION OF BIDS (MAR 1997) and BIDDERS INSTRUCTIONS.

FAR clause 52.212-1 states "Offers may be submitted on the SF 1449, letterhead stationery, or as otherwise specified in the solicitation."

FAR clause 52.214-5 states

"a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.

(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.

(c) Telegraphic bids will not be considered unless authorized by the solicitation;

however, bids may be modified or withdrawn by written or telegraphic notice.

(d) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.

(e) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.

BIDDERS INSTRUCTIONS (p 101) states "Bidders shall ensure bids are submitted in accordance with FAR clause 52.214-5: Also include:

-Total of Base Year, total of Option Year One and Aggregate total.

-Completed pricing (all CLINS shall be priced)

-Acknowledged amendments, if applicable

-Completion of the following representations and certifications (copy furnished). 52.212- 3 Alt I; 52.219-1 Alt I; and 52.209-7.

32a. How would the Government prefer contractors to provide Offers? On SF 1449, on letterhead stationery, or in another manner?

Answer: The FAR gives the contracting officer the flexibility to state a specific method. Submission is your choice (IAW) (52.212-1(b)).”

32b. The reference to FAR clause 52.214-5 within the BIDDERS INSTRUCTIONS indicates that the Government would like bidders to package their offer in accordance with that FAR clause. Can the Government please confirm that this is an accurate interpretation of that instruction?

Answer: Package bids in accordance with FAR clause 52-214-5.

32c. FAR 52.212-1 item (4) states offeror’s must show… "A technical description of the items being offered in sufficient detail to evaluate compliance with the requirements in the solicitation. This may include product literature, or other documents, if necessary.”

The solicitation does not contain any other instructions regarding how contractors are to show they meet the requirements of the PWS. Does the Government have a specific format that offerors should use to provide this technical description?

Answer: No, how you submit is bidder’s choice.

32d. FAR 52.212-1 item (10) states "Past performance information, when included as an evaluation factor, to include recent and relevant contracts for the same or similar items and other references (including contract numbers, points of contact with telephone numbers and other relevant information." The solicitation does not contain any other instructions regarding providing past performance information. Will the Government confirm that because past performance is not included as an evaluation factor the Government does not want contractors to provide Past Performance information?

Answer: Although past performance is not an evaluation factor it will be considered when determining responsibility.

33. BIDDERS INSTRUCTIONS (p 101) states "Bidders shall ensure bids are submitted in accordance with FAR clause 52.214-5: Also include:

-Total of base period, total of optional years one, two, three and four and the aggregate total.

-Completed pricing (all CLINS shall be priced)

-Acknowledged amendments, if applicable

-Completion of the following representations and certifications (copy furnished). 52.212- 3 Alt I; 52.219-1 Alt I; and 52.209-7.

-Pre-award Information Sheet

33a. Please confirm that the above listed information is the only content the Government requires for a complaint bid.

Answer: Submit your bid in accordance with the information requested in the solicitation.

33b. Please confirm that the Government would like the above listed information packaged in accordance with FAR clause 52.214-5.

Answer: Submit your bid in accordance with the information requested in the solicitation.

34. BIDDERS INSTRUCTIONS (p 102) sites FAR 9.104-1 GENERAL STANDARDS.

Does the Government want offerors to provide proof of responsibility in accordance with the items identified in FAR 9.104-1?

Answer: No, this information may be requested in accordance with FAR Part 9.104-1

35. BIDDER INFORMATION (p 103) states “…Contract award will be made to the responsible bidder whose bid represents the lowest price for the required services per FAR 52.214-12. Please confirm that the Government requires only offeror pricing and contractual information within each bid.

Answer: Furnish the information required by the solicitation.

36. What is the current amount of the annual contract?

Answer: The total value of the current contract is $4.3M, contact the current contractor for more specific information.

37. Page 3 – Item#1 – Are we to provide a price per day for the Phase in Period?

Answer: Provide a unit price per day/job, and total extended price for each CLIN.

38. Item #2 – Clarification of Unit Price – Do you want a price per pickup per container, or something different?

Answer: Provide price per pick-up.

39. Page 4 – Item #3 – Clarification of Unit Price – Do you want a price per pickup per container, or something different?

Answer: Provide price per pick-up.

40. Item # 4 – Clarification of Unit Price – Do you want a price per pickup per container, or something different?

Answer: Provide price per pick-up.

41. Page 5 – Item #5 – Clarification of Unit Price – Do you want a price per pickup per container, or something different?

Answer: Provide price per pick-up.

42. Item #6 – Clarification of Unit Price – Do you want a price per pickup per container, or something different?

Answer: Provide price per pick-up.

43. Page 6 – Item #7 – Clarification of Quantity – 1,040 – Provide explanation of “clean”.

Are these containers ordered for the Recycle facility periodically? Assuming they are delivered & removed upon request?

Answer: Clean – See definition in PWS paragraph 5.1.2. Containers are delivered and moved upon request.

44. Pages 6 thru 8 – Item #8 –# 12 – 20yd OT 1x wk – Are we to provide a haul price and disposal cost/ton? Is this 25 containers with 1,300 hauls estimated?

Answer: Provide price per pickup

45. Page 7 – Item #10 – #11 – 40yd OT – Same as Question #6

Answer: Provide price per pickup

46. Page 9 – Item #13 – Quantity 18,000 – Provide definition of 18,000.

Answer: The approximate tonnage collected annually.

47. Page 9 – Item #14 – Quantity 780 – 35yd CP – Are we to provide a haul price and disposal cost/ton?

Answer: Provide price for haul and disposal per pickup.

48. Page 10 – Item #15 – Quantity 6,000 – 24,000 tons – Provide explanation of what we are to price.

Answer: Provide price for any additional tonnage over the annual collected amount.

49. Page 10 – Item #16 – Are these just extra pick ups?

Answer: Yes, these are extra pick-ups “as ordered.”

50. Page 10 – Item #16 – Are you asking for a delivery price per container?

Answer: Provide price per pickup

51. Page 11 – Item #17 - #18 – Same as Question #15.

Answer: Provide price per additional placement of any additional containers.

52. Page 12 – Item #19 – Additional services for 35 yd CP’s? Are we to provide a haul price and disposal cost/ton?

Answer: Provide price for any additional pick-up and disposal of 35 CY compactors.

53. Page 12 – Item #20 - Are you asking for a delivery price per container?

Answer: Provide price per additional placement of any additional containers.

54. Page 12 – Item #20 - Are we to provide a haul price and disposal cost/ton?

Answer: Provide price for haul and disposal for placement of additional containers.

55. Page 13 thru Page 14– Item #21 - #23– Same as Questions #18 & #19.

Answer: Provide price for any additional pick-up and disposal of 20 CY containers.

56. Page 14 – Item #24 – Provide definition of Emergency Pick up. Price would be different for FEL container vs Roll Off Container.

Answer: Emergency pick-ups are natural disasters and environmental spills.

57. Page 16 – Item #26 – Please explain/clarify the breakdown of what is to be provided.

Answer: Provide your price to report the required information.

58. Pages 17 – 29 – Item #1001 - #1025 – Assuming this is for the 2nd year?

Answer: CLINs 1001 – 1025 are for optional ordering period I.

59. Page 69 – Item #4026 – Are you requesting a Lump sum for removal of all equipment?

Answer: Provide the pricing to remove all your equipment as you phase-out.

60. Page 127 – Part 5 – Specific Tasks – Historical data, container types and schedules provided in TE-3. – Can not locate TE-3.

Answer: Technical Exhibit (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

61. Page 130 – TE-A – Can you provide service frequency for each location identified?

Answer: Technical Exhibit (TE) has been revised and added as an attachment.

See revised TE for service levels, locations and frequencies.

62. Due to the time frame of the Bid date, what is the realistic/anticipated start date?

Answer: Phase-in period to begin 1 January 2018 with full operation 1 February 2018.