Solicitation Amendment 02 W911RX26BA0020002 SF 30.pdf

PDF 4 MB Posted

Attached to
Ft. Bliss BLDG 2479 Kitchenette Installation Amendment 03
Solicitation number
W911RX-26-B-A002
Issued by

About this file

This is Amendment 0002 to solicitation W911RX26BA002, issued by the U.S. Army Corps of Engineers (USACE) Fort Riley, Kansas on July 22, 2026, with an effective date of July 22, 2026. The amendment is not extended, meaning the receipt deadline for offers remains unchanged. The amendment updates Section J (List of Attachments) to clarify kitchen installation requirements for Building 2479, specifying that only two kitchen installations are required. The project number is PANMCC-26-P-0000 044426.

The amendment adds one new contract document—Attachment 11-Updated Industry Q&A (22JUL2026)—and modifies the display order of Attachment 12 (As-Built Drawings) from position 12 to position 13. All other terms and conditions of the original solicitation dated June 25, 2026 remain unchanged and in full force and effect. Offerors must acknowledge receipt of this amendment prior to the specified deadline by completing required items, acknowledging receipt on each offer copy, or sending separate written communication that references both the solicitation and amendment numbers. Failure to provide timely acknowledgment may result in offer rejection.

View the file

Other files

File Type Posted
Attachment 14-Project closeout report (2008) W911RX26BA002.pdf PDF
Solicitation Amendment 03 W911RX26BA0020003.pdf PDF
Attachment 13-Ltd Asbestos-Lead Survey_Bldg-2479_20080704 W911RX26BA002.pdf PDF
Solicitation Amendment 03 W911RX26BA0020003 SF 30.pdf PDF
Attachment 02-Asbestos-Lead Survey_Bldg-2479 W911RX26BA002.pdf PDF
Solicitation Amendment 02 W911RX26BA0020002.pdf PDF
Attachment 11-Updated Industry QA 22JUL2026 W911RX26BA002.pdf PDF
Solicitation Amendment W911RX26BA0020001.pdf PDF
Solicitation Amendment W911RX26BA0020001 SF 30.pdf PDF
Attachment 01-SOW B2479 Kitchenette 8A Rev2 07172026 W911RX26BA002.pdf PDF
Attachment 11-Industry QA 07152026 W911RX26BA002.pdf PDF
Attachment 12- As Built Drawings W911RX26BA002.pdf PDF
Attachment 02-Asbestos-Lead Survey Bldg 2478_20120209 W911RX26BA002.pdf PDF
Attachment 03-ENG_FORM_4288-R W911RX26BA002.pdf PDF
Attachment 07-Drawing of Bldg 2479 - Kitchenette - 04232026 W911RX26BA002.pdf PDF
Attachment 06-iWATCH Trng for Contractors 20190613 W911RX26BA002.pdf PDF
Attachment 10-26-0345_Environmental Review_11B 10118 6P W911RX26BA002.pdf PDF
Attachment 08-Material Approval Submittal_-FILLABLE W911RX26BA002.pdf PDF
Solicitation - W911RX26BA002.pdf PDF
Attachment 01-SOW Rev2 06-03-26 W911RX26BA002.pdf PDF
Attachment 04-DPW-RFI Template Blank Form V.1.2 W911RX26BA002.pdf PDF
Attachment 05-FIRE PREVENTION CONSTRUCTION GUIDE 2025 W911RX26BA002.pdf PDF
Attachment 09-Davis-Bacon Act WD TX20260245 W911RX26BA002.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section J - List of Attachments

The attachments table has changed from:

Identifie r

Document Name

Document Description Reference Identifier

Date Line Item Page N umbers

Docum ent Type

Provide d Under Separat e Cover

0011 Attachment 01-

SOW B2479

Kitchenette_8A Rev2 07-17-

2026, W911RX

26BA002

Statement of Work 20 Jul 2026 Attach ment

No

0002 Attachment 02- Asbestos-Lead Survey Bldg 24 78_20120209, W911RX26BA0

Environmental Review 25 Jun 2026 Attach ment

No

0003 Attachment 03-

ENG_FORM_4

288-R, W911R

X26BA002

Form 4288-R 25 Jun 2026 Attach ment

No

0004 Attachment 04-

DPW-RFI

Template Blank Form V.

1.2, W911RX2

6BA002

RFI 25 Jun 2026 Attach ment

No

0005 Attachment 05-

FIRE

PREVENTION

CONSTRUCTI

ON GUIDE

2025, W911RX

26BA002

Fire Prevention Construction Guide

25 Jun 2026 Attach ment

No

0006 Attachment 06-iWATCH Trng for Contractors iWATCH Training for Contractors 25 Jun 2026 Attach ment

No

W911RX26BA0020002

20190613, W9

11RX26BA002

0007 Attachment 07- Drawing of Bldg 2479 - Kitchenette - 04232026, W9

11RX26BA002

Drawings 25 Jun 2026 Attach ment

No

0008 Attachment 08- Material Approval Submittal_-

FILLABLE, W9

11RX26BA002

Material Approval 25 Jun 2026 Attach ment

No

0009 Attachment 09- Davis-Bacon Act WD #

TX20260245,

W911RX26BA0

Wage Determination 25 Jun 2026 Attach ment

No

0010 Attachment 10- 26-0345_Envir onmental Review_11B 10118 6P, W91

1RX26BA002

Environmental Review 25 Jun 2026 Attach ment

No

0014 Attachment 11- Industry Q&A

(15JUL2026),

W911RX26BA0

Industry Questions and Answers 20 Jul 2026 Attach ment

No

0013 Attachment 12- As-Built Drawings, W91

1RX26BA002

Drawings 20 Jul 2026 Attach ment

No

To:

Identifie r

Document Name

Document Description Reference Identifier

Date Line Item Page N umbers

Docum ent Type

Provide d Under Separat e Cover

0011 Attachment 01-

SOW B2479

Kitchenette_8A Rev2 07-17-

2026, W911RX

26BA002

Statement of Work 20 Jul 2026 Attach ment

No

0002 Attachment 02- Asbestos-Lead Survey Bldg 24 78_20120209, W911RX26BA0

Environmental Review 25 Jun 2026 Attach ment

No

0003 Attachment 03-

ENG_FORM_4

288-R, W911R

X26BA002

Form 4288-R 25 Jun 2026 Attach ment

No

0004 Attachment 04-

DPW-RFI

Template Blank Form V.

1.2, W911RX2

6BA002

RFI 25 Jun 2026 Attach ment

No

0005 Attachment 05-

FIRE

PREVENTION

CONSTRUCTI

ON GUIDE

2025, W911RX

26BA002

Fire Prevention Construction Guide

25 Jun 2026 Attach ment

No

0006 Attachment 06-iWATCH Trng for Contractors 20190613, W9

11RX26BA002

iWATCH Training for Contractors 25 Jun 2026 Attach ment

No

0007 Attachment 07- Drawing of Bldg 2479 - Kitchenette - 04232026, W9

11RX26BA002

Drawings 25 Jun 2026 Attach ment

No

0008 Attachment 08- Material Approval Submittal_-

FILLABLE, W9

11RX26BA002

Material Approval 25 Jun 2026 Attach ment

No

0009 Attachment 09- Davis-Bacon Act WD #

TX20260245,

W911RX26BA0

Wage Determination 25 Jun 2026 Attach ment

No

0010 Attachment 10- 26-0345_Envir onmental Review_11B

Environmental Review 25 Jun 2026 Attach ment

No

10118 6P, W91

1RX26BA002

0014 Attachment 11- Industry Q&A

(15JUL2026),

W911RX26BA0

Industry Questions and Answers 20 Jul 2026 Attach ment

No

0015 Attachment 11- Updated Industry Q&A

(22JUL2026),

W911RX26BA0

Attachment 11-Update to Industry

Q&A (22JUL2026)

22 Jul 2026 Attach ment

No

0013 Attachment 12- As-Built Drawings, W91

1RX26BA002

Drawings 20 Jul 2026 Attach ment

No

The following contract documents were added:

Attachment 11-Updated Industry Q&A (22JUL2026), W911RX26BA002

The following contract documents were modified:

Attachment 12- As-Built Drawings, W911RX26BA002

INFORMATION FROM TO

Contract Document Display Order

12 13

IDCode: J
Page: 1
Pages: 5
AmendNo: 0002
EffDate: 22 JUL 2026
ReqNo:
ProjNo: PANMCC-26-P-0000 044426
IssCode: W911RX
AdmCode:
IssuedBy: W6QM MICC-FT RILEY

KO DIRECTORATE OF CONTRACTIN, 1792 12TH STREET

FORT RILEY, KS 66442-0248

UNITED STATES

JONI WARDOSKY, EMAIL: JONI.N.WARDOSKY.CIV@ARMY.MIL TELEPHONE: 5206843849

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W911RX26BA002
SolDate: 25 JUN 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: Update to Attachment 11 to specify room numbers for the kitchen installations. Clarifying only two kitchen installations are required for Building 2479.
ContNameTitle:
CoNameTitle: TRAVIS E. ENGLE
ContDate:
CODate: 22 JUL 2026

File details come from the government source that posted it. Updated .