W911SA-16-B-0004_Solicitation_Amendment_0001.docx

DOCX document 215 KB Posted

Attached to
Buckeye Job Order Contract (JOC) Federal contract opportunity
Solicitation number
W911SA-16-B-0004
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort McCoy

About this file

Solicitation Amendment

View the file

Other files for this federal contract opportunity

Other files attached to Buckeye Job Order Contract (JOC), newest first.
File Type Posted
W911SA-16-B-0004_Buckeye_JOC_Preliminary_Bid_Opening_Results.pdf PDF
29_Feb_2016_W911SA-16-B-0004_TE-2_Buckeye_JOC_Coefficient_Spreadsheet.xlsx XLSX spreadsheet
W911SA-16-B-0004_Solicitation_Modification_0003.docx DOCX document
29_Feb_2016_W911SA-16-B-0004_TE-2_Buckeye_JOC_Coefficient_Spreadsheet.xlsx XLSX spreadsheet
Corrected_W911SA-16-B-0004_TE-2_Buckeye_JOC_Coefficient_Spreadsheet.xlsx XLSX spreadsheet
W911SA-16-B-0004_Final_Solicitation_Amendment_0002.docx DOCX document
W911SA-16-B-0004_Conformed_Copy_of_Solicitation.docx DOCX document
Historical_Data_for_Buckeye_JOC.docx DOCX document
W911SA-14-B-0015_Award_Notice.pdf PDF
W911SA-16-B-0004_TE-5_Wage_Rate_Requirements.xlsx XLSX spreadsheet
W911SA-16-B-0004_Pre-Bid_Conference_Slides.pptx PPTX presentation
W911SA-16-B-0004_Pre-Bid_Conference_Sign_In_Sheet.pdf PDF
W911SA-16-B-0004_Appendix_A_-_Pre-Bid_Conference_Registration_(F).docx DOCX document
W911SA-16-B-0004_TE-4_Unified_Facilities_Criteria.pdf PDF
W911SA-16-B-0004_TE-3_AT-OPSEC_Coversheet_-_Buckeye.pdf PDF
W911SA-16-B-0004_Final_Solicitation.docx DOCX document
W911SA-16-B-0004_TE-1_Scope_of_Work_-_Buckeye_JOC.doc DOC document
W911SA-16-B-0004_TE-2_Buckeye_JOC_Coefficient_Spreadsheet.xlsx XLSX spreadsheet
W911SA-16-B-0004_TE-5_Wage_Rate_Requirements.xlsx XLSX spreadsheet
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911SA-16-B-0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

QUESTIONS AND ANSWERS

1. On page 16, item 10 discusses the bid bond and bond guarantee and it states that a payment and performance bond will be required to be in the maximum amount of $1,500,000.00 for each year. The contract has a minimum guarantee of $200,000.00 (see page 11, item 3.C.) for each year. By having the payment and performance bond at the Maximum amount this may tie up bonding capacity for the small business’ if the maximum amount is not contracted and a lessor amount is awarded. This may harm the small business and may actually end up hurting the awarded contractor.

a. Per AFARS 5117.9004-2(g) “Bonding must be sufficient to cover the stated estimated annual maximum contract value.”

2. We would like to propose that a payment and performance bond be provided in the amount of $200,000 and then provide additional bonds for each additional task order or block of task orders.

a. Please see above.

3. The bid documents show that this project is a HUB Zone set a side contract. FBO.GOV states that the contract changed from a HUB Zone Set a side to having no set a side. Can you please clarify what type of set a side contract this is, if any?

a. This solicitation is set-aside as a Hub-zone per Solicitation and www.fbo.gov information has been confirmed that Hub-zone set-aside is annotated 2/16/16.

4. Was there a prior Buckeye JOC? If so could we get the previous coefficient?

a. Award Notification that was publicly released at the time of Award will be released showing this information.

b. See “W911SA-14-B-0015 Award Notice” document

5. Page 15 of the solicitation, paragraph 8f speaks to the “Lincoln JOC Facilities coefficient schedule.”

What is meant by the “Lincoln JOC?”

a. This is a typographical error that will be fixed with this amendment. That sentence should read “Buckeye JOC”. The Lincoln JOC is a separate solicitation listed under solicitation number W911SA-16-B-0002.

6. Will Division 1 line items be allowed?

a. Where applicable, line items in Division 1 are allowed.

7. If you can use Division 1 line items, on page 14-15 of the solicitation you exclude several of these items from Division 1. Are we to expect that these costs, such as, Project Manager, Superintendent, traffic signs and barriers will be expected to be built into our coefficient? Or will these cost be allowed to be built into the proposal utilizing the line items provided in Division 1?

a. See response to above question. The coefficient definition calls out what is considered in-direct costs and part of the coefficient.

8. From the RS Means catalog will we be required to use the bare costs or the line item total including O & P

a. Bare Costs

9. C.1.4 c. TECHNICAL / PROJECT MANAGEMENT STAFF. The Contractor shall maintain sufficient technical design and project management personnel to perform the scope of the required work, and to respond to the Government’s requirements within the times specified for multiple, concurrent actions which will require simultaneous execution. How do we know or estimate the number of simultaneous executions that may take place so there is sufficient technical and management staff?

a. After minimum guarantee is met, delivery orders will be issued and there is no way of knowing the number of delivery orders to be issued.

10. It takes time to put estimates together and costs time and money and some projects do not get handled under the JOC, how would the contractor get paid for the time to take the estimates especially the projects that the Government decides not to do after the estimate is done?

a. Part of your coefficient, technical design and project mgmt. costs

11. How many total facilities does this contract include?

a. All facilities are listed on the coefficient schedule

12. On page 12 of the solicitation, paragraph 5a, second paragraph states that “The approved UPB cost data and associated software shall be utilized to produce the cost proposal.” Specific Question: There are variety of ways that this could be answered. In the most basic form, RS Means offers for purchase, an electronic version of their database which can be utilized with Microsoft Excel to provide an electronic estimate. Beyond that, there are systems which manipulate the RS Means database more efficiently than others. Does the government have a preference in what software system is to be used?

a. No, but the government is currently using e4Clicks and is very compatible to the required needs for negotiations

13. Page 13 of the specification, paragraph 7, speaks extensively to the use of a government credit card for order less than $25,000. Questions: Is the use of the credit card “typical?”

a. Yes, for all projects under $25,000.00

14. How does the contractor recover the credit card processing fee?

a. Part of your coefficient

WAGE DETERMINATIONS

General Decision Number: OH160083 02/05/2016 OH83

Superseded General Decision Number: OH20150083

State: Ohio

Construction Type: Building

County: Williams County in Ohio.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/08/2016 1 02/05/2016

ASBE0045-004 07/01/2015

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 30.00 24.78

BROH0022-007 06/01/2013

Rates Fringes

BRICK POINTER/CAULKER/CLEANER....$ 25.63 11.20

CARP0351-001 05/01/2014

Rates Fringes

CARPENTER (Excluding Soft Floor Laying)....................$ 24.66 16.47

CARP0372-005 05/01/2014

Rates Fringes

SOFT FLOOR LAYER.................$ 23.78 16.35

ELEC0008-003 05/26/2014

Rates Fringes

ELECTRICIAN......................$ 37.12 18.88

ENGI0018-033 05/01/2015

Rates Fringes

POWER EQUIPMENT OPERATOR

Backhoe/Excavator/Trackhoe;

Crane; Scraper..............$ 33.04 14.25 Forklift....................$ 31.88 14.25

IRON0055-013 07/01/2015

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 29.12 21.47

IRON0550-009 05/01/2015

Rates Fringes

IRONWORKER, ORNAMENTAL...........$ 26.66 18.36

LABO0423-002 05/01/2014

Rates Fringes

LABORER

Chain Link/Cyclone Fence Erection....................$ 27.72 9.80

LABO0500-004 07/01/2014

Rates Fringes

LABORER

Mason Tender - Cement/Concrete.............$ 24.13 12.50

PAIN0948-002 07/01/2015

Rates Fringes

GLAZIER..........................$ 27.48 14.11

PLAS0886-002 07/01/2014

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 27.18 18.11

PLUM0050-010 06/29/2015

Rates Fringes

PIPEFITTER (Excludes HVAC Pipe Installation)...............$ 39.30 23.62 PLUMBER (HVAC Pipe Installation Only)...............$ 39.30 23.62

ROOF0134-006 07/01/2013

Rates Fringes

ROOFER...........................$ 24.46 16.87

SHEE0033-017 07/01/2015

Rates Fringes

SHEET METAL WORKER (Excludes HVAC Duct and Unit Installation)....................$ 31.53 26.70

* UAVG-OH-0012 08/29/2014

Rates Fringes

BRICKLAYER: TILE FINISHER........$ 24.24 13.62

BRICKLAYER: TILE SETTER..........$ 28.31 12.94

* UAVG-OH-0013 01/01/2016

Rates Fringes

IRONWORKER, REINFORCING..........$ 27.37 19.81

SUOH2012-064 08/29/2014

Rates Fringes

BRICKLAYER.......................$ 27.47 12.26

DRYWALL FINISHER/TAPER...........$ 18.57 3.12

DRYWALL HANGER AND METAL STUD

INSTALLER........................$ 17.63 5.64

LABORER: Common or General......$ 24.76 9.10

LABORER: Landscape & Irrigation.......................$ 10.39 0.00

LABORER: Mason Tender - Brick...$ 22.74 8.60

LABORER: Pipelayer..............$ 18.37 4.79

OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 20.00 3.26

OPERATOR: Bulldozer.............$ 23.50 7.51

OPERATOR: Loader................$ 17.43 2.72

OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 25.85 10.42

PAINTER (Brush and Roller).......$ 17.91 10.85

PLUMBER, Excludes HVAC Pipe Installation.....................$ 29.57 17.20

SHEET METAL WORKER (HVAC Duct and HVAC Unit Installation Only)............................$ 22.05 12.18

SPRINKLER FITTER (Fire Sprinklers)......................$ 25.91 9.18

TRUCK DRIVER: Dump (All Types)...$ 17.97 4.14

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

General Decision Number: OH160002 02/19/2016 OH2

Superseded General Decision Number: OH20150002

State: Ohio

Construction Types: Heavy and Highway

Counties: Ohio Statewide.

Heavy and Highway Construction Projects

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/08/2016 1 01/15/2016 2 02/05/2016 3 02/19/2016

BRKY0007-003 06/01/2011

LAWRENCE

Rates Fringes

Bricklayer, Stonemason...........$ 28.29 16.80

BROH0001-001 07/01/2014

DEFIANCE, FULTON (Excluding Fulton, Amboy & Swan Creek Townships), HENRY (Excluding Monroe, Bartlow, Liberty, Washington, Richfield, Marion, Damascus & Townships & that part of Harrison Township outside corporate limits of city of Napoleon), PAULDING, PUTNAM and WILLIAMS COUNTIES

Rates Fringes

Bricklayer, Stonemason...........$ 30.05 13.02

BROH0001-004 06/01/2014

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 28.33 11.37

BROH0003-002 07/01/2014

FULTON (Townships of Amboy, Swan Creek & Fulton), HENRY (Townships of Washington, Damascus, Richfield, Bartlow, Liberty, Harrison, Monroe, & Marion), LUCAS and WOOD (Townships of Perrysburg, Ross, Lake, Troy, Freedom, Montgomery, Webster, Center, Portage, Middleton, Plain, Liberty, Henry, Washington, Weston, Milton, Jackson & Grand Rapids) COUNTIES

Bricklayer, Stonemason...........$ 30.05 13.02

BROH0005-003 05/01/2015

CUYAHOGA, LORAIN & MEDINA (Hinckley, Granger, Brunswick, Liverpool, Montville, York, Homer, Harrisville, Chatham, Litchfield & Spencer Townships and the city of Medina)

BRICKLAYER

BRICKLAYERS; CAULKERS;

CLEANERS; POINTERS; &

STONEMASONS.................$ 33.81 14.00

SANDBLASTERS................$ 33.81 14.00

SEWER BRICKLAYERS & STACK

BUILDERS....................$ 33.81 14.00

SEWER BRICKLAYERS; STACK

BUILDERS; & SWING SCAFFOLDS.$ 30.91 11.78

SWING SCAFFOLDS.............$ 33.81 14.00

BROH0006-005 05/01/2015

CARROLL, COLUMBIANA (Knox, Butler, West & Hanover Townships), STARK & TUSCARAWAS

Bricklayer, Stonemason...........$ 26.84 12.60

BROH0007-005 09/01/2014

PORTAGE & SUMMIT

Rates Fringes

BRICKLAYER.......................$ 29.35 14.36

BROH0007-010 06/01/2014

PORTAGE & SUMMIT

Rates Fringes

MASON - STONE....................$ 28.33 11.37

BROH0008-001 06/01/2014

COLUMBIANA (Salem, Perry, Fairfield, Center, Elk Run, Middleton, & Unity Townships and the city of New Waterford), MAHONING & TRUMBULL

BRICKLAYER.......................$ 27.10 16.89

BROH0009-002 06/01/2014

BELMONT & MONROE COUNTIES and the Townships of Warren & Mt.

Pleasant and the Village of Dillonvale in JEFFERSON COUNTY

Bricklayer, Stonemason...........$ 28.33 11.37 Refractory.......................$ 30.24 17.14

BROH0010-002 07/01/2015

COLUMBIANA (St. Clair, Madison, Wayne, Franklin, Washington, Yellow Creek & Liverpool Townships) & JEFFERSON (Brush Creek & Saline Townships)

Bricklayer, Stonemason...........$ 28.57 17.85

BROH0014-002 06/01/2014

HARRISON & JEFFERSON (Except Mt. Pleasant, Warren, Brush Creek, Saline & Salineville Townships & the Village of Dillonvale)

BROH0016-002 05/01/2015

ASHTABULA, GEAUGA, and LAKE COUNTIES

Rates Fringes

Bricklayer, Stonemason...........$ 32.03 14.9

BROH0018-002 06/01/2014

BROWN, BUTLER, CLERMONT, HAMILTON, PREBLE (Gasper, Dixon, Israel, Lanier, Somers & Gratis Townships) & WARREN COUNTIES:

BROH0022-004 06/01/2014

CHAMPAIGN, CLARK, CLINTON, DARKE, GREENE, HIGHLAND, LOGAN,

MIAMI, MONTGOMERY, PREBLE (Jackson, Monroe, Harrison, Twin, Jefferson & Washington Townships) and SHELBY COUNTIES

BROH0032-001 06/01/2014

GALLIA & MEIGS

Rates Fringes

Bricklayer, Stonemason...........$ 28.33 11.37

BROH0035-002 06/01/2014

ALLEN, AUGLAIZE, MERCER and VAN WERT COUNTIES

Rates Fringes

Bricklayer, Stonemason...........$ 28.33 11.37

BROH0039-002 06/01/2014

ADAMS & SCIOTO

Rates Fringes

Bricklayer, Stonemason...........$ 31.27 15.89

BROH0040-003 06/01/2015

ASHLAND, CRAWFORD, HARDIN, HOLMES, MARION, MORROW, RICHLAND,

WAYNE and WYANDOT (Except Crawford, Ridge, Richland & Tymochtee Townships) COUNTIES

Bricklayer, Stonemason...........$ 29.09 17.18

FOOTNOTE: Layout Man and Sawman rate: $1.00 per hour above journeyman rate.

Free standing stack work ground level to top of stack;

Sandblasting and laying of carbon masonry material in swing stage and/or scaffold; Ramming and spading of plastics and gunniting: $1.50 per hour above journeyman rate.

"Hot" work: $2.50 above journeyman rate.

BROH0044-002 06/01/2015

Rates Fringes

Bricklayer, Stonemason

COSHOCTON, FAIRFIELD,

GUERNSEY, HOCKING, KNOX,

KICKING, MORGAN,

MUSKINGUM, NOBLE (Beaver, Buffalo, Seneca & Wayne Townships) & PERRY

COUNTIES:...................$ 26.20 13.89

BROH0045-002 06/01/2014

FAYETTE, JACKSON, PIKE, ROSS and VINTON COUNTIES

Rates Fringes

Bricklayer, Stonemason...........$ 29.88 12.89

BROH0046-002 06/01/2015

ERIE, HANCOCK, HURON, OTTAWA, SANDUSKY, SENECA, WOOD (Perry & Bloom Townships) and WYANDOT (Tymochtee, Crawford, Ridge & Richland Townships) COUNTIES & the Islands of Lake Erie north of Sandusky

Bricklayer, Stonemason...........$ 29.60 16.88

FOOTNOTE: Layout Man and Sawman rate: $1.00 per hour above journeyman rate.

Free standing stack work ground level to top of stack;

Sandblasting and laying of carbon masonry material in swing stage and/or scaffold; Ramming and spading of plastics and gunniting: $1.50 per hour above journeyman rate.

"Hot" work: $2.50 above journeyman rate.

BROH0052-001 06/01/2014

ATHENS COUNTY

Rates Fringes

Bricklayer, Stonemason...........$ 28.33 11.37

BROH0052-003 06/01/2014

NOBLE (Brookfield, Noble, Center, Sharon, Olive, Enoch, Stock, Jackson, Jefferson & Elk Townships) and WASHINGTON COUNTIES

Bricklayer, Stonemason...........$ 27.77 14.93

BROH0055-003 06/01/2014

DELAWARE, FRANKLIN, MADISON, PICKAWAY and UNION COUNTIES

Rates Fringes

Bricklayer, Stonemason...........$ 29.88 12.89

CARP0003-004 05/01/2014

MAHONING & TRUMBULL

Rates Fringes

CARPENTER........................$ 25.61 15.10

CARP0069-003 05/01/2014

CARROLL, STARK, TUSCARAWAS & WAYNE

Rates Fringes

CARPENTER........................$ 25.50 13.67

CARP0069-006 05/01/2014

COSHOCTON, HOLMES, KNOX & MORROW

Rates Fringes

CARPENTER........................$ 23.66 13.05

CARP0171-002 05/01/2014

BELMONT, COLUMBIANA, HARRISON, JEFFERSON & MONROE

Rates Fringes

CARPENTER........................$ 26.02 15.49

CARP0200-002 05/01/2014

ADAMS, ATHENS, DELAWARE, FAIRFIELD, FAYETTE, FRANKLIN, GALLIA,

GUERNSEY, HIGHLAND, HOCKING, JACKSON, LAWRENCE, LICKING,

MADISON, MARION, MEIGS, MORGAN, MUSKINGUM, NOBLE, PERRY,

PICKAWAY, PIKE, ROSS, SCIOTO, UNION, VINTON and WASHINGTON

COUNTIES

CARPENTER........................$ 28.22 13.50

Diver............................$ 39.41 10.40

PILEDRIVERMAN....................$ 28.22 13.50

CARP0248-005 07/01/2008

LUCAS & WOOD

Rates Fringes

CARPENTER........................$ 27.27 14.58

CARP0248-008 07/01/2008

Rates Fringes

CARPENTER

DEFIANCE, FULTON, HANCOCK,

HENRY, PAULDING & WILLIAMS

COUNTIES....................$ 23.71 13.28

CARP0254-002 05/01/2014

ASHTABULA, CUYAHOGA, GEAUGA & LAKE

Rates Fringes

CARPENTER........................$ 31.61 14.46

CARP0372-002 07/01/2008

ALLEN, AUGLAIZE, HARDIN, MERCER, PUTNAM & VAN WERT

Rates Fringes

CARPENTER........................$ 23.18 13.28

CARP0639-003 05/01/2014

MEDINA, PORTAGE & SUMMIT

Rates Fringes

CARPENTER........................$ 29.59 14.64

CARP0735-002 05/01/2014

ASHLAND, ERIE, HURON, LORAIN & RICHLAND

Rates Fringes

CARPENTER........................$ 24.80 13.29

CARP1311-001 05/01/2014

BROWN, BUTLER, CHAMPAIGN, CLARK, CLERMONT, CLINTON, DARKE,

GREENE, HAMILTON, LOGAN, MIAMI, MONTGOMERY, PREBLE, SHELBY &

WARREN

Carpenter & Piledrivermen........$ 27.39 14.33 Diver............................$ 40.58 9.69

CARP1393-002 07/01/2008

CRAWFORD, DEFIANCE, FULTON, HANCOCK, HENRY, LUCAS, OTTAWA,

PAULDING, SANDUSKY, SENECA, WILLIAMS & WOOD

Piledrivermen & Diver's Tender...$ 27.30 16.05

DIVERS - $250.00 per day

CARP1393-003 07/01/2008

ALLEN, AUGLAIZE, HARDIN, MERCER, PUTNAM, VAN WERT & WYANDOT

Rates Fringes

Piledrivermen & Diver's Tender...$ 25.15 15.92

DIVERS - $250.00 per day

CARP1871-006 06/01/2013

BELMONT, HARRISON, & MONROE

Rates Fringes

Diver, Wet.......................$ 47.07 13.92 Piledrivermen; Diver, Dry........$ 31.38 13.92

CARP1871-008 06/01/2013

ASHLAND, ASHTABULA, CUYAHOGA, ERIE, GEAUGA, HURON, LAKE,

LORAIN, MEDINA, PORTAGE, RICHLAND & SUMMIT

Diver, Wet.......................$ 44.22 15.49 Piledrivermen; Diver, Dry........$ 29.48 15.49

CARP1871-014 06/01/2013

CARROLL, STARK, TUSCARAWAS & WAYNE

Rates Fringes

Diver, Wet.......................$ 37.40 13.81 Piledrivermen; Diver, Dry........$ 24.93 13.81

CARP1871-015 06/01/2013

COSHOCTON, HOLMES, KNOX & MORROW

Rates Fringes

Diver, Wet.......................$ 36.53 12.96 Piledrivermen; Diver, Dry........$ 24.35 12.96

CARP1871-017 06/01/2013

MAHONING & TRUMBULL

Rates Fringes

Diver, Wet.......................$ 39.44 14.16 Piledrivermen; Diver, Dry........$ 26.29 14.16

CARP2235-012 01/01/2014

COLUMBIANA & JEFFERSON

Rates Fringes

PILEDRIVERMAN....................$ 31.74 16.41

CARP2239-001 07/01/2008

CRAWFORD, OTTAWA, SANDUSKY, SENECA & WYANDOT

Rates Fringes

CARPENTER........................$ 23.71 13.28

ELEC0008-002 05/26/2014

DEFIANCE, FULTON, HANCOCK, HENRY, LUCAS, OTTAWA, PAULDING,

PUTNAM, SANDUSKY, SENECA, WILLIAMS & WOOD

CABLE SPLICER....................$ 38.98 18.96

ELECTRICIAN......................$ 37.12 18.88

ELEC0032-003 06/01/2014

ALLEN, AUGLAIZE, HARDIN, LOGAN, MERCER, SHELBY, VAN WERT &

WYANDOT (Crawford, Jackson, Marseilles, Mifflin, Ridgeland, Ridge & Salem Townships)

ELECTRICIAN......................$ 28.32 15.18

ELEC0032-004 06/01/1998

ALLEN, HARDIN, VAN WERT & WYANDOT (Crawford, Jackson, Marseilles, Mifflin, Richland, Ridge & Salem Townships)

Line Construction Equipment Operator..........$ 20.27 4.12+a Groundman Truck Driver......$ 14.43 3.63+a Lineman.....................$ 22.52 4.31+a

FOOTNOTE: a. Half day's Paid Holiday: The last 4 hours of the workday prior to Christmas or New Year's Day

ELEC0038-002 04/27/2015

CUYAHOGA, GEAUGA (Bainbridge, Chester & Russell Townships) & LORAIN (Columbia Township)

ELECTRICIAN

Excluding Sound & Communications Work.........$ 37.13 19.88

FOOTNOTES;

a. 6 Paid Holidays: New Year's Day; Memorial Day; July 4th;

Labor Day; Thanksgiving Day; & Christmas Day

b. 1 week's paid vacation for 1 year's service; 2 weeks' paid vacation for 2 or more years' service

ELEC0038-008 04/27/2015

CUYAHOGA, GEAUGA (Bainbridge, Chester & Russell Townships) & LORAIN (Columbia Township)

Sound & Communication Technician Communications Technician...$ 26.05 10.40+a+b Installer Technician........$ 24.55 10.11+a+b

FOOTNOTES;

a. 6 Paid Holidays: New Year's Day; Memorial Day; July 4th;

Labor Day; Thanksgiving Day; & Christmas Day

b. 1 week's paid vacation for 1 year's service; 2 weeks' paid vacation for 2 or more years' service

* ELEC0064-003 11/30/2015

COLUMBIANA (Butler, Fairfield, Perry, Salem & Unity Townships) MAHONING (Austintown, Beaver, Berlin, Boardman, Canfield, Ellsworth, Coitsville, Goshen, Green, Jackson, Poland, Springfield & Youngstown Townships), & TRUMBULL (Hubbard & Liberty Townships)

ELECTRICIAN......................$ 32.02 13.74

ELEC0071-001 12/28/2015

ASHLAND, CHAMPAIGN, CLARK, COSHOCTON, CRAWFORD, DELAWARE,

FAIRFIELD, FAYETTE, FRANKLIN, GUERNSEY, HIGHLAND, HOCKING,

JACKSON (Coal, Jackson, Liberty, Milton, Washington & Wellston Townships), KNOX, LICKING, MADISON, MARION, MONROE, MORGAN, MORROW, MUSKINGUM, NOBLE, PERRY, PICKAWAY, PIKE (Beaver, Benton, Jackson, Mifflin, Pebble, Peepee, Perry & Seal Townships), RICHLAND, ROSS, TUSCARAWAS (Auburn, Bucks, Clay, Jefferson, Oxford, Perry, Salem, Rush, Washington & York Townships), UNION, VINTON (Clinton, Eagle, Elk, Harrison, Jackson, Richland & Swan Townships), and WASHINGTON COUNTIES

Equipment Operators.........$ 32.24 12.34 Groundmen...................$ 23.28 10.37 Linemen & Cable Splicers....$ 35.82 13.13

ELEC0071-004 12/28/2015

AUGLAIZE, CLINTON, DARKE, GREENE, LOGAN, MERCER, MIAMI,

MONTGOMERY, PREBLE, and SHELBY COUNTIES

Equipment Operator..........$ 32.24 12.34 Groundman...................$ 23.28 10.37 Lineman & Cable Splicers....$ 35.82 13.13

ELEC0071-005 12/29/2015

ASHTABULA, CUYAHOGA, GEAUGA, LAKE & LORAIN

Rates Fringes

LINE CONSTRUCTION: Equipment Operator DOT/Traffic Signal & Highway Lighting Projects...$ 31.30 13.07 Municipal Power/Transit Projects....................$ 37.34 14.58 LINE CONSTRUCTION: Groundman DOT/Traffic Signal & Highway Lighting Projects...$ 24.34 11.33 Municipal Power/Transit Projects....................$ 29.05 12.51

LINE CONSTRUCTION:

Linemen/Cable Splicer DOT/Traffic Signal & Highway Lighting Projects...$ 34.78 13.94 Municipal Power/Transit Projects....................$ 41.49 15.61

ELEC0071-008 12/28/2015

COLUMBIANA, MAHONING, and TRUMBULL COUNTIES

Rates Fringes

Line Construction Equipment Operator..........$ 32.24 12.34 Groundman...................$ 23.28 10.37 Lineman & Cable Splicers....$ 35.82 13.13

ELEC0071-010 12/28/2015

BELMONT, CARROLL, HARRISON, HOLMES, JEFFERSON, MEDINA, PORTAGE,

STARK, SUMMIT, and WAYNE COUNTIES

Equipment Operator..........$ 32.24 12.34 Groundman...................$ 23.28 10.37 Lineman & Cable Splicers....$ 35.82 13.13

ELEC0071-013 12/28/2015

BROWN, BUTLER, CLERMONT, HAMILTON, and WARREN COUNTIES

Rates Fringes

Line Construction Equipment Operator..........$ 32.24 12.34 Groundman...................$ 23.28 10.37 Lineman & Cable Splicers....$ 35.82 13.13

ELEC0071-014 12/28/2015

ADAMS, ATHENS, GALLIA, JACKSON (Bloomfield, Franklin, Hamilton, Lick, Jefferson, Scioto & Madison Townships), LAWRENCE, MEIGS, PIKE (Camp Creek, Marion, Newton, Scioto, Sunfish & Union Townships), SCIOTO & VINTON (Brown, Knox, Madison, Vinton & Wilkesville Townships)

Equipment Operator..........$ 32.24 12.34 Groundman...................$ 23.28 10.37 Lineman & Cable Splicers....$ 35.82 13.13

* ELEC0082-002 11/30/2015

CLINTON, DARKE, GREENE, MIAMI, MONTGOMERY, PREBLE & WARREN

(Wayne, Clear Creek & Franklin Townships)

ELECTRICIAN......................$ 28.60 17.60

ELEC0082-006 12/01/2014

CLINTON, DARKE, GREENE, MIAMI, MONTGOMERY, PREBLE & WARREN

(Wayne, Clear Creek & Franklin Townships)

Sound & Communication Technician Cable Puller................$ 10.24 4.91 Installer/Technician........$ 22.75 9.91

ELEC0129-003 03/01/2010

LORAIN (Except Columbia Township) & MEDINA (Litchfield & Liverpool Townships)

ELECTRICIAN......................$ 31.00 13.80

ELEC0129-004 03/01/2010

ERIE & HURON (Lyme, Ridgefield, Norwalk, Townsend, Wakeman, Sherman, Peru, Bronson, Hartland, Clarksfield, Norwich, Greenfield, Fairfield, Fitchville & New London Townships)

ELECTRICIAN......................$ 31.00 13.80

ELEC0141-003 09/01/2015

BELMONT COUNTY

Rates Fringes

CABLE SPLICER....................$ 32.25 23.67

ELECTRICIAN......................$ 28.80 23.06

ELEC0212-003 07/01/2013

BROWN, CLERMONT & HAMILTON

Rates Fringes

Sound & Communication Technician.......................$ 22.50 9.51

ELEC0212-005 06/01/2015

BROWN, CLERMONT, and HAMILTON COUNTIES

Rates Fringes

ELECTRICIAN......................$ 27.03 17.02

ELEC0245-003 08/26/2013

DEFIANCE, FULTON, HANCOCK, HENRY, HURON, LUCAS, OTTAWA,

PAULDING, PUTNAM, SANDUSKY, SENECA, WILLIAMS, and WOOD COUNTIES

Cable Splicer...............$ 39.72 24.77%+$5.00+a Groundman/Truck Driver......$ 15.11 24.77%+$5.00+a Heli-arc Welding............$ 34.84 24.77%+$5.00+a Lineman.....................$ 24.54 24.77%+$5.00+a Operator - Class 1..........$ 27.63 24.77%+$5.00+a Operator - Class 2..........$ 24.18 24.77%+$5.00+a Traffic Signal & Lighting Technician..................$ 31.09 24.77%+$5.00+a

FOOTNOTE: a. 6 Observed Holidays: New Year's Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; & Christmas Day. Employees who work on a holiday shall be paid at a rate of double their applicable classified straight-time rates for the work performed on such holiday.

ELEC0245-004 09/01/2014

ERIE COUNTY

Rates Fringes

Line Construction Cable Splicer...............$ 40.83 25.20%+$5.00+a Groundman/Truck Driver......$ 15.53 25.20%+$5.00+a Lineman.....................$ 35.50 25.20%+$5.00+a Operator - Class 1..........$ 28.40 25.20%+$5.00+a Operator - Class 2..........$ 24.85 25.20%+$5.00+a

FOOTNOTE: a. 6 Observed Holidays: New Year's Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; & Christmas Day. Employees who work on a holiday shall be paid at a rate of double their applicable classified straight-time rates for the work performed on such holiday.

ELEC0246-006 10/29/2012

Rates Fringes

ELECTRICIAN......................$ 33.00 26.16

* ELEC0306-005 06/01/2015

MEDINA (Brunswick, Chatham, Granger, Guilford, Harrisville, Hinckley, Homer, Lafayette, Medina, Montville, Sharon, Spencer, Wadsworth, Westfield & York Townships), PORTAGE (Atwater, Aurora, Brimfield, Deerfield, Franklin, Mantua, Randolph, Ravenna, Rootstown, Shalersville, Streetsboro & Suffield Townships), SUMMIT & WAYNE (Baughman, Canaan, Chester, Chippewa, Congress, Green, Milton, & Wayne Townships)

CABLE SPLICER....................$ 36.87 16.56

ELECTRICIAN......................$ 34.14 16.56

ELEC0317-002 05/28/2014

GALLIA & LAWRENCE

Rates Fringes

CABLE SPLICER....................$ 32.68 18.13

ELECTRICIAN......................$ 32.62 21.45

ELEC0540-003 06/05/1997

TUSCARAWAS COUNTY (North of Auburn, Clay, Rush & York Townships)

Rates Fringes

Line Construction Groundman; & Truck Driver...$ 14.65 8.18 Line Equipment Operator.....$ 19.02 8.69 Lineman; & Cable Splicer....$ 21.86 9.01

* ELEC0540-005 12/28/2015

CARROLL (Northern half, including Fox, Harrison, Rose & Washington Townhships), COLUMBIANA (Knox Township), HOLMES, MAHONING (Smith Township), STARK, TUSCARAWAS (North of Auburn, Clay, Rush & York Townships), and WAYNE (South of Baughman, Chester, Green & Wayne Townships) COUNTIES

ELECTRICIAN......................$ 30.04 21.78

ELEC0573-003 06/01/2015

ASHTABULA (Colebrook, Wayne, Williamsfield, Orwell & Windsor Townships), GEAUGA (Auburn, Middlefield, Parkman & Troy Townships), MAHONING (Milton Township), PORTAGE (Charlestown, Edinburg, Freedom, Hiram, Nelson, Palmyra, Paris & Windham Townships), and TRUMBULL (Except Liberty & Hubbard Townships)

ELECTRICIAN......................$ 30.57 16.85

ELEC0575-001 06/02/2015

ADAMS, FAYETTE, HIGHLAND, HOCKING, JACKSON (Bloomfield, Franklin, Hamilton, Jefferson, Lick, Madison, Scioto, Coal, Jackson, Liberty, Milton & Washington Townships), PICKAWAY (Deer Creek, Perry, Pickaway, Salt Creek & Wayne Townships), PIKE (Beaver, Benton, Jackson, Mifflin, Pebble, PeePee, Perry, Seal, Camp Creek, Newton, Scioto, Sunfish, Union & Marion Townships), ROSS, SCIOTO & VINTON (Clinton, Eagle, Elk, Harrison, Jackson, Richland & Swan Townships)

ELECTRICIAN......................$ 31.70 14.58

ELEC0648-001 08/31/2015

BUTLER and WARREN COUNTIES (Deerfield, Hamilton, Harlan, Massie, Salem, Turtle Creek, Union & Washington Townships)

CABLE SPLICER....................$ 29.39 17.17

ELECTRICIAN......................$ 28.89 17.15

ELEC0673-004 06/01/2015

ASHTABULA (Excluding Orwell, Colebrook, Williamsfield, Wayne & Windsor Townships), GEAUGA (Burton, Chardon, Claridon, Hambden, Huntsburg, Montville, Munson, Newbury & Thompson Townships) and

LAKE COUNTIES

CABLE SPLICER....................$ 33.29 17.11

ELECTRICIAN......................$ 33.37 18.05

ELEC0683-002 06/02/2014

CHAMPAIGN, CLARK, DELAWARE, FAIRFIELD, FRANKLIN, MADISON,

PICKAWAY (Circleville, Darby, Harrison, Jackson, Madison, Monroe, Muhlenberg, Scioto, Walnut & Washington Townships), and

UNION COUNTIES

CABLE SPLICER....................$ 31.45 15.85

ELECTRICIAN......................$ 30.85 15.85

ELEC0688-003 06/02/2014

ASHLAND, CRAWFORD, HURON (Richmond, New Haven, Ripley & Greenwich Townships), KNOX (Liberty, Clinton, Union, Howard, Monroe, Middleberry, Morris, Wayne, Berlin, Pike, Brown & Jefferson Townships), MARION, MORROW, RICHLAND and WYANDOT (Sycamore, Crane, Eden, Pitt, Antrim & Tymochtee Townships)

ELECTRICIAN......................$ 26.75 15.31

ELEC0972-002 06/01/2014

ATHENS, MEIGS, MONROE, MORGAN, NOBLE, VINTON (Brown, Knox, Madison, Vinton & Wilkesville Townships), and WASHINGTON

COUNITES

CABLE SPLICER....................$ 32.49 21.33

ELECTRICIAN......................$ 32.24 21.33

ELEC1105-001 12/28/2015

COSHOCTON, GUERNSEY, KNOX (Jackson, Clay, Morgan, Miller, Milford, Hilliar, Butler, Harrison, Pleasant & College Townships), LICKING, MUSKINGUM, PERRY, and TUSCARAWAS (Auburn, York, Clay, Jefferson, Rush, Oxford, Washington, Salem, Perry & Bucks Townships) COUNTIES

ELECTRICIAN......................$ 30.20 15.08

ENGI0018-003 05/01/2015

ASHTABULA, CUYAHOGA, ERIE, GEAUGA, LAKE, LORAIN, MEDINA,

PORTAGE, and SUMMIT COUNTIES

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 34.83 14.25

GROUP 2.....................$ 34.73 14.25

GROUP 3.....................$ 33.69 14.25

GROUP 4.....................$ 32.47 14.25

GROUP 5.....................$ 27.18 14.25

GROUP 6.....................$ 35.08 14.25

GROUP 7.....................$ 35.33 14.25

OPERATING ENGINEER CLASSIFICATIONS

GROUP 1 - Air Compressor on Steel Erection; Barrier Moving Machine; Boiler Operator on Compressor or Generator when mounted on a Rig; Cableway; Combination Concrete Mixer & Tower; Concrete Plant (over 4 yd. Capacity); Concrete Pump;

Crane (All Types, Including Boom Truck, Cherry Picker);

Crane-Compact, Track or Rubber over 4,000 lbs. capacity;

Cranes-Self Erecting, Stationary, Track or Truck (All Configurations); Derrick; Dragline; Dredge (Dipper, Clam or Suction); Elevating Grader or Euclid Loader; Floating Equipment (All Types); Gradall; Helicopter Crew (Operator-Hoist or Winch); Hoe (all types); Hoisting Engine on Shaft or Tunnel Work; Hydraulic Gantry (Lifting System);

Industrial-Type Tractor; Jet Engine Dryer (D8 or D9) Diesel Tractor; Locomotive (Standard Gauge); Maintenance Operator Class A; Mixer, Paving (Single or Double Drum); Mucking Machine; Multiple Scraper; Piledriving Machine (All Types);

Power Shovel; Prentice Loader; Quad 9 (Double Pusher); Rail Tamper (with auto lifting & aligning device); Refrigerating Machine (Freezer Operation); Rotary Drill, on Caisson work;

Rough Terrain Fork Lift with Winch/Hoist; Side-Boom;

Slip-Form Paver; Tower Derrick; Tree Shredder; Trench Machine (Over 24" wide); Truck Mounted Concrete Pump; Tug Boat; Tunnel Machine and/or Mining Machine; Wheel Excavator; and Asphalt Plant Engineer (Cleveland District Only).

GROUP 2 - Asphalt Paver; Automatic Subgrader Machine, Self-Propelled (CMI Type); Bobcat Type and/or Skid Steer Loader with Hoe Attachment Greater than 7,000 lbs.; Boring Machine More than 48"; Bulldozer; Endloader; Horizontal Directional Drill (Over 50,000 ft lbs thrust); Hydro Milling Machine; Kolman-type Loader (production type-Dirt);

Lead Greaseman; Lighting & Traffic Signal Installation Equipment (includes all groups or classifications);

Material Transfer Equipment (Shuttle Buggy) Asphalt;

Pettibone-Rail Equipment; Power Grader; Power Scraper; Push Cat; Rotomill (all), Grinders & Planers of All types;

Trench Machine (24" wide & under); Vermeer type Concrete Saw; and Maintenance Operators (Portage and Summit Counties Only).

GROUP 3 - A-Frame; Air Compressor on Tunnel Work (low pressure); Asphalt Plant Engineer (Portage and Summit Counties Only); Bobcat-type and/or Skid Steer Loader with or without Attachments; Highway Drills (all types);

Locomotive (narrow gauge); Material Hoist/Elevator; Mixer, Concrete (more than one bag capacity); Mixer, one bag capacity (Side Loader); Power Boiler (Over 15 lbs.

Pressure) Pump Operator installing & operating Well Points;

Pump (4" & over discharge); Roller, Asphalt; Rotovator (lime soil stabilizer); Switch & Tie Tampers (without lifting & aligning device); Utility Operator (Small equipment); Welding Machines; and Railroad Tie Inserter/Remover; Articulating/straight bed end dumps if assigned (minus $4.00 per hour.

GROUP 4 - Backfiller; Ballast Re-locator; Bars, Joint & Mesh Installing Machine; Batch Plant; Boring Machine Operator (48" or less); Bull Floats; Burlap & Curing Machine;

Concrete Plant (capacity 4 yd. & under); Concrete Saw (Multiple); Conveyor (Highway); Crusher; Deckhand;

Farm-type Tractor with attachments (highway); Finishing Machine; Fireperson, Floating Equipment (all types);

Forklift; Form Trencher; Hydro Hammer expect masonary;

Hydro Seeder; Pavement Breaker; Plant Mixer; Post Driver;

Post Hole Digger (Power Auger); Power Brush Burner; Power Form Handling Equipment; Road Widening Trencher; Roller (Brick, Grade & Macadam); Self-Propelled Power Spreader;

Self-Propelled Power Subgrader; Steam Fireperson; Tractor (Pulling Sheepfoot, Roller or Grader); and Vibratory Compactor with Integral Power.

GROUP 5 - Compressor (Portable, Sewer, Heavy & Highway); Drum Fireperson (Asphalt Plant); Generator; Masonry Fork Lift;

Inboard-Outboard Motor Boat Launch; Oil Heater (asphalt plant); Oiler/Helper; Power Driven Heater; Power Sweeper & Scrubber; Pump (under 4" discharge); Signalperson; Tire Repairperson; VAC/ALLS; Cranes - Compact, track or rubber under 4,000 pound capacity; fueling and greasing; and Chainmen.

GROUP 6 - Master Mechanic & Boom from 150 to 180.

GROUP 7 - Boom from 180 and over.

ENGI0018-004 05/01/2015

ADAMS, ALLEN, ASHLAND, ATHENS, AUGLAIZE, BELMONT, BROWN,

BUTLER, CARROLL, CHAMPAIGN, CLARK, CLERMONT, CLINTON,

COSHOCTON, CRAWFORD, DARKE, DEFIANCE, DELAWARE, FAIRFIELD,

FAYETTE, FRANKLIN, FULTON, GALLIA, GREENE, GUERNSEY, HAMILTON,

HANCOCK, HARDIN, HARRISON, HENRY, HIGHLAND, HOCKING, HOLMES,

HURON, JACKSON, JEFFERSON, KNOX, LAWRENCE, LICKING, LOGAN,

LUCAS, MADISON, MARION, MEIGS, MERCER, MIAMI, MONROE,

MONTGOMERY, MORGAN, MORROW, MUSKINGUM, NOBLE, OTTAWA, PAULDING,

PERRY, PICKAWAY, PIKE, PREBLE, PUTNAM, RICHLAND, ROSS,

SANDUSKY, SCIOTO, SENECA, SHELBY, STARK, TUSCARAWAS, UNION, VAN

WERT, VINTON, WARREN, WASHINGTON, WAYNE, WILLIAMS, WOOD, and

YANDOT COUNTIES

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 33.34 14.25

GROUP 2.....................$ 33.22 14.25

GROUP 3.....................$ 32.18 14.25

GROUP 4.....................$ 31.00 14.25

GROUP 5.....................$ 25.54 14.25

GROUP 6.....................$ 33.59 14.25

GROUP 7.....................$ 33.84 14.25

OPERATING ENGINEER CLASSIFICATIONS

GROUP 1 - Air Compressor on Steel Erection; Barrier Moving Machine; Boiler Operator on Compressor or Generator when mounted on a Rig; Cableway; Combination Concrete Mixer & Tower; Concrete Plant (over 4 yd. Capacity); Concrete Pump;

Crane (All Types, Including Boom Truck, Cherry Picker);

Crane-Compact, Track or Rubber over 4,000 lbs. capacity;

Cranes-Self Erecting, Stationary, Track or Truck (All Configurations); Derrick; Dragline; Dredge (Dipper, Clam or Suction); Elevating Grader or Euclid Loader; Floating Equipment (All Types); Gradall; Helicopter Crew (Operator-Hoist or Winch); Hoe (all types); Hoisting Engine on Shaft or Tunnel Work; Hydraulic Gantry (Lifting System); Industrial-Type Tractor; Jet Engine Dryer (D8 or D9) Diesel Tractor; Locomotive (Standard Gauge);

Maintenance Operator Class A; Mixer, Paving (Single or Double Drum); Mucking Machine; Multiple Scraper;

Piledriving Machine (All Types); Power Shovel; Prentice Loader; Quad 9 (Double Pusher); Rail Tamper (with auto lifting & aligning device); Refrigerating Machine (Freezer Operation); Rotary Drill, on Caisson work; Rough Terrain Fork Lift with Winch/Hoist; Side-Boom; Slip-Form Paver;

Tower Derrick; Tree Shredder; Trench Machine (Over 24" wide); Truck Mounted Concrete Pump; Tug Boat; Tunnel Machine and/or Mining Machine; and Wheel Excavator.

GROUP 2 - Asphalt Paver; Automatic Subgrader Machine, Self-Propelled (CMI Type); Bobcat Type and/or Skid Steer Loader with Hoe Attachment Greater than 7,000 lbs.; Boring Machine More than 48"; Bulldozer; Endloader; Hydro Milling Machine; Horizontal Directional Drill (over 50,000 ft. lbs.

thrust);Kolman-type Loader (production type-Dirt); Lead Greaseman; Lighting & Traffic Signal Installation Equipment (includes all groups or classifications); Material Transfer Equipment (Shuttle Buggy) Asphalt; Pettibone-Rail Equipment; Power Grader; Power Scraper; Push Cat; Rotomill (all), Grinders & Planers of All types; Trench Machine (24" wide & under); and Vermeer type Concrete Saw.

GROUP 3 - A-Frame; Air Compressor on Tunnel Work (low pressure); Asphalt Plant Engineer; Bobcat-type and/or Skid Steer Loader with or without Attachments; Highway Drills (all types); Locomotive (narrow gauge); Material Hoist/Elevator; Mixer, Concrete (more than one bag capacity); Mixer, one bag capacity (Side Loader); Power Boiler (Over 15 lbs. Pressure) Pump Operator installing & operating Well Points; Pump (4" & over discharge); Railroad Tie Inserter/Remover; Roller, Asphalt; Rotovator (lime soil stabilizer); Switch & Tie Tampers (without lifting & aligning device); Utility Operator (Small equipment); and Welding Machines; Artiaculating/straight bed end dumps if assigned (minus $4.00 per hour.

GROUP 4 - Backfiller; Ballast Re-locator; Bars, Joint & Mesh Installing Machine; Batch Plant; Boring Machine Operator (48" or less); Bull Floats; Burlap & Curing Machine;

Concrete Plant (capacity 4 yd. & under); Concrete Saw (Multiple); Conveyor (Highway); Crusher; Deckhand;

Farm-type Tractor with attachments (highway); Finishing Machine; Fireperson, Floating Equipment (all types); Fork Lift; Form Trencher; Hydro Hammer expect masonary; Hydro Seeder; Pavement Breaker; Plant Mixer; Post Driver; Post Hole Digger (Power Auger); Power Brush Burner; Power Form Handling Equipment; Road Widening Trencher; Roller (Brick, Grade & Macadam); Self-Propelled Power Spreader;

Self-Propelled Power Subgrader; Steam Fireperson; Tractor (Pulling Sheepfoot, Roller or Grader); and Vibratory Compactor with Integral Power.

GROUP 5 - Compressor (Portable, Sewer, Heavy & Highway); Drum Fireperson (Asphalt Plant); Generator; Masonary Forklift;

Inboard-Outboard Motor Boat Launch; Oil Heater (asphalt plant); Oiler/Helper; Power Driven Heater; Power Sweeper & Scrubber; Pump (under 4" discharge); Signalperson; Tire Repairperson; VAC/ALLS; Cranes - Compact, track or rubber under 4,000 pound capacity; fueling and greasing; and Chainmen.

GROUP 6 - Master Mechanic & Boom from 150 to 180.

GROUP 7 - Boom from 180 and over.

ENGI0066-023 06/01/2014

COLUMBIANA, MAHONING & TRUMBULL COUNTIES

Rates Fringes

POWER EQUIPMENT OPERATOR

ASBESTOS; HAZARDOUS/TOXIC

WASTE PROJECTS

GROUP 1 - A & B.............$ 37.55 17.51

ASBESTOS; HAZARDOUS/TOXIC

WASTE PROJECTS

GROUP 2 - A & B.............$ 37.22 17.51

ASBESTOS; HAZARDOUS/TOXIC

WASTE PROJECTS

GROUP 3 - A & B.............$ 33.49 17.51

ASBESTOS; HAZARDOUS/TOXIC

WASTE PROJECTS

GROUP 4 - A & B.............$ 29.54 17.51

ASBESTOS; HAZARDOUS/TOXIC

WASTE PROJECTS

GROUP 5 - A & B.............$ 26.15 17.51

HAZARDOUS/TOXIC WASTE

PROJECTS

GROUP 1 - C & D.............$ 34.42 17.51

HAZARDOUS/TOXIC WASTE

PROJECTS

GROUP 2 - C & D.............$ 34.12 17.51

HAZARDOUS/TOXIC WASTE

PROJECTS

GROUP 3 - C & D.............$ 30.70 17.51

HAZARDOUS/TOXIC WASTE

PROJECTS

GROUP 4 - C & D.............$ 27.08 17.51

HAZARDOUS/TOXIC WASTE

PROJECTS

GROUP 5 - C & D.............$ 23.97 17.51

ALL OTHER WORK

GROUP 1.....................$ 31.29 17.51

ALL OTHER WORK

GROUP 2.....................$ 31.02 17.51

ALL OTHER WORK

GROUP 3.....................$ 27.91 17.51

ALL OTHER WORK

GROUP 4.....................$ 24.62 17.51

ALL OTHER WORK

GROUP 5.....................$ 21.79 17.51

GROUP 1 - Rig, Pile Driver or Caisson Type; & Rig, Pile Hydraulic Unit Attached

GROUP 2 - Asphalt Heater Planer; Backfiller with Drag Attachment; Backhoe; Backhoe with Shear attached; Backhoe-Rear Pivotal Swing; Batch Plant-Central Mix Concrete; Batch Plant, Portable concrete; Berm Builder-Automatic; Boat Derrick; Boat-Tug;

Boring Machine Attached to Tractor; Bullclam; Bulldozer;

C.M.I. Road Builder & Similar Type; Cable Placer & Layer;

Carrier-Straddle; Carryall-Scraper or Scoop; Chicago Boom;

Compactor with Blade Attached; Concrete Saw (Vermeer or similar type); Concrete Spreader Finisher; Combination, Bidwell Machine; Crane; Crane-Electric Overhead;

Crane-Rough Terrain; Crane-Side Boom; Crane-Truck;

Crane-Tower; Derrick-Boom; Derrick-Car; Digger-Wheel (Not trencher or road widener); Double Nine; Drag Line; Dredge;

Drill-Kenny or Similar Type; Easy Pour Median Barrier Machine (or similar type); Electromatic; Frankie Pile;

Gradall; Grader; Gurry; Self-Propelled; Heavy Equipment Robotics Operator/Mechanic; Hoist-Monorail;

Hoist-Stationary & Mobile Tractor; Hoist, 2 or 3 drum;

Horizontal Directional Drill Operator; Jackall; Jumbo Machine; Kocal & Kuhlman; Land-Seagoing Vehicle; Loader, Elevating; Loader, Front End; Loader, Skid Steer;

Locomotive; Mechanic/Welder; Metro Chip Harvester with Boom; Mucking Machine; Paver-Asphalt Finishing Machine;

Paver-Road Concrete; Paver-Slip Form (C.M.I. or similar);

Place Crete Machine with Boom; Post Driver (Carrier mounted); Power Driven Hydraulic Pump & Jack (When used in Slip Form or Lift Slab Construction); Pump Crete Machine;

Regulator-Ballast; Hydraulic Power Unit not attached to Rig for Pile Drillings; Rigs-Drilling; Roto Mill or similar Full Lane (8' Wide & Over); Roto Mill or similar type (Under 8'); Shovel; Slip Form Curb Machine; Speedwing;

Spikemaster; Stonecrusher; Tie Puller & Loader; Tie Tamper;

Tractor-Double Boom; Tractor with Attachments; Truck-Boom;

Truck-Tire; Trench Machine; Tunnel Machine (Mark 21 Java or similar); & Whirley (or similar type)

GROUP 3 - Asphalt Plant; Bending Machine (Pipeline or similar type); Boring machine, Motor Driven; Chip Harvester without Boom; Cleaning Machine, Pipeline Type; Coating Machine, Pipeline Type; Compactor; Concrete Belt Placer;

Concrete Finisher; Concrete Planer or Asphalt; Concrete Spreader; Elevator; Fork Lift (Home building only); Fork lift & Lulls; Fork Lift Walk Behind (Hoisting over 1 buck high); Form Line Machine; Grease Truck operator; Grout Pump; Gunnite Machine; Horizontal Directional Drill Locator; Single Drum Hoist with or without Tower; Huck Bolting Machine; Hydraulic Scaffold (Hoisting building materials); Paving Breaker (Self-propelled or Ridden);

Pipe Dream; Pot Fireperson (Power Agitated); Refrigeration Plant; Road Widener; Roller; Sasgen Derrick; Seeding Machine; Soil Stabilizer (Pump type); Spray Cure Machine, Self-Propelled; Straw Blower Machine; Sub-Grader; Tube Finisher or Broom C.M.I. or similar type; & Tugger Hoist

GROUP 4 - Air Curtain Destructor & Similar Type; Batch Plant-Job Related; Boiler Operator; Compressor; Conveyor;

Curb Builder, self-propelled; Drill Wagon; Generator Set;

Generator-Steam; Heater-Portable Power; Hydraulic Manipulator Crane; Jack-Hydraulic Power driven;

Jack-Hydraulic (Railroad); Ladavator; Minor Machine Operator; Mixer-Concrete; Mulching Machine; Pin Puller;

Power Broom; Pulverizer; Pump; Road Finishing Machine (Pull Type); Saw-Concrete-Self-Propelled (Highway Work); Signal Person; Spray Cure Machine-Motor Powered; Stump Cutter;

Tractor; Trencher Form; Water Blaster; Steam Jenny;

Syphon; Vibrator-Gasoline; & Welding Machine

GROUP 5 - Brakeperson; Fireperson; & Oiler

IRON0017-002 05/01/2015

ASHTABULA (North of Route 6, starting at the Geauga County Line, proceeding east to State Route 45), CUYAHOGA, ERIE (Eastern 2/3), GEAUGA, HURON (East of a line drawn from the north border through Monroeville & Willard), LAKE, LORAIN, MEDINA (North of Old Rte. #224), PORTAGE (West of a line from Middlefield to Shalersville to Deerfield), and SUMMIT (North of Old Rte. #224, including city limits of Barberton) COUNTIES

IRONWORKER

Ornamental, Reinforcing, & Structural..................$ 31.30 22.01

IRON0017-010 05/01/2015

ASHTABULA (Eastern part from Lake Erie on the north to route #322 on the south to include Conneaut, Kingsville, Sheffield, Denmark, Dorset, Cherry Valley, Wayne, Monroe, Pierpont, Richmond, Andover & Williamsfield Townships)

Structural, including metal building erection & Reinforcing..........

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .