W911SA21B2007 Attachment 2 SOW Updated 23 July 2021.docx

DOCX document 754 KB Posted

Attached to
Interior & Exterior Renovation of Various Buildings at Fort Hunter Liggett, CA
Solicitation number
W911SA21B2007
Issued by

About this file

This pre-solicitation notice describes an upcoming federal contract opportunity for interior and exterior renovation work at various buildings on Fort Hunter Liggett in California. The Mission and Installation Contracting Command at Fort McCoy intends to issue a solicitation within 30 days seeking fixed-price bids to renovate buildings 301, 301B, 301C, 301J, and upgrade bathrooms in building 296. The work includes activities such as roofing, siding, window, and door replacements, electrical and lighting upgrades, flooring installation, bathroom fixture replacements, and painting services. The period of performance is anticipated to last until September 2022. The estimated value is between $1 million and $5 million. The NAICS code is 236220 for commercial and institutional building construction with a small business set-aside. Interested vendors should monitor the federal business opportunities website for notice of solicitation issuance and site visit details.

View the file

Other files

File Type Posted
W911SA21B2007 Abstract Page 2.pdf PDF
W911SA21B2007 Abstract Page 3.pdf PDF
W911SA21B2007 Signed Abstract Page 1.pdf PDF
W911SA21B2007 Complete Abstract.pdf PDF
W911SA21B2007 Attachment 18 Picture Flooring.jpeg JPEG file
W911SA21B2007 Amendment 0002.docx DOCX document
W911SA21B2007 Attachment 17 Picture Flooring.jpeg JPEG file
W911SA21B2007 Attachment 15 Picture Flooring.jpeg JPEG file
W911SA21B2007 Attachment 13 Picture Flooring.jpeg JPEG file
W911SA21B2007 Attachment 16 Picture Flooring.jpeg JPEG file
W911SA21B2007 Attachment 14 Picture Flooring.jpeg JPEG file
W911SA21B2007 Attachment 8 Wage Determination 22 July 2021.pdf PDF
W911SA21B2007 Attachment 11 Picture Sidewalk Repairs.pdf PDF
W911SA21B2007 Attachment 12 Bldg 301 Asbestos Survey.pdf PDF
W911SA21B2007 Amendment 0001.docx DOCX document
W911SA21B2007 Site Visit Sign In Sheet.pdf PDF
W911SA21B2007 Attachment 5 Bldg 301C Floor Plan.pdf PDF
W911SA21B2007 Attachment 1 AT OPSEC.pdf PDF
W911SA21B2007 Attachment 4 Bldg 301B Floor Plan.pdf PDF
W911SA21B2007 Attachment 8 Wage Determination.pdf PDF
W911SA21B2007 Attachment 6 Bldg 301J Floor Plan.pdf PDF
W911SA21B2007 Attachment 2 SOW.pdf PDF
W911SA21B2007 Attachment 3 Bldg 301 Plans.pdf PDF
W911SA21B2007 Attachment 9 SF 24 Sample.pdf PDF
W911SA21B2007 Solicitation.docx DOCX document
W911SA21B2007 Attachment 7 Bldg 296 Floor Plan.pdf PDF
W911SA21B2007 Attachment 10 FHL Form 7.pdf PDF
W911SA21B2007 Attachment 5 - Bldg. 301 Main.pdf PDF
W911SA21B2007 Attachment 7 - Fort Hunter Liggett 301C Floor 01.pdf PDF
W911SA21B2007 Attachment 4 - SOW -Reno 301 Complex.pdf PDF
W911SA21B2007 Attachment 6 - Fort Hunter Liggett 301B Floor 01.pdf PDF
W911SA21B2007 Attachment 3 - COVID-19 Site Visit Information.docx DOCX document
W911SA21B2007 Attachment 8 - Fort Hunter Liggett 301J Floor 01.pdf PDF
W911SA21B2007 Attachment 2 - TE-5 Construction.xlsx XLSX spreadsheet
W911SA21B2007 Attachment 1 - Wage Determinations.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Project Site Address:

Building 301 Complex Renovations U.S. Army Garrison – FHL Monterey County, CA 93928

Submitted by:

Directorate of Public Works – Engineering Division U.S. Army Fort Hunter Liggett Building 232 California Avenue Fort Hunter Liggett, Monterey County, CA 93928

Revision Date:

July 20, 2021

Table of Contents

1.0GENERAL- 4 -
1.1 OBJECTIVES AND CRITERIA- 4 -
1.1.1 General Information.- 4 -
1.1.1.1 Project Number.- 4 -
1.1.1.2 Period of Performance.- 4 -
1.1.2 Goal and Objectives.- 4 -
1.1.2.1 Agreement of Confidentiality.- 4 -
1.1.2.2 Betterments and Enhancements Considerations.- 4 -
1.1.2.3 Proprietary Names.- 5 -
2.2 Fort Hunter Liggett physical security requirments- 5 -
2.2 Personnel Security- 5 -
2.2.1 Access and General Protection/Security Policy and Procedures.- 5 -
2.2.2 Contractors that Require Access to DOD Facility or Installation.- 5 -
2.3 Physical Security.- 5 -
2.3.1 Identification Badges.- 6 -
2.3.2 Antiterrorism Training.- 6 -
2.3.2.1 iWatch Training.- 6 -
3.0 Construction Requirements- 6 -
3.1 Contractor Requirements.- 6 -
3.2 Conformance with Environmental Management Systems.- 8 -
3.3 Submittals.- 8 -
3.3.1 Government Review.- 8 -
3.3.2 Government Approval.- 9 -
3.3.3 Substitutions.Error! Bookmark not defined.
3.3.4 Referenced Specifications.- 9 -
3.3.5 Project Schedule.- 9 -
3.3.6 Project Submittals.- 9 -
3.3.7 General Requirements.- 9 -

STATEMENT OF WORK

Building 301 Complex Renovations U.S. Army Garrison –FHL Jolon, California

1.0 Directorate of Public Works – Fort Hunter Liggett pg. - 14 -

2.0 GENERAL

1.1 OBJECTIVES AND CRITERIA

1.1.1 General Information.

The construction shall comply with the specifications and requirements contained in this Statement of Work (SOW). The design and technical criteria contained and cited in this SOW establish minimum standards for construction quality. During the contractor’s review of this SOW, items not specifically address shall adhere to the National Electric Code, Uniform Plumbing Code Unified Facility Criteria (UFC), specification and the latest local, state and federal code to include none specifiecally address items.

1.1.1.1 Project Number.

1.1.1.2 Period of Performance.

The Performance duration shall be three hundred and sixty (360) days from the notice to proceed.

1.1.2 Goal and Objectives.

The objective of this project is to upgrade the interior and exterior to the following buildings: 301, 301B 301C, 301J & 296. All listed buildings are located on Government-owned land at Fort Hunter Liggett (FHL), CA 93928. This work shall consist of exterior and interior work such as: painting (exterior/interior), wall and roofing panel replacement, sidewalk repairs, light replacement, doors and windows replacement, floor replacement and bathrooms upgrades. Additionally, minor plumbing and electrical repairs and upgrades shall be required as part of the Statement of Work (SOW).

1.1.2.1 Agreement of Confidentiality.

The contractor will be required to sign an agreement of confidentiality with the Government prior to release of said items. AS-Built drawings and Conceptual Design drawings provided by the Government shall be used as information purpose only. The Contractor is not to rely solely on any data or dimensions shown on these drawings. Any dimensions, elevations, existing conditions, or utilities shown on these drawings which shall in any way be incorporated into and/or shown in the design drawings, specifications, materials or control estimate of this project, must be field-verified by the Contractor.

1.1.2.2 Betterments and Enhancements Considerations.

All proposals received MUST include the minimum requirements set-forth in this statement of work in addition to providing AS-built drawing at the completion of the project to be considered for evaluation and award. In no case will proposals be accepted to allow for inclusion of betterments or enhancements after final layout has been approved by the government. Betterments and enhancements will not be considered unless the proposal meets the minimum requirements set-forth in this statement of work. Contractors are encouraged to review the statement of work to familiarize themselves with all of the available options and alternatives included herein.

1.1.2.3 Proprietary Names.

In many instances several finishes or materials are identified for a specific item, however, the primary consideration of this solicitation is obtaining the minimum requirements set-forth for construction in this project. Due to the specialized nature of certain components requested and/or required for this project, these specifications, in some instances, refer to various components by trade or manufacturer’s name. Whenever a proprietary (trade) name is used within this Specification Section, it is used to describe a standard of required function, dimension, appearance, fabrication, materials, finish and quality. References to materials by trade name, make, or model number shall not be construed as limiting competition.

2.2 FHL AND PRFTA PHYSICAL SECURITY REQUIREMENTS

2.2 Personnel Security

2.2.1 Access and General Protection/Security Policy and Procedures.

Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplish by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor’s workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

2.2.2 Contractors that Require Access to DOD Facility or Installation.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures. This includes, but not limited to using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulation.

2.3 Physical Security.

The contractor will have a law enforcement background check completed for all employees who will be entering Army-controlled installations or facilities. Additionally, the contractor will provide to the COR, fifteen (15) calendar days in advance of the event, names and Social Security numbers (or equivalent identification numbers for non-U.S. citizens) of all employees who will be entering Army-controlled installations or facilities. Non-U.S. citizens must produce a valid work visa along with said documentation. The contractor will ensure requirement are met for all subsequent employees who will be entering the installation after the initial start date, and they will ensure that a law enforcement background check is completed for all employees on a yearly basis thereafter. Furthermore, the contractor will ensure that its employees entering Army-controlled installations or facilities have obtained access badges and passes in accordance with facility regulations and that these badges and passes are obtain in advance so as not to delay the accomplishment of contracted services. Lastly, the contractor will return all issued U.S. Government Common Access Cards, installation badges, and/or access passes to the Army installation Physical Security Officer when the contract is completed or when a contractor employee no longer requires access to the installation or facility.

2.3.1 Identification Badges.

Identification badges, if required, will be furnish without charge. Application for and use of badges will be as directed by the Contracting Officer. The Contractor shall be responsible to immediately report instances of lost or stolen badges to the Contracting Officer. Upon completion of the contract, the company will return all issued CAC Cards, Installation Badges, and/or access passes to the Contracting Officer and/or Contracting Officer Representative.

2.3.2 OPSEC Training

Per AR 530-1 Operations Security, the contractor employees must complete Level OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter. Contact the installation OPSEC officer at (831) 386-2118/2119 to arrange for OPSEC training. OPSEC Level I training certification can be obtained at https://www.lms.army.mil.

2.3.3 Antiterrorism Training.

All Contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or control access areas shall complete AT Level I awareness training within seven (7) calendar days after contract start date or effective date of incorporation of this requirement into the contract; whichever applies. The Contractor shall submit certificates of completion for each associated contractor employee and subcontractor employee to the COR (or submit to contracting officer, if a COR is not assigned) within 10 calendar days after completion of training by all employees and subcontractor personnel. The COR will assure all Contractors, contractor employees and all associated subcontractors’ employees AT Level I Training is current, all current AT Level I certificates (new and refresher training), are provided to FHL ATO, DPTMS building 290, annually or until said contract expires. This is an annual requirement and can be accomplished by one of two means: under the instruction of a qualified Level 1 AT Awareness Instructor (Level II Trained and Certified ATO), or completion of a DoD-sponsored and certified computer or web-based distance learning instructions. Virtual, AT Level I Training can be coordinated with the FHL Garrison ATO at (831) 386-3816. AT Level I training is available at the following website: https://jkodirect.jten.mil

2.3.4 iWATCH Training.

An ATO (Level II Trained and Certified) will facilitate, face to face in-person iWATCH Training for Contractors and all associated subcontractors’ employees via FHL ATO. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR, iWATCH line (831) 386-3457 or DES Police (831) 386-2526. The COR will track completion of training. The COR will provide a roster of attendees and the ATO will certify attendee roster after completion of training. The Contractor and all associated subcontractors’ shall provide the roster to the COR no more than 10 days after project start and within 10 calendar days for new employees commencing performance. COR will give a copy to the ATO. Individual records will reflect completion of the iWATCH training. The Contractor and all associated subcontractors’ shall encourage personnel to report suspicious activity and/or stolen equipment. iWATCH Training is an annual requirement.

3.0 Construction Requirements

3.1 Contractor Requirements.

The Contractor shall be lawfully licensed in the state of California in all the applicable disciplines required to work on this project. If the contractor will require the usage of Subcontractors to perform specific task involved with this project, said subcontractor must also be lawfully licensed in their applicable disciplines.

The Contractor shall supervise and direct the work, using qualified labor, materials, and proper equipment for all tasks to be performed or provide in accordance with this statement of work. The Contractor shall be responsible and have control over construction means, methods, techniques, sequences, and procedures for coordinating all portions of work. The Contractor and/or Subcontractors shall undergo a full background check resulting in a favorable review by the Parks Reserve Force Training Area and Fort Hunter Liggett Security and Intelligence office prior to entering the garrison.

The contractor shall ensure that each representative requiring access to the installation completes Antiterrorism Level I ‘Awareness’ Training annually and prior to accessing the installation.

The Contractor shall conduct field investigations and it shall be his/her responsibility to visit the project site to verify existing conditions affecting this project. This may be accomplished through field inspections, discussions with appropriate personnel, and by checking previous work and as-built drawings. If field inspections indicate minor discrepancies or missing information between the plans provided and actual site conditions, the Contractor shall contact the Contracting Officer (KO) immediately to report the discrepancies found.

If in the course of the Contractor’s investigations, should he/she discover any errors, inconsistencies, or omissions in information provided by Directorate of Public Works (DPW) that affect the SOW, then the Contractor shall promptly notify the KO.

Safety of the Contractor’s personnel and equipment is the responsibility of the Contractor. Appropriate safety measures shall be adopted to protect all personnel whether or not associated with the project for the duration of the entire construction project. The Contractor shall be responsible for determining what permits are necessary to perform under the contract. Obtaining permits is the contractor’s responsibility and that if such permits are required then Directorate of Public Works shall review and approve permit submittals.

The Contractor shall be responsible for taking corrective action for any notices of violations issued as a result of the Contractors or any subcontractors’ actions or operations during the performance of this contract. Corrections for any such violations shall be at no additional expense to Fort Hunter Liggett and Parks Reserve Force Training Area.

The Contractor shall be responsible for control of pedestrian and vehicular traffic in the work area. The Contractor shall provide flag persons, signs, equipment and other devices necessary to meet Federal, State and local requirements.

The Contractor shall be responsible for providing Fort Hunter Liggett with a finished product in accordance with all applicable US Federal, State of California, and local county regulations & requirements. Additionally, all work shall comply with applicable DoD, Army Reserve IT Manual, Army Technical Guide for Installation Information Infrastructure Architecture, and Army Corp of Engineers (USACE) regulations & requirements. A complete and usable product shall be available upon completion of this project.

The Contractor shall submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements shall govern.

Materials and equipment specified shall be the most up to date design of standard catalogued products of manufacturers regularly engaged in the production of such equipment and material, and shall be installed according to the manufacturer’s recommendations. All equipment and material shall applicably conform to the requirements of American National Standards Institute (ANSI), American Society of Testing and Materials (ASTM), National Electrical Manufacturer’s Association (NEMA), National Fire Protection Association (NFPA) or other national trade association as applicable. Where standards exist, materials and equipment shall bear the label and be listed by Underwriters Laboratories, Inc. (UL) or other Nationally Recognized Testing Laboratory (NRTL) per the NEC. Building codes shall conform to the International Building Code (IBC) and the California Building Codes, Title 24.

3.2 Conformance with Environmental Management Systems.

The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the United States Army, United States Army Reserve, United States Army Garrison, and/or Camp Parks environmental management system (EMS) applicable for the contract.

The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the United States Army, United States Army Reserve, or United States Army Garrison, Parks Reserve Force Training Area EMS.

In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities in following legal and other requirements, and how these requirements affect their work performed under this contract. All on-site contractor personnel shall complete training specified for the type of work conducted on-site and maintain training records.

The Contractor shall provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals.

In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, which is identified during an EMS audit, the nonconformity will be communicated to the Contractor by the EMS Management Representative and a reasonable corrective action will be identified and completed based on the time schedule agreed upon by all applicable parties.

Contractors are liable for any enforcement actions, fines and/or penalties resulting from the failure of the contractor to comply with applicable environmental requirements. (AR 200-1, Sec. 2-2d) Upon inclusion in the contract Statement of Work or contract award, the Contracting Officer's Representative will verify that all appropriate contractor personnel have completed EMS Awareness Training.

3.3 Submittals.

3.3.1 Government Review.

The government review period will be set fourteen (14) calendar day. All reviews will be completed at (or within) the review period. The government shall review the contractor’s submittals for checking for conformance with the qualitative requirements of this project. Review of such submittals are not conducted for the purpose of determining accuracy and completeness of other details such as dimensions and quantities, or for substantiating instructions for installation or performance of equipment or systems, all of which remain the responsibility of the contractor as required by this scope.

3.3.2 Government Approval.

The government’s approval of submittals shall not be construed as being contractual, and shall not relieve the contractor of responsibilities for deviations from the actual contract or from this scope. Any deviations from the actual contract or this scope shall be coordinated with the appropriate agency through the COR.

Substitutions that have a major effect on the design for this project shall be reviewed by the government for conformity with the qualitative requirements of this project.

3.3.4 Referenced Specifications.

Follow submittal procedures shown in specification Section UFGS 01 33 00 SUBMITTAL PROCEDURES.

3.3.5 Project Schedule.

The contractor shall submit a construction project schedule no later than seven (7) calendar days after the delivery order notice to proceed. The contractor shall provide a comprehensive Gantt, or bar, schedule that properly indicates all major milestones, submittals, critical path items and the anticipated completion date for all construction activities. The schedule shall be sufficiently detailed to enable tracking of construction progress and to anticipate critical tasks. Additionally, schedule will meet all requirements specified in UFGS 01 32 01.00 10 Project Schedule.

3.3.6 Project Submittals.

The contractor shall prepare submittals as required by the project specifications, the contract for construction or as requested by the COR. Submittals may include but are not limited to product data, installation and maintenance instructions, shop drawings, calculations, samples and test reports. Submittals shall be presented to the COR for review and approval at least fourteen (14) calendar days prior to purchase or installation. Failure to present submittals to the COR in a timely manner will not justify any claims for a schedule delay of added costs. Once a roofing system ‘Material’ submittal is accepted, it may be considered a ‘Master Submittal’, and it may be used for subsequent delivery orders without resubmitting. The designation of ‘Master Submittal’ is intended for physical material submittals only. However, it is at the discretion on the government whether non-material submittal may or may not be establish as a ‘Master Submittal’.

3.3.7 General Requirements.

The following are the minimum but not limited to general requirements that must be obtained for this project:

Demolition/Removal

· Remove and dispose roofing system (thin gauged metal sheeting) to a total three (3) buildings (301B, 301C, & 301J). This includes, but not limited to: gutters, downspouts and miscellaneous components.

· Remove and disposed exterior wall panels (thin gauged corrugated metal panels covered with polyurethane foam insulation, and all associated hardware) to a total three (3) buildings (301B, 301C, & 301J).

· Remove an estimated fifteen hundred (1,200’) (1,500) sq. /ft. of concrete sidewalk in identified areas. Contractor shall prepare areas for new sidewalk.

· Remove and dispose exterior lighting assemblies (i.e. wall pack, wiring and associated hardware). Each area shall be prepare to receive new commercial grade LED wall packs.

· Remove and disposed interior lighting to the following buildings, 301, 301B, 301C, 301J & 296. Contractor shall prepare each room for new lighting.

· Remove and disposed a total of fifteen (15) sets of exterior metal doors to include frames, hardware and other miscellaneous components (i.e. openers, panic bar, threshold, deadlocks, hinges, etc...). Each opening shall be prepare for new doors.

· Remove and disposed windows to include metal frames. Each opening shall be prepare for new window.

· Remove and dispose all drop down ceiling tiles to include suspension system to the following buildings 301, 301B, 301C, & 301J.

· Remove and disposed electrical outlets, GFI outlets, switches, dimmers and data that are no longer working or not in compliant with National Electric Code.

· Remove and disposed flooring to the following buildings: 301, 301B, 301C, & 301J.Removal includes, but not limited to: carpet and pad, Vinyl Composition Tile (VCT) and linoleum. Additionally, base boards, mastic and other miscellaneous components shall be included in the removal.

· A total of eight (8) ten (10) restroom consist of men and women shall be upgraded with new fixtures and minor repairs. Demolition includes, but not limited to: toilets, sinks, paper towel and soap dispenser, flooring, base board, electrical outlets, lighting, doors and miscellaneous plumbing components (i.e. wax ring, angle-stop, valves, floor flange, facets, inlet supply lines bolts, caps seats and covers).

· Remove and dispose four (4) 5’x 10’ (15-20 ton) inactive AC units located a building 301; these system are no longer in use. This includes but not limited to condenser unit, coils, fan, compressor, electrical (i.e. conduits, shut off switch and boxes), refrigerant and miscellaneous components.

· Remove and dispose exterior metal cover on the south side of building 301. This includes, but not limited to, roof, frame, doors, lights, and other miscellaneous items accosted with the metal cover. Contractor shall prepare the area for painting.

· Remove and dispose two (2) 4’x 5’ 2’-6” x 2’6” (30” x 30”) exterior louvers. Contractor shall prepare opening for new louvers.

· Remove and dispose thirty (30) ceiling diffusers and twenty four (24) ceiling returns. Contractor shall prepare openings for new ceiling diffusers and returns.

Sidewalk Repair

· The Contractor shall remove and disposed existing concrete sidewalk in varies location. The contractor shall saw-cut in sections specified areas that been identified by the COR. Map of the location shall be provided by the COR.

· Contractor shall remove 6” sub-base material and add 6” compacted aggregate base course material.

· Contractor shall, moisten, and compact the existing subgrade to 90% of maximum dry density per ASTMD 698.

· Contractor shall place new concrete with minimum thickness of four (4”). Each new concrete section shall have expansion and contraction joints. Contractor shall refer to the Caltrans Standard Specification (2018) 73 Concrete Curb and Sidewalks for additional requirements.

Building Envelope Upgrades (301B, 301C & 301J)

· The contractor shall furnish and install Polyisocyanurate Insulated Prefabricated 4 inches (or R-30 equivalent) standing seam metal roof panels, minimum thickness of interior and exterior sheet metal shall be 24 gauge. Buildings include 301B, 301C, & 301J. Contractor shall verify Unified Facilities Criteria (UFC) DoD Minimum Antiterrorism Standards for Buildings 4-010-01 February 2012 (Change 1, October 2013) to ensure the materials meet the UFC requirements. The system shall be complete and usable which shall include the installation of all auxiliary components (i.e. fasteners, butyl tape, butyl sealants, molding closure strips, gutters, downspout, trim, ridge caps, equipment curbs, and other similar sheet metal accessories) necessary to achieve a weather-tight seal on the entire system. The color samples for the roof panel shall be Colonial Red or equivalent.

· The contractor shall provide a Polyisocyanurate Insulated prefabricated 2.5 inches wall panel system, minimum thickness of interior and exterior sheet metal shall be 24 gauge. Buildings include 301B, 301C, & 301J. The system shall be complete and usable which shall include the installation of all auxiliary components (i.e. fasteners, closure strips, sealants, and sheet metal flashing) necessary to achieve a weather-tight seal on the entire system. The contractor shall provide color samples for wall panels.

Openings

· The contractor shall furnish and install (9) eleven (11) fire rated standard steel single door with frame assembly; one (1) two (2) standard steel double doors with farm frame assembly; one (1) double door louver with frame assembly; one (1) glass Storefront with frame assembly and full lite;. Buildings included 301, 301B, 301C, 301J and 296. Hardware and all auxiliary components shall be included in order to achieve a complete and usable system. This includes but not limited to interchangeable ADA door handle, deadbolt set/deadbolt privacy lock with outside keyed Core for Access, interchangeable door handle (ADA) push plate, door closer, door stops, kick plate, threshold, weather stripping, panic bars, glass lite. Contractor shall be aware each main entrance door shall receive glass lite. Contractor shall provide color samples and submittals for approval.

· The contractor shall furnish and install an estimated seventeen (15) (17) exterior Thermally Improved Window Assemblies and two interior sliding windows for the office. Buildings include 301B, 301C, and 301J. Frames shall be a Bronze Finish. Glazing shall be double pane glass separated airspace filled with krypton gas, low solar heart gain, and low-E glass. Item includes all auxiliary components required to achieve a complete and usable system (i.e. sills, sashes, spacers, weather-stripping, backer rods, fasteners, adhesives, etc.) Item also includes the delivery of material to the project site location. The contractor shall be responsible for verifying measurement, quantiles and type of window required. In addition, Contractor shall refer to the UFC 4-010-01 12 December 2018 (Change1, 19 August 2020) Standard 10, to ensure the new windows assembly meets DoD Minimum Antiterrorism Standards for Buildings.

Exterior & Interior Painting

· For exterior painting Contractor shall cover/protect windows, doors and surrounding grounds (shrubs, bushes, trees, and other miscellaneous vegetation) from debris, water and paint generated from the project.

· Pressure wash exterior wall surface to building 301 and 296. Surface areas impacted during pressure wash are made of stucco, wood trim and metal. Equipment use for pressure wash shall not exceed twenty five hundred (2500) lb. operation pressure.

· Exterior buildings shall be free of loose foreign matter such as mold, mildew, dirt, paint and corrosion.

· Contractor(s) shall prime and paint exterior and interior surface for building 301, 301B, 301C, 301J and 296. Contractor shall ensure that primer, sealers and undercoats are suitable for the substrate and compatible with the finish coat and each other.

· For exterior and interior walls, contractor shall use appropriate methods for patch, fill and retexture for areas that have cracks, holes and gouges. Any expose or repaired areas shall be prime prior to painting.

· Contractor shall provide color samples to DPW and COR for approval. Contractor shall ensure color choices comply with Fort Hunter Liggett Installation Design Guide.

· Contractor(s) shall apply one (1) coat of primmer to areas that have been worn, repaired or replace with new material. This includes, but not limited to, interior and exterior wall and ceiling, doors, frames gutters, down spouts railings.

· Contractor(s) shall paint two (2) coats of pre-selected color of new elastomeric paint for each listed buildings. Contractor shall determine the best method of paint application and ensuring evenness throughout the building exterior and interior. Areas to be included, but not limited to, walls and ceilings, doors (interior and exterior), frames gutters, trim, down spouts railings.

· Contractor shall place “Wet Paint Warning” signs to all areas that paint was applied.

Flooring Replacement

· Furnish and install new 12x12 resilient Vinyl Composition Tile (VCT) commercial grade throughout buildings 301, 301B, 301C and 301J. Areas of installation includes: offices, class rooms, corridors, hallways and storage closets. Prior to installation, the contractor shall provide floor sample with color choices to the COR for approval.

· Building 301 existing floor shall stay in-place except where there is carpet. Carpets in offices shall be replace with the same existing flooring as in the halls and class rooms. In addition, the contractor shall inspect the existing floors for damages and make necessary repairs.

· Contractor shall prepare all sub-floor prior to flooring installation. This includes but, not limit, replacing damage wood, patching holes, self-leveling and concrete seal.

· Furnish and install 6” rubber cove base throughout each room. This includes, but not limited to: offices, class rooms, corridors, hallways restrooms and storage closets.

· The Contractor shall replace broken and missing floor tile to the raise floor in building 301. Contractor shall match the floor tile to existing. If for some reason the Contractor is not able to match existing tile, then the COR shall be notified of findings. Contractor shall provide submittals for review and approval.

· Furnish and install new seamless sheet linoleum flooring with 6” rubber cove base to eight (8) existing bathrooms. Prior to installation, the contractor shall provide floor sample with color choices to the COR for approval.

Replace Ceiling Tiles & Suspension System

· The contractor shall furnish and install ceiling suspension system (fire rated, 15/16”T bar, 25% recycled steel, 2' x 4' grid (Suspended acoustic ceiling tiles (2’x 2’ visual tile pattern), mineral fiber, 75% recycled content, ¾” thick, seismic straps, and seismic bracing) for buildings 301, 301B 301C, & 301J. Contractor shall submit grid layout and submittals prior to installation.

Exterior Building Penetrations.

· Identify, uninstall and store any exterior building penetrations (telecommunications, antennas, vents, water spigots, exterior ducting and other miscellaneous items) where building envelope upgrades will occur. The contractor shall re-install all exterior building penetrations (telecommunications, antennas, vents, electrical conduits, etc.) to its original location.

Restroom Upgrades (301, 301B, 301C & 296)

· Contractor shall upgrade eight (8) ten (10) existing restrooms located in the following buildings: 301, 301B, 301C, 301J & 296. Work shall include, but not limited to, interior and exterior painting, flooring replacement, light replacement and bathroom fixtures.

· Furnish and install toilets, sinks with counter top solid surface with integrated solid surface sink bowl, facets, soap and sanitizer dispensers, and grab bar, bathroom tissue dispenser towel dispenser (fold/multi F fold paper). Additionally, contractor shall furnish and install new bathroom metal partition stalls to each bathrooms with privacy locks. Bathroom accessories shall meet ADA/ABA requirements.

· Minor upgrades to electrical such as new cover plates, light switches, electrical outlets and GFCI outlets Contractor shall verify electrical panel to ensure existing breakers are sufficient for outlets and switches.

· Additional replacement shall include, wax ring; angle-stop, valves (i.e. emergency shut off valves); floor flange; stainless braid inlet supply connectors (water supply line); bolts with caps, seat covers and other miscellaneous axillary components.

· Contractor shall remove and dispose existing tile floor in building 301and prepare the floor for new linoleum flooring.

· Furnish and install new seamless sheet linoleum flooring with 6” rubber cove base to six (6) eight (8) existing bathrooms. Prior to installation, the contractor shall provide floor sample with color choices to the COR for approval.

· Contractor shall remove and dispose tile wall in both restrooms in building 301. Contractor shall prepare the wall for new FRP. Prior to installation, the contractor shall provide submittals for review and approval.

HVAC

· The contractor shall furnish and install new 24” x 24” drop ceiling diffuser and air vent register with perforated face to the following buildings: 301, 301B 301C, & 301J. Contractor shall be responsible for quantity. Submittal shall be provided for approval.

Electrical

· All electrical outlets and switches shall be check and verified by the contractor ensure the outlets are in good working condition (i.e. electrical outlets, GFCI, switches and dimmers). Areas include, but not limited to, class rooms, offices, hallways, restrooms. If outlets are not working, the contractor shall furnish and install new 120V 20A electrical outlets and switches in identified areas. Contractor shall replace existing cover plates (i.e. electrical outlets, switches, dimmers) with new color coordinated plates. All electrical shall adhere the most current National Electric Code.

· Contractor shall verify if the current electrical panel can support newly electrical upgrades in the following areas; offices, conference rooms, class rooms and new lighting. If the existing panel cannot support the new up upgrades then the contractor shall make the necessary upgrades to the existing panel. This includes but not limited to: conduit, conductors, breakers, fuses and all necessary auxiliary components. Installation of these components shall meet all requirements specified in National Electric Code and NFPA 70.

· Furnish and install new energy efficient photocell sensor controlled 150W LED, clear lens wall pack assemblies. Contractor shall provide submittals for review prior to install. Contractor shall be responsible for quantities needed for each buildings (301, 301B, 301C, 301J and 296).

· Furnish and install an estimated one hundred and twenty nine (129) new LED lighting with a minimum 50 foot-candles throughout each listed buildings (301, 301B, 301C, 301J and 296). The contractor shall refer to the Army Reserve Lighting Level. Areas of replacements includes, offices, classrooms, storage, restrooms, hallways, corridors, and entryways. Light fixture shall be grid mounted T5 indirect fixtures. The contractor shall design and submit a reflected ceiling plan (RCP) for review and approval. Additionally, the contractor shall inspect existing switches and dimmers to ensure compatibility for new lighting. If the contractors identified switches and dimers not to be combatable, contractor shall replace with new. All new electrical work shall be in accordance with National Electric Code and the UFC standards. The Contractor responsible for field check, measurements and quantities prior to furnish and install.

· Contractor shall furnish and install minimum required exit and emergency lighting to the following buildings 301, 301B, 301C and 30J. Exit lighting shall be a combination exist (light and sign) with 90 minute batter back up. Contractor shall provide submittals for review prior to installation to include egress plan for each building.

Telecommunication Upgrades

· Contractor shall upgrade existing data/voice outlets with new color coordinated cover plates. The following areas include, but not limited to, class rooms, offices, and conference rooms. Contractor shall consult with Network Enterprise Center (NEC) for requirement for installation materials and equipment for data connection.

END OF STATEMENT OF WORK