This document contains a tower inspection report and related federal contract opportunity solicitation. The tower inspection report provides details on the condition of a 40-foot communication tower located at Site 8, including structural evaluations, foundation assessments, guy wire fittings and corrosion inspections. The related federal contract opportunity is solicitation number W911SA23Q3109 from the Department of the Army Materiel Command Mission and Installation Contracting Command Fort McCoy for LMR communication tower inspections and maintenance services at Fort Hunter Liggett and Parks Reserve Forces Training Area in California. The solicitation seeks inspection and maintenance of LMR communication towers but does not specify pricing terms, response dates or other contract details.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site and Tower Information Location/Site ID/Tower Name Tower Manufacturer/Model No. UNK Tower Type GPS Coordinates Weather Description of facility Road conditions/Accessibility Accessibility easy 4x4 during rain Inspector

1. SITE PLAN

1.1 Indicate the tower layout relative to north, include relationship of equipment shelter.

1.1.1 Self Supporting Tower-show site view and assign legs a letter designation.

1.1.2 Guyed Tower - show site view and assign anchors & legs a letter designation.

1.1.3 Mono Pole

Mike Ruch / Sabino Perez Date(s) 3/25/2022

Tower Height (ft) 40'

Tower Inspection Report

SSS - Free Standing Structure

35.9509 -121.2344 sunny concrete building tower on top of structure with stairs to tower

Job No. 22-049Site 8 X

L 1

L 3 L 2

L 1

L 2L 3

N

E

S

W

2. TOWER ELEVATIONS

2.1 Indicate tower height above ground.

2.2 Indicate locations of all antennas, antenna mounting brackets, microwave dishes.

This information shall show the relation to north.

St ru ct ur e He ig ht

A bo ve G ro un d

He ig ht P oi nt

A bo ve G ro un d

N

EW

S

3. TOWER STRUCTURE

3.1 General conditions?................................................................................ Good

3.2 Are any loose bolts present?.................................................................... yes

3.3 Are any damaged members present?....................................................... no

3.4 Are signs of unusual stress or vibration present?...................................... no

3.5 Any missing members?............................................................................ no

3.6 Are climbing ladders, platforms and safety equipment secure?................ yes

3.7 Structural Members

3.7.1 Spot check at least ten (10) bolts on vertical tower members at intervals of approximately twenty-five (25) feet apart on all tower faces.

3.7.2 Record the number of bolts and/or nuts that were found missing.

________0________

3.7.3 Record the percentage of bolts that were checked and found to be loose.

3.7.4 Inspect structural members for fractures, bends and defective welds.

3.7.5 Ensure the tightness of tower base anchor bolts.

3.7.6 Inspect the general condition of stub antenna towers.

3.7.7 Specific weld joint inspections.

3.7.7.1 Guyed tower cantilevered joints above the guy level.

3.7.7.2 Guy and torque arm lugs.

3.7.7.3 Welds on equalizer plate where it connects to anchor shaft.

4. TOWER FOUNDATIONS & GUY ANCHORS

4.1 General conditions?

4.1.1 Are any cracks observed?......................................................................... no

4.1.2 Are there any signs of movement?.......................................................... no

4.1.3 Are anchors clear of brush, vines and trees?............................................ yes

4.1.4 Is tower and anchors fenced?................................................................... yes

4.1.5 Is grading sufficient to ensure proper water drainage?............................. yes

4.1.6 Is guy anchor head clear of earth?............................................................ yes

4.1.7 Any evidence of anchor bolt corrosion?................................................... n/a

4.1.8 Any low spots that may collect moisture?................................................ n/a

4.2 Structural Members

4.2.1 Inspect guy plates and rods for bends and fractures.

4.2.2 Inspect concrete tower foundation(s) for cracking, spalling and settling.

4.2.3 Inspect guy anchor foundations for cracking, weathering and creepage.

4.2.4 Inspect anchor rod condition below earth to a depth of at least 12 inches.

4.2.5 Has base of tower been properly grouted with sufficient drain holes?

4.2.6 Check drain holes at base for any obstructions.

Sa tis fa ct or y

U ns at isf ac to ry (S ee Ite m

N /A

5. GUY WIRES & FITTINGS

5.1 General conditions?

5.2 Connection points (top and bottom) condition?

5.3 Are end fittings secure?

5.4 Is rusting evident? yes

5.5 Is vibration observed?

5.6 Is guy wire tensioned properly?

5.7 Structural Members

5.7.1 Inspect all turnbuckles for slippage and their condition.

5.7.2 Inspect the turnbuckle jam-nut safeties and cable safeties

5.7.3 Inspect all guy cable clamps for security and slippage.

5.7.4 Inspect all pre-forms for unwinding and slippage.

5.7.5 Inspect all shackles, clevises and thimbles.

5.7.6 Inspect guy wire dead ends.

5.7.7 Visually inspect all guy wires with binoculars for broken strands and or damaged insulators.

6. PAINT & OBSTRUCTION MARKING

6.1 General conditions?

6.2 Is rusting evident? yes

6.3 Is painting necessary?

6.4 Is there any paint splatter near the surrounding area? no

6.5 Rust & Corrosion

6.5.1 Inspect for any particular portion of the tower that appears to have rust.

6.5.2 Inspect all antenna mounts and hardware for rust.

6.5.3 Inspect all guy plates and rods for rust and corrosion.

6.5.4 Inspect all guy cable clamps for rust.

6.5.5 Inspect ice shields for rust. (If present)

6.5.6 Inspect transmission line clamps and hanger bolts for rust.

6.6 Tower Paint

6.6.1 Inspect percentage of paint for peeling, flaking and fading.

6.6.2 Check visual effectiveness of the paint.

7. ELECTRICAL & LIGHTING SYSTEMS

7.1 General condition?

7.2 Obstruction lights (circle one) YES NO

Condition_______________________________________________________

Sa tis fa ct or y

U ns at isf ac to ry (S ee It em

N /A

8. EXPLANATION OF UNSATISFACTORY CONDITIONS

Specification Section

Top

20' Base

Inspector Signature __________________________________________________ Date ______________________

Surface rust on guy wires holders.

Surface rust on guy hardware.

Tree growing through the bottum of the stairs Wood structure could use a new coat of paint

Surface rust on guy wires and hardware.

Idle hardware was removed leaving an unpainted spot Loose grounds on antenna.

Surface rust on bottom plate of tower.

Description of Condition Loose bolt on top.

Surface rust on hardware.

Surface rust on angled iron.

Loose and cut communication wire.

(missing) 3/25/2022

3/25/2022

Mike Ruch 3/25/2022