Washer and Dryer Solicitation Questions 13May2022 (V2)-KO Reviewed.pdf

PDF 411 KB Posted

Attached to
AMENDMENT-03 W911RX-22-Q-0041 WASHERS AND DRYERS MAINTENANCE SERVICE
Solicitation number
W911RX-22-Q-0041
Issued by

View the file

Other files

File Type Posted
Washer and Dryer Solicitation Questions (2) 2022-05-24.pdf PDF
Technical Exhibit A Price Bid Schedule v3 2022-05-24.xlsx XLSX spreadsheet
3rd Amendment Solicitation Conformed 2022-05-24.pdf PDF
3rd Amendment Solicitation Modification 2022-05-24.pdf PDF
Technical Exhibit 02 - Washer and Dryer Locations v3 2022-05-12.xlsx XLSX spreadsheet
2nd Amendment Solicitation Modification Copy 2022-05-13.pdf PDF
Technical Exhibit A - Price Bid Schedule v2 2022-05-12.xlsx XLSX spreadsheet
2nd Amendment Solicitation Conform Copy 2022-05-13.pdf PDF
1st Amendment Solicitation Modification Copy 2022-05-05.pdf PDF
Atttachment 06 - Performance Work Statement v7 2022-05-12.pdf PDF
Attachment 04 - Samples of Records-Reports and Forms.pdf PDF
Technical Exhibit 04 - Dryer Vent Details v3 2022-05-12.pdf PDF
Technical Exhibit 03 - Building Floor Plans v2 2022-05-12.pdf PDF
Technical Exhibit 04 - Dryer Vent Details.pdf PDF
Washer and Dryer Maintenance Service Solicitation (W911RX-22-Q-0041).pdf PDF
Technical Exhibit A - Price Bid Schedule.xlsx XLSX spreadsheet
Technical Exhibit 03 - Building Floor Plans.pdf PDF
Attachment 01 - Wage Determinations.pdf PDF
Tchnical Exhibit 02 - Washer and Dryer Locations v2.xlsx XLSX spreadsheet
Attachment 03- Deliverables.pdf PDF
Attachment 02 - Performance Requirements Summary.pdf PDF
Attachment 06 - Performance Work Statement.pdf PDF
Technical Exhibit 04 - Dryer Vent Details.pdf PDF
Technical Exhibit 01 - Location Maps.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911RX-22-Q-0041 Solicitation Date: 05/13/22 Washer & Dryer Maintenance Question/Answers

1. When was the last time the venting system was completely cleaned and by whom? Records show the vents were last cleaned between 5 May 2021 and 14 May 2021.

2. How many buildings have convergent vents with or without fan assist motors? See Technical

Exhibit 03 – Building Floor Plans v2 and Technical Exhibit 4 – Dryer Vent Details v3 for building vent details, specifically 7001, 7003, 7081, 7815A and 7815B.

3. During the annual maintenance if the contractor discovers items in need of repair in the venting system or convergent vents, will the contractor be responsible for those repairs? See revised Attachment 06 – Performance Work Statement v7 paragraph 3.4.3 and 3.4.3.1.

4. Buildings with multiple stories do they have available elevators? See Technical Exhibit 03 – Building Floor Plans v2.

5. The government has provided detailed floor plans all the locations of each one of the laundry rooms does it have any more detailed information regarding the venting servicing these laundry rooms? For example size of ducting, associated elements such as fan assist motors plenums and accesses to venting in order to clean properly. See Techncial Exhibit 4 – Dryer Vent Details v3.

6. Is the contractor responsible for vent caps or venting elements on the sides of the building? See revised Attachment 06 – Performance Work Statement v7 paragraph 3.4.3.

7. Will the government provide a lift in order to gain access to the multi-story vent exits? No

8. There are no drawings in TE 4. Can the Gov’t please update this technical exhibit and include the appropriate drawings? See revised Techncial Exhibit 4 – Dryer Vent Details v3.

9. Please clarify the pricing requirement. Does the contractor submit TE A Price Schedule as a separate proposal document (in EXCEL) or do we include this pricing sheet in Technical Exhibit A (Pricing Schedule) of our proposal? Submit using the provided excel sheet in Technical Exhibit A v2 as a separate document.

10. Since the Gov’t purchased new machines, what is the warranty on the new washers and dryers?

There is a 5 year limited warranty on parts.

11. Can the Gov’t please confirm that the contractor is only required to remove snow from all sidewalks and steps only for their assigned portion of Building 263? See revised Attachment 06

– Performance Work Statement v7 paragraph 7.4.1.1.1.

12. Will the government conduct a site visit? This will allow the contractors to ascertain the current conditions and to identify various types of venting systems used throughout the base, to include determining the current amount of buildup and the difficulty as well as accessibility to each system? Yes

13. From the contract information, the washer and dryers are already provided and awaiting installation/maintenance correct? Yes

W911RX-22-Q-0041 Solicitation Date: 05/13/22 Washer & Dryer Maintenance Question/Answers

14. What is the make and/or model number of the washer/dryer? See Techncial Exhibit 02 – Washer and Dryer Locations v2. The Equipment Description, make, model, quantities and dimensions are listed along with the location.

15. How would you like the service quotes to be provided for the bid? Would you like the solicitation form to be submitted with quotes written in or can it be a separate document? Bid price totals will be provided on the solicitation written in or typed for each CLIN and also on the excel sheet in Technical Exhibit A v2.

16. Are there elevators to transport equipment? See Technical Exhibit 03 – Building Floor Plans v2.

17. Are there any restrictions regarding base access for individuals with a criminal history? See paragraph 2.14.5.1 and 2.15.2.