W911SA21B2007 Amendment 0001.docx
DOCX document 46 KB Posted
- Solicitation number
- W911SA21B2007
About this file
This document provides an amended statement of work and questions and answers for a federal solicitation seeking interior and exterior renovation services at various buildings on Fort Hunter Liggett in California. The renovation work includes items such as replacing flooring, fixtures, doors, windows, and exterior wall panels as well as painting, concrete work, and bathroom upgrades. The period of performance is until September 2022. The estimated value of the contract is between $1 million to $5 million. The solicitation will utilize full and open competition procedures and be awarded as a firm fixed-price contract to the responsible bidder providing the lowest price. The bid due date is in mid-August 2021 with an anticipated award in July 2021. The North American Industry Classification System code for this requirement is 236220 for commercial and institutional building construction with a small business size standard of $39.5 million.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911SA21B2007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 08-Jul-2021 10:30 AM to 12-Aug-2021 10:30 AM.
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been added by full text:
QUESTIONS AND ANSWERS
Reference the SOW line item number 216: States "fifteen hundred (1200) sq ft" of sidewalk……”. Should the (1200) be revised to read (1500)? Please clarify. Answer: Yes, this should read (1,500) and will be revise in the SOW.
Reference the SOW line item number 247 thru 249: States “ The contractor shall remove and disposed existing concrete sidewalk in various locations. The contractor shall saw-cut in sections specified areas that been identified by the COR. Map of the location shall be provided by the COR” Please provide the map of the various locations as it was not provided with the RFP bid documents. Answer: see Attachment 11 Reference the SOW line item number 285: States “ The contractor shall furnish and install an estimated seventeen (15) exterior Thermally Improved Window Assemblies…….” Should the (15) be revised to read (17)? Please clarify. Answer: Yes, the quantity shall be change in the SOW to read (17). However, the Contractor is still responsible for their own measurements and quantities.
Are there any known hazardous materials? Answer: Yes, testing was done for Asbestos. A report will be provide for building 301, See attachment 12. Buildings. 301B none found & 301C none found & 301J no report available. LBP: There is limited test results available for buildings. We do not track LBP. Demo/Reno projects are expected to survey as part of the contract.
Is there a Lead/Asbestos survey report? If so, may the contractors get a copy? Answer: see previously answered question.
If a Lead/Asbestos survey is not available, should the contractor figure a lead/asbestos survey in their proposal? Answer: see previously answered question.
Will the Site Superintendent be allowed to act as the Quality Control Manager (QCM) and Site Safety Health Officer (SSHO); one person wearing all three hats (triple hat)? Or, will a separate QCM and or SSHO be required? Answer: Per FAR 52.236-6, an On Site Superintendent is required. As long as that requirement is met, the rest is a business decision to be made by your firm, in accordance with the rules that require a QCM and SSHO.
Will all of the buildings be vacant and unoccupied during the entire construction period? Answer: Yes the buildings will be vacant during construction. Are there any phasing requirements? Answer: No. Will one building need to be completed prior to moving on to the next building? Answer: No.
Are there any available blueprints/as-builts for buildings 296, 301B, 301C and 301J? If so, please provide. Answer: There are no true blueprints/ as-built for the listed buildings (301B, 301C, and 301J) what is available is the interior floor layout with room dimensions. There are no blueprints/ as-built for building 296 restroom.
Reference the SOW line item number 243: States to “Remove and dispose two (2) 4' x 5' exterior louvers. Contractor shall prepare opening for new louvers”. Currently on the west side exterior wall of Bldg. 301 there are two (2) 25” x 25” louvers. Are these the two louvers being replaced? If so, are the new louvers 4' x 5'? Or, 25" x 25"? Answer: 2’6”x2’6” (30”x30”) are the two louver vents to be replace.
Reference the SOW line item number 347 thru 349: States, “Furnish and install toilets, sinks with counter top, faucets, soap and sanitizer dispensers, and grab bar, bathroom tissue dispenser (fold/multi F fold paper). Additionally, contractor shall furnish and install new bathroom stalls to each bathrooms with privacy locks”. Will the new fixtures, bathroom accessories, and partitions need to be ADA/ABA compliant? Please advise. Answer: Yes, the fixtures, bathroom accessories and partition will need to be ADA/ABA.
Can the GOV. please provide an updated SOW that breaks down the concrete work to be performed for each building. The current SOW does not clearly define what each building requires. Answer: There are serval areas of the sidewalk that need to be replace. There is no specific building that needs concrete work. There will be a map provided of the location. See Attachment 11.
Will all buildings be available at the same time? If not please define the desired phasing. Answer: Yes the buildings will be available at the same time, no phasing needed.
Please provide pictures of all buildings since we were unable to take pics of 301B 301C, 301J. Answer: Government personnel will not provide pictures, see the specification and drawings Will any architectural, engineering, mechanical plans or shop drawings be necessary for the awarded contractor to provide? Answer: Yes.
Will the buildings be clear of all furniture and equipment, or will the contractor be responsible for moving? Answer: Yes, building will be clear of furniture and equipment.
Will the raised access floor in 301 be part of the SOW? Answer: Yes the raised floor will be part of the SOW to replace missing floor panels.
Since the buildings were occupied and hard to see all wall conditions, can you please provide an estimated % we should account for wall penetrations and patching that should be accounted for? Answer: There are no major damage to the exiting walls. Minor repairs will only be needed.
Can the Gov. Please provide the manufacturer of the wall panels being installed on other locations next to headquarters? Answer: Kingspan and MBCI were the two manufactures used in pervious projects.
Will the bathrooms require new FRP for walls? If so please specify height and which walls? Answer: Yes, the bathrooms will required FRP walls. Estimated 4’ft up the wall.
What type of restroom stall will be required? Metal, stainless steel, HDPE Phenolic? Please specify. Answer: Metal for all bathrooms. Contractor is still responsible to submit submittals for review.
Please specify what type of bathroom sink and countertop will be required? Example, solid surface corian and top mount porcelain sink or Solid surface with integrated solid surface sink bowl. Answer: Solid Surface w/integrated solid surface sink bowl. Contractor is still responsible to submit submittals for review.
Please provide quantity and location of restroom requirements for each building. We were not allowed to take pics during site walk and some restrooms were not available to look at due to military personnel occupying room. Answer: the Statement of work provides estimated quantity and location of the restrooms.
Please provide quantities of lights and any other electrical/date required to help bidding purposes. Answer: There is an estimated 129 lights in varies size and locations. However, the Contractor is still responsible for their own measurements and quantities.
What are the requirements for site management? Will this be a tri hat, dual hat, or single hat role project? Answer: Per FAR 52.236-6, an On Site Superintendent is required. As long as that requirement is met, the rest is a business decision to be made by your firm, in accordance with the rules that require a QCM and SSHO.
Will we be able to have a laydown yard in adjacent parking lot by 301? Answer: Yes, the adjacent parking can be available for Laydown yard.
What are the requirements for SSHO/QC/Superintendent? Is triple hatter accepted for SSHO/QC/Superintendent for this project? Answer: Per FAR 52.236-6, an On Site Superintendent is required. As long as that requirement is met, the rest is a business decision to be made by your firm, in accordance with the rules that require a QCM and SSHO.
What is the anticipated award date? Answer: This is not known at this time, the time for acceptance is stated on the solicitation in Block 13.
Does any of these building occupied during the course of construction? Answer: No the buildings will be vacant during construction.
Are these buildings tested for lead and asbestos? Provide asbestos and lead reports for 301, 301B, 301C, 301J and 296? Answer: see previously answered question.
Does the contractor need to provide temporary toilets for government operations during the course of constructions? If yes please provide the number of woman and men in each building? Answer: No, the buildings will be vacant during construction. However, temporary toilets maybe needed for contractor’s personnel.
Please provide the contact information for vendors servicing fire alarm system? Answer: This will be provided to the awardee if necessary.
Please provide the contact information for vendors servicing the telecommunication and network system? Answer: This will be provided to the awardee if necessary.
Are we replacing Exit or Emergency signs? Or adding any? Answer: Yes, Exit and emergency signs are to be replace Upon demo of old light fixture, do we need to save anything from them? Answer: Answer: No, however, the light bulbs are consider hazardous and will need to be dispose of properly.
Provide minimum foot candles required for LED lighting per location? Answer: 50 foot-candles. However the contractor shall refer to Army Reserve Lighting Level which will be provided to the awardee.
Per the scope of work all floors need to be replaced with new 12x12 resilient vinyl composite tile (VCT) commercial grade throughout buildings 301, 301B, 301C, 301J. But in building 301 room DEC 10 (computer room) has raised flooring. Please confirm the scope of work for this area? Answer: buildings 301B, 301C, & 301J shall receive 12x12 VCT flooring throughout. Restroom in buildings 301, 301B, 301C, 301J shall receive linoleum flooring. Building 301 existing floor shall stay in-place except where there is carpet. Carpets in offices shall be replace with the same existing flooring as in the halls and class rooms. The Raise shall remain. Missing and broken floor panels shall replace in kind.
Please provide any specifications or make or model available for the following items: ceiling tiles, ceiling grid, VCT, light fixtures, registers, windows and doors? Answer: The Contractor will need to provide submittals to the Government for approval for ceiling tiles, ceiling grid, VCT, light fixtures, registers, windows and door. These buildings were built in the 70’s and 80’s information for the listed items are not available.
In building 301 there is an existing fire alarm system, do we remove and re-install? Answer: No.
Are there any sensors above the ceiling? Answer: Its undetermined if sensors are located above the ceiling. It’s the contractor’s responsibility to verify.
Per the scope of work there are 8 existing restrooms in which only 6 receives new seamless sheet linoleum flooring, please confirm the 2 restrooms in building 296 do not receive new flooring? Answer: No building 296 restroom floors will stay the same. The contractor shall clean the floors.
In buildings 301B, 301C and 301J we noticed that there are ceiling mounted receptacles installed to the ceiling tiles, are we re-installing them back on the new ceiling? Answer: Yes. Receptacles shall be receptacles. Contractor shall ensure the receptacles are in good working order and replace the covers.
Will the government remove all the furniture and equipment prior to start of the project? Answer: Yes, building will be clear of furniture and equipment.
Do we need to provide storage containers for the government to store the existing furniture? Answer: No, Government will be responsible for storage.
Building 301, tape facility room there is an existing partition wall 3’ lower than the ceiling and covered with a piece of plywood. Do we need to frame the wall to fill the gap? Answer: Yes, Contractor shall frame the wall to fill the gap.
Per the scope of work contractor to remove selected windows, do we need to remove and replace window blinds? Answer: No, blinds are not required.
Our bonding company is requesting the amount of liquidated damages incurred if project isn’t completed on time. Please advise.Answer: Liquidated Damages DO NOT apply to this project.
Reference the SOW line item number 222: States, “Remove and disposed exterior metal doors…………”. Line item 276 states, “furnish and install (9) fire rated standard steel single doors…….” If the exterior doors located at Bldg. 296 are to be replaced then the quantity should read 10. If the door at Bldg. 296 are to remain, then the quantity is 8. Please confirm that the replacement of doors is limited only to the exterior doors and confirm quantity. Answer: Building 301 has two (2) double solid doors, one (1) double louver door, one (1) glass store front door and (1) single door. Building 301B has three (3) single door; 301C has three (3) single doors; building 301J has two (2) single doors and building 276 has two (2) set of sold double doors. Total of exterior doors to be replace is fifteen (15) sets of doors. Statement of work will be adjusted. However, the Contractor is still responsible for their own measurements and quantities.
Reference the SOW line item number 325-328: Indicates to provide 12”x12” resilient Vinyl Composition Tile (VCT) throughout Bldg’s 301, 301B, 301C, and 301J. Line item 358-360 indicates to provide seamless sheet linoleum in six (6) existing bathrooms located in these same buildings.. Please clarify. Answer: buildings 301B, 301C, & 301J shall receive 12x12 VCT flooring throughout. Restroom in buildings 301, 301B, 301C, 301J shall receive linoleum flooring. Building 301 existing floor shall stay in-place except where there is carpet. Carpets in offices shall be replace with the same existing flooring as in the halls and class rooms. The Raise shall remain. Missing and broken floor panels shall replace in kind.
Reference the SOW line item number 304-306: indicates to paint the exterior surfaces of Bldg.’s 301, 301B, 301C, and 301J. Line items 270-274 indicates to provide new exterior wall panels on Bldg.’s 301B, 301C, and 301J. Is the intent to paint the new exterior wall panels? Or, is it MICC’s desire to have pre-finished wall panels directly from the manufacturer? Answer: the intent is to paint the exterior of building 301 and 296 to include doors. The exterior wall panels for 301B, 301C, 301J will be pre-finish. Buildings 301, 301B, 301C, 301J & 296 shall have the interior walls and doors painted.
Reference the SOW line item number 237-239: indicates to remove (4) inactive AC units and associated components. Please provide points of disconnection. Answer: Just the exterior connection near the units. The building recently received new HVAC system.
Due to the upcoming Federal holiday (July 4th), is it possible to get the proposal due date extended? Answer: This holiday was accounted for in the planning of the requirement. An Extension will not be granted further for this reason.
Is abatement required of any kind as part of this project on any of the five buildings covered by the SOW? Answer: This question has been answered numerous times already, see previous answers.
Is hazardous survey available for the areas to be disturbed for this renovation work? Answer: There is limited test results available for these buildings. However if there any survey reports available it will be provided.
We assume if a hazardous survey is not available, we are then to include costs to perform a hazardous survey? Any abatement confirmed to be required would then be issued as a mod to the contract, please confirm. Answer: Yes.
SOW, Restroom upgades, line #358 references for seamless sheet linoleum flooring. Is the intent to install over the existing tile at Bldg#301, or to remove existing floor tile. Answer: The intent is to remove existing flooring and replace with linoleum.
SOW, Restroom upgades, line #358 references for seamless sheet linoleum flooring. Is the intent for the existing wall tile at Bldg#301 to remain or to be removed and replaced with new tile or different wall covering/finish. Please clarify. Answer: The intent is to remove existing wall tile and replace with different wall covering/finish FRP.
We noticed a fire alarm panel & system in building #301. Please clarify the limits of scope with this system. Answer: Fire Alarm Panel and system is not included in scope of work.
Is there a new fire alarm system required in any of the other buildings #301B, #301C, & #301J? Answer: No, just new smoke detectors.
Where is the site concrete removal and replacement locations per DOR? Answer: see attachment 11.
Is the concrete removal and replacement 1,200 sf or 1,500 sf? Answer: 1,500. Statement of work will be corrected. However, the Contractor is still responsible for their own measurements and quantities.
Please identify the location of the 9 FR single doors, 2 double doors, and 1 storefront assembly. These numbers don’t match up to the existing opening counts. Answer: Building 301 has two (2) double solid doors, one (1) double louver door, one (1) glass store front door and (1) single door. Building 301B has three (3) single door; 301C has three (3) single doors; building 301J has two (2) single doors and building 276 has two (2) set of sold double doors. Total of exterior doors to be replace is fifteen (15) sets of doors. Statement of work will be adjusted. However, the Contractor is still responsible for their own measurements and quantities.
Is the intent to paint the factory finish of the new IMP’s at buildings 301B, 301C, and 301J, or only paint exterior doors and the exterior of building 301? Answer: the intent is to paint the exterior of building 301 and 296 to include doors. The exterior wall panels for 301B, 301C, 301J will be pre-finish. Buildings 301, 301B, 301C, 301J & 296 shall have the interior walls and doors painted.
We assume exterior painting at 296 is not part of this contract. Please advise. Answer: Exterior painting for building 296 is part of the project. Statement of Work shall indicate exterior painting for building 296.
Are we to assume that all toilet flanges are damaged and will need to be saw cut out, replaced and new concrete poured back? Answer: Yes. It is unknown of the current condition.
Contractor was unable to inspect Building 301 due to it being locked. Please provide interior photographs of this building. Answer: Government does not provide pictures
Contractors were not allowed to take photographs. Please provide interior and exterior photos of all buildings. Answer: Government does not provide pictures Regarding Buildings 301B, 301C, and 301J, there were ivory colored hand labeled “LAN” outlets that did not appear to be in use. What is the governments intent for these outlets, i.e., abandon, replace, blank-off, etc.? Answer: The Contractor shall work with the local NEC to determine if the LAN are active or will be abandon.
Statement of Work, Page 10, Line 247 states a map of the locations of sidewalk repairs will be provided by the COR. Please provide “Map of Location” of required site concrete work. Answer: Map will be provide, see attachment 11
Statement of Work, Page 9, Line 216 states “Remove an estimated fifteen hundred (1,200’) sq./ft. of concrete sidewalk in identified areas. Please clarify if contractor is removing fifteen hundred or 1200 sq. ft. Answer: Yes, this should read (1,500) and will be revise in the SOW. However, the Contractor is still responsible for their own measurements and quantities.
Statement of Work, Page 11, Line 277 states to furnish and install (9) fire rated standard steel single door with frame assembly; one (1) standard steel double doors with farm assembly. Please clarify the term “farm” assembly. Answer: Typo “frame assembly”
Statement of Work, Page 11, Line 276 states the number and type of doors to be replaced but is silent on the locations of the doors to be replaced. Please provide exact locations of the doors to be replaces since the building uses and/or type of construction of the buildings will require different levels of effort. Answer: Building 301 has two (2) double solid doors, one (1) double louver door, one (1) glass store front door and (1) single door. Building 301B has three (3) single door; 301C has three (3) single doors; building 301J has two (2) single doors and building 276 has two (2) set of sold double doors. Total of exterior doors to be replace is fifteen (15) sets of doors. Statement of work will be adjusted. However, the Contractor is still responsible for their own measurements and quantities.
Statement of Work, Page 11, Line 258 states the contractor shall furnish and install and estimated seventeen (15) exterior Thermally Improved Window Assemblies and two interior sliding windows for the office.
· Please clarify the number of exterior windows to be installed, seventeen or (15).
· Plans only show one (1) interior window. Please provide location of interior windows to be installed.
Answer: buildings 301B has six (6) exterior windows; 301C has six (6) exterior windows and 301J has five (5) exterior windows. Buildings 276 and 301 does not have window. Total windows to be replace Seventeen (17). Statement of work will revise.
Statement of Work, Page 11, Line 290 states contractor is to verify type of windows. Can the same style “horizontal slider” be used providing it complies with the ATFP requirements stated in the Statement of Work? Answer: Yes.
Building Envelope Upgrades – The existing exterior roof panels cantilever beyond the exterior wall leaving a gap between the existing gutter and wall. Can the contractor provide an assembly with the gutter tight against the exterior walls? Answer: Yes, Contractor will need to provide drawing prior to install for review and approval.
Building Envelope Upgrades – The contractor did not have access to the roofs at the time of the site visit. Please provide photos of the roofs for buildings 301, 301B, 301C, and 301J. Answer: Government does not provide pictures
Will the contractor be required to provide roof vents for the new roofs? If so, please provide the government’s requirements. Answer: Yes, new roof vents are required. Contractor shall provide a design of the roof and wall panels to be replace for each metal building. The design shall include the quantity of vents, the location and size.
Please confirm the new exterior metal finishes are to be pre-finished and not painted. Answer: Exterior metal shall be pre-finished.
Statement of work, Page 12, Line 318 stated contractor(s) shall paint two (2) coats of pre-selected color of new elastomeric paint for each listed buildings. Contractor shall determine the best method of paint application and ensuring evenness throughout the building exterior and interior. Areas to be included, but not limited to, walls and ceilings, doors (interior and exterior), frames gutters, trims down spouts railings. Elastomeric paint is generally used as an exterior paint due to its flexibility for expansion and contraction and sometimes requires UV light to cure. Can the contractor apply Elastomeric paint to the required exterior surfaces and apply 2 coats of interior acrylic paint to the required interior surfaces? Answer: Yes, as long as submittals are provided to the Government for review and approval.
Flooring – Flooring manufactures generally require a moisture test to verify moisture content in concrete slabs in order to provide a warranty for their product. In the event the moisture in the existing slabs exceed maximum allowance per manufacture’s standards, sealing the concrete will be required. Does the government want to the contractor to include the sealing of the slabs in the bid as a fail-safe or treat concrete sealing as a change order if needed? Answer: Include the sealing price in the bid.
Flooring – Flooring manufactures require a minimum tolerance in concrete flatness to warrant VCT flooring. In the event that the existing slab do not meet this tolerance the slabs will have to have floor prep to level. Does the government want to the contractor to include the leveling of the slabs in the bid as a fail-safe or treat concrete leveling as a change order if needed? Answer: Include the leveling price in the bid.
The existing windows currently have mini-blinds. Does the government want the contractor to provide new window blinds or only dispose of the existing blinds? Answer: Contractor shall dispose existing blinds. Contractor is not required to provide new blinds.
What is the brand name of the current fire alarm system? Answer: The fire alarm system is not part of the scope of work.
Is the existing fire alarm system currently monitored and functioning? Answer: The fire alarm system is not part of the scope of work.
What is the brand name of the existing evacuation systems? Answer: The existing evacuation system is not part of the scope of work.
Is the existing evacuation system functioning? Answer: The evacuation system is not part of the scope of work.
As-builts indicate an electro-mechanical man gate with an intercom connection. Are these systems currently functioning? Answer: Electro-mechanical man gate w/intercom is not part of the scope of work.
Network Enterprise Center is based in Fort Hood. Is there a contact that could offer communications specifications and requirements? Answer: Yes, Fort Hunter Liggett also has a Network Enterprise Center (NEC). This will be provided to the awardee.
Will the new lighting and controls be required to meet current State of California Title 24 requirements/? Answer: Yes.
The SOW requires that all electrical and communication entering from the outside of the building shall be removed for new metal installations. Will all Affected electrical systems be tested and documented that they are operational? Answer: The Contractor shall ensure that all electrical and communication system are in operation before and after completion of work.
As-built plans indicate a raised steel floor. Will the existing grounding system be adequate? Answer: Broken and missing panels of the existing raised floor shall be replace utilizing the existing frame.
Will the contractor have access to the entire site during construction? Answer: Yes.
Will the buildings be occupied during construction? Answer: No, all buildings will be vacant during construction.
Contractor is responsible for their own measurements and quantities.
In reference to Asbestos:
Asbestos per 1991 surveys:
301 – yes, multiple occurrences, see report 301B – none found 301C – none found 301J – no report available
LBP: Limited test results available for buildings. We do not track LBP. Demo/Reno projects are expected to survey as part of the contract.
The following have been modified:
SUPPLEMENTAL INFORMATION
Contract Specialist:
Michelle Harvey Phone: 608-388-1250 E-mail: michelle.m.harvey3.civ@mail.mil
Contracting Officer:
Steve Bailey Phone: 608-388-6077 Email: steven.m.bailey2.civ@mail.mil
In response to the COVID-19 pandemic and the President’s declaration of a National Emergency concerning COVID-19 on 13 March 2020, MICC Ft McCoy is following the recommended safety guidelines imposed by the World Health Organization (WHO) and the Centers for Disease Control and Prevention (CDC) to mitigate the spread of COVID-19, therefore, the procedures for bid submission and public bid openings are hereby changed as detailed in the following paragraphs.
Please note: The time the Bid is due is different from the time of the Public Bid Opening. This will allow time for bids to be downloaded from DoD SAFE in order to be read aloud during the Public Bid Opening teleconference. Late Bids received after the Bid Due date/time will not be considered for award; even if they are received before the Public Bid Opening. Screen Shots of the SAFE submission will be taken to confirm each contractor bid was received by the bid due date/time.
Bid Due Date: 12 August 2021 Bid Due Time: 10:30 AM CDT Bid Opening Time: 1:30 PM CDT
DUNS ________________________________________
TAXPAYER ID # _______________________________
CAGE CODE__________________________________
CONTRACT MAGNITUDE: The magnitude of this contract is between $1,000,000 and $5,000,000.
This will be a single award, firm fixed priced contract.
Any questions concerns, verification or clarification of information of the documents included in the solicitation package shall be submitted in writing and submitted to the Contract Specialist identified herein no later than 11:00 AM, local time CST on 23 June 2021. Include in the subject line of the email the Government’s solicitation number; failure to do so will lessen the Government’s ability to ensure all questions are considered during the bidding process. Provide your company name, POC and contact information in the body of the email.
SITE VISIT: In response to the COVID-19 pandemic and the President’s declaration of a National Emergency concerning COVID-19 on 13 March 2020, MICC Ft McCoy is following the recommended safety guidelines imposed by the World Health Organization (WHO) and the Centers for Disease Control and Prevention (CDC) to mitigate the spread of COVID-19, therefore, the procedures for Site Visits are hereby changed as detailed in the following paragraphs.
1. RSVP for site visit are required 48 hours before the site visit, if the site visit is on Tuesday, all site visit RSVPs are due on the preceding Friday– Please email the Contract Specialist if your company will be attending and how many people from your firm will be attending. – please include the solicitation number in the subject line of the email and the words “site visit”.
2. The names of people who are projected to attend, may change, especially due to any COV19 symptoms, we are not collecting people’s names, but rather the quantity of people who are attending. We will be limiting the groups to 10 at a time, therefore there will be staggering of groups if necessary.
3. Two people per firm are allowed to attend the site visit only; this includes any subcontractors who wish to attend. A Prime contractor can bring a subcontractor but then they have met their two person limit. Please clarify in your email to the Contract Specialist, how many people will be attending.
4. Face masks must be worn by all attending parties, we will not be providing face masks, ensure you bring one with you.
5. Six feet social distancing space to be accommodated at all times.
6. Bathrooms are accessible before and after the site visit for hand washing
7. Violation of these rules will be grounds for the person to be removed from the site visit
These ground rules will be followed by all attending the site visit and those conducting the site visit. This is to ensure the safety of the entire acquisition team, including the people attending and conducting the site visits. These measures ensure that all parties are following the CDC Guidelines to prevent the spread of COV19. If you have any symptoms or are unsure of your COV19 status, please do not attend the site visit. Please follow CDC Guidelines for self isolation if you have any symptoms as identified by the CDC.
Please ensure you arrive early enough to gain access to the installation prior to the beginning of the site visit. All parties will meet at the location listed in 52.236-27 before visiting any site locations. Late arrivals will not be accommodated nor will any additional site visits be scheduled.
Please utilize the time before the site visit to become familiar with the documents.
Please see Attachment 10 if you need to access Fort Hunter Liggett, instructions are on the form.
Questions are not answered at the site visit. All questions are to be emailed to the Contract Specialist by the deadline. All questions will be answered via an amendment posted to sam.gov.
Please ensure before your firm submits a bid, that you checkwww.beta.sam.gov for all amendments and updated documents. Wage Determinations are updated 10 days before the Bid Opening Date.
In accordance with DPAP changes to reporting requirements under FAR 52.223-2, Affirmative Procurement of Bio-based Products under Service and Construction Contracts, contractors are now required to submit annual bio-based reports to the new reporting module in the System for Award Management (SAM). SAM can be accessed at www.beta.sam.gov
The “Equal Employment Opportunity Is the Law” notice (poster) referenced in FAR clause 52.222-26(b)(3), Equal Opportunity, is located at http://www.dol.gov/ofccp/regs/compliance/posters/ofccpost.htm
In accordance with FAR 22.404-10, the contractor must post a copy of the wage determination and Department of Labor Form WH-1321 in a prominent place where employees working on federal construction contracts can easily see it. The applicable wage determination is incorporated into the contract at Section H. The WH-1321 poster is located at http://www.dol.gov/compliance/guide/index.htm
VETS-4212 Registration: You shall register on the VETS-4212 site to be considered for award. http://www.dol.cov/vets/vets-4212.html if you have a Government contract or subcontract in the amount of $150,000 or more that was entered into or modified on or after December 1, 2003.
ATTACHMENTS: All referenced documents for this solicitation are available at the Government Point of Entry at https://beta.sam.gov Potential bidders are encouraged to subscribe for real-time e-mail notifications when information has been posted to the website for this solicitation.
Attachments listed below will be incorporated into the resultant contract.
W911SA21B2007 Attachment 1 AT OPSEC W911SA21B2007 Attachment 2 SOW Updated 23 July 2021 W911SA21B2007 Attachment 3 Bldg 301 Plans W911SA21B2007 Attachment 4 Bldg 301B Floor Plan W911SA21B2007 Attachment 5 Bldg 301C Floor Plan W911SA21B2007 Attachment 6 Bldg 301J Floor Plan W911SA21B2007 Attachment 7 Bldg 296 Floor Plan W911SA21B2007 Attachment 8 Wage Determination 22 July 2021 W911SA21B2007 Attachment 9 SF 24 Sample W911SA21B2007 Attachment 10 FHL Form 7 W911SA21B2007 Attachment 11 Picture Sidewalk Repair W911SA21B2007 Attachment 12 Bldg 301 Asbestos Survey
EVALUATION OF BIDS
BASIS OF AWARD
This requirement shall be awarded utilizing Sealed Bidding Procedures in accordance with Federal Acquisition Regulation (FAR) Part 14, as supplemented by the Defense Federal Acquisition Regulation Supplement (DFARS), and the Army Federal Acquisition Regulation Supplement (AFARS). Award will be made with reasonable promptness to the responsible bidder submitting the lowest responsive bid in accordance with requirements and provisions herein.
EVALUATION CRITERIA
The Government will evaluate bids received in response to this solicitation solely on the basis of price and price related factors.
a. Evaluations will be conducted on the total price only.
b. RESPONSIVENESS OF BID. For a bid to be determined responsive and considered for award, the bid must comply in all material respects with the invitation for bids. Such compliance enables bidders to stand on an equal footing, and maintain integrity of the sealed bidding system (Subpart 14.301).
In order to be considered responsive the Bidder:
· Properly signed SF 1442, with Signature
· Acknowledgement (if any) of all Material Amendments,
· Shall not qualify the terms and conditions of the solicitation in the submitted bid
· Shall comply with the instructions of the solicitation.
· A Bid Bond/Guarantee is required and shall be provided in the amount of twenty percent (20%) of the bid price or $3 Million whichever is less. (Bidders must use the Standard Form (SF) 24 if providing a bid bond as the bid guarantee)
· Shall submit electronic bid through DoD Secure Access File Exchange (SAFE) (https://safe.apps.mil) will be the only accepted method for submission of bids for this solicitation.
Non-Responsive bids will not be considered for contract award.
INSTRUCTIONS TO BIDDERS
In response to the COVID-19 pandemic and the President’s declaration of a National Emergency concerning COVID-19 on 13 March 2020, MICC Ft McCoy is following the recommended safety guidelines imposed by the World Health Organization (WHO) and the Centers for Disease Control and Prevention (CDC) to mitigate the spread of COVID-19, therefore, the procedures for bid submission and public bid openings are hereby changed as follows.
Bid Submission: Due to the current COVID-19 public health crisis, electronic bids submitted through DoD Secure Access File Exchange (SAFE) (https://safe.apps.mil) will be the only accepted method for submission of bids for this solicitation. Traditional paper bids will not be accepted. Non-CAC users will not have the capability to upload proposals or documents without a Drop-Off request. Offerors must send an email to the Contract Specialist at michelle.m.harvey3.civ@mail.mil to receive a Drop-Off request; please include the solicitation number in the subject line of the email. Once the Offeror receives the Drop-Off request, the Drop-Off can only be accessed for a period of 14 days to upload files. We request that you submit your request for a Drop-Off no sooner than two to three days prior to the submission due date because all uploaded files will be automatically deleted from DoD SAFE 7 days after upload. Offeror's are reminded to allow sufficient time for their submittals' files to upload, transmit, and timestamp. Therefore, waiting until the last minute to attempt transmission of your proposal could result in your submittal being deemed late should the website encounter performance or technical issues.
NOTE: Upon successful upload, there is a confirmation screen that informs you that your upload is successful, if you get a blank screen your upload DID NOT work, please submit until you get a confirmation screen. Submit your documents early enough so you have time in case the upload does not work.
Public Bid Openings: Due to the current COVID-19 public health crisis, the Public Bid Opening for this solicitation will be conducted via teleconference. To attend the Public Bid Opening teleconference, any interested party must submit an email request to the Contract Specialist (michelle.m.harvey3.civ@mail.mil) prior to the Bid Due Time in order to access the teleconference. The Contract Specialist will provide you the phone number and attendee passcode for attendance. Once the teleconference has begun, no access information will be distributed, and no information will be repeated for late attendees.
The public bid opening teleconference will occur after the time that the bids are due in order to facilitate the transfer of bid submission via DoD SAFE to the MICC as well as set up the teleconference call. All times are listed above. Late Bids received after the Bid Due date/time will not be considered for award; even if they are received before the Public Bid Opening. Screen Shots of the DoD SAFE submission will be taken to confirm each contractor bid was received by the bid due date/time.
Bid abstracts and Screen Shots of the DoD SAFE submission will be posted on www.beta.sam.gov at the conclusion of the Public Bid Opening Teleconference.
The bidder’s failure to include information required by this solicitation may result in the bid submission being found non-responsive and may therefore be ineligible for award.
(End of Summary of Changes) image1.wmf