Amendment to Responses to Questions

View the file

Other files

File Type Posted
W911S8-16-R-0006_0004_Fire_Suppression.pdf PDF
W911S8-16-R-0006-0004.pdf PDF
Attachment_E_PWS_W911S8-16-R-0006__Fire_Supp_6_March_2017.docx DOCX document
Amendment_3_-_W911S8-16-R-0006_Fire_Kitchen_Suppression_ITM_3-7-17.pdf PDF
TE_3_-_Revised_3-6-17.xlsx XLSX spreadsheet
QA_W911S8-16-R-0002_JBLM_Fire_Suppression_3_March_2017.pdf PDF
W911S8-16-R-0006-0002.pdf PDF
Pre-proposal_Conf_Slides_W911S8-16-R-0006_JBLM_Fire_Suppr_(7Feb2017).pptx PPTX presentation
Site_Visit_Attendee_List_2-7-17.pdf PDF
16-R-0006-0001.pdf PDF
TE_3_-_Revised_1-31-17.xlsx XLSX spreadsheet
Attachment_A_Fire_Alarm_Inspection_&_Testing_form.docx DOCX document
Attachment_E_PWS_W911S8-16-R-0006__Fire_Supp.docx DOCX document
Attachment_C_Sprinkler_System_test_form.docx DOCX document
Attachment_B_Kitchen_hood_suppression_form.doc DOC document
Attachment_D__Fire_Pump_test_form.docx DOCX document
Technical_Exhibit_3_Contractor_Proposal_Data_Matrix.xlsx XLSX spreadsheet
Technical_Exhibit_1_Facilities_List.xlsx XLSX spreadsheet
Attachment_F_WD_15-5539_Rev_2_-_Pierce_County_1-23-17.docx DOCX document
Attachment_A2_Fire_Alarm_continuation_form.docx DOCX document
Exhibit_1_Daily_Inspection_Report.docx DOCX document
W911S8-16-R-0006_JBLM_Fire_Suppression_ITM.pdf PDF
Attachment_G_WD_15-2569_Yakima_County_-_1-23-17.docx DOCX document
Technical_Exhibit_2_Fire_Systems_Building_Devices.xlsx XLSX spreadsheet
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDED Response to Questions W911S8-16-R-0006 Fire Suppression, Fire Alarm, Fire Sprinkler Systems Inspection, Testing & Maintenance Joint Base Lewis-McChord, WA

28. AFFF/HEF – Per PWS 1.5 “aircraft hangar AFFF foam agent systems (to include lab testing of concentrate)” is listed. Question: There is no CLIN offered to price this action. Should there be?

Answer: An amendment addressing this issue is forthcoming. See TE-3 item, “Foam Fire Suppression.”

29. AFFF/HEF – Pew PWS 1.5 “All performed work shall comply with and be in accordance with (IAW) the Unified Facilities Criteria (UFC) 3-601-02”, per the UFC 03-601-2 annual requirements from table 2.8 the foam pumps/proportions are to be tested to verify operability and proper proportioning, and to flush after operation.

Questions:

Is the intent to flow foam per the UFC?

If yes does the foam concentrate level have to be filled back to the beginning levels upon completion, and priced accordingly?

If yes who is responsible for disposal of the foam and flushing wastes?

There is no CLIN to price these actions. Should there be?

Answer: Yes, the intent is flow foam per the UFC. Yes, the concentrate level has to be filled back to beginning levels upon completion. The contractor is required to perform in accordance with the UFC. If the test causes the system to drop below safe operating range or below UFC operational standard the contractor is required to inform the COR. The contractor is required to dispose of all test wastes or discharges, to include flushing, to return the system to normal operating standard in accordance the PWS and EPA regulations. An amendment addressing the CLIN issue is forthcoming.