20240719_RFI_604.pdf
PDF 64 KB Posted
- Solicitation number
- W911SD-24-R-0105
About this file
This document is a Request for Information (RFI) response regarding the upgrade of Central Power Plant 604 at West Point, NY. The RFI provides responses to several questions related to the upcoming solicitation for this project. Key details include:
The solicitation number is W911SD-24-R-0105, and the project is for the renovation of the Central Power Plant (Building 604) at West Point. The scope includes upgrades to the building envelope, facility support areas, combustion and ventilation systems, and supporting electrical, plumbing, and structural systems. To be considered similar in size, projects must be at least $30 million in total contract value and at least 50,050 square feet requiring renovation. For the past performance evaluation, the government will consider projects that include civil, architectural, preservation, structural, and life safety work. The government may use information from various sources, including CPARS, to evaluate past performance.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Response – Upgrade of Central Power Plant 604.
19 July 2024
John Duncombe – PM
RFI: Upgrade of Central Power Plant 604.
Questions:
1. PDF page no 67 Volume 1 TAB D- If it’s a JV does each partner need to complete certs and Reps.
The Offeror submitting the proposal shall compete Tab D, Section K, “Representations, Certifications, and other statements of Offerors.”
2. PDF page no 74 Volume 2 Mission Capability (c) Element 3 Technical Experience, will the govt. consider a project at the size of 25 Million and 20000 SF, can the govt. be flexible with the square footage factor. Can it be 30 Million or 50,050 SF.
In accordance with solicitation W911SD-24-R-0105, Section M, Evaluation Factors for Award, paragraph c, (2), Element Three, “To be similar in size, the effort must be at least $30 Million in terms of total contract value and at least 50,050 square footage requiring renovation.”
3. PDF page 75 Factor 2 Past Performance: what is the size of the projects to be submitted. How many projects have to be submitted for review is it 5 to confirm for this factor as well, is this in lieu of projects being submitted under element 3 technical experience? Is CPARS accepted in lieu of PPQ
To be similar in size, the effort must be at least $30 Million in terms of total contract value and at least 50,050 square footage requiring renovation.
To be relevant, the recent efforts when combined must include all of the following similar areas of work such as Civil, Architectural, Preservation, Structural, and Life Safety work to include work on Fire Protection and Standpipe systems, Fire Alarm systems, Plumbing, Heating Ventilation and Air Conditioning, electrical, Information Technology and Communication systems, hazardous materials, and project phasing.
In conducting the Past Performance evaluation, the Government reserves the right to use both the information provided in the Offeror’s Past
Performance Volume and information obtained from other sources, available to the Government, such as: the Contractor Performance Assessment Reporting System (CPARS), Electronic Subcontract Reporting System (eSRS), o other databases; the Defense Contract Management Agency (DCMA); and interviews with Project Managers and/or Contracting Officers, personal professional knowledge, and other sources.