This document provides details on a solicitation issued by the U.S. Army Corps of Engineers Engineering District Alaska for environmental remediation services. The solicitation is set aside for small businesses and has a total value of $140 million. Offerors are required to submit proposals by May 14th, 2019 responding to factors including technical capability and experience, past performance, and a firm-fixed price proposal for a sample task order. Key experience includes projects in Alaska and remote locations, as well as experience with arctic/subarctic conditions. Labor categories and rates are identified for evaluation.
AMENDMENT 0003 & REVISED ATTACHMENT L-6
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SB ERS MATOC RFP, $140M Shared Capacity
The purpose of this Amendment is to entend the proposal due date, update the RFP per responses to bidder inquiries where applicable, and incorporate the final responses to all bidder inqiuries as included in the Summary of Changes.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 57
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 02-May-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB19R0007
X 9B. DATED (SEE ITEM 11)
02-Apr-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-May-2019
CODE
U.S. ARMY ENGINEER DISTRICT, AK
CEPOA-CT (W911KB)
PO BOX 6898
JBER AK 99506-0898
W911KB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
X 1
ALDONE R. GRAHAM, Branch Chief, Contracting Officer aldone.r.graham@usace.army.mil
W911KB19R0007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 09-May-2019 02:00 PM to 14-May-2019 02:00 PM.
SECTION B - SUPPLIES OR SERVICES AND PRICES
The following have been modified: LABOR RATES FOR IDC
Base Period (3 Years)
Base Period FFP Ceiling Fully Burdened Hourly Rates – These are Firm-Fixed Price (FFP) Ceiling Fully Burdened Hourly Rates. The contractor may propose lower rates for any task order, but shall not exceed these rates in task order proposals. AMENDMENT 0003…Provide labor rate calculation chart from Section J in support of listed rates… AMENDMENT 0003
*The offeror shall completely fill out all tables in Section B for the prime offeror and any key subcontractor firm(s).
TABLE 1
Key Personnel Basic Hourly Rate Contract Year 1
Basic Hourly Rate Contract Year 2
Basic Hourly Rate Contract Year 3
Program Manager Project Manager(s) Program Chemist Health & Safety Manager Contractor Quality Control (CQC) Systems Manager Environmental Engineer(s) Environmental Scientist(s) Site Superintendent
Escalation Factor Over Previous Year Rates NA % %
G&A
OVERHEAD
PROFIT
Non-Key Personnel Basic Hourly Rate Contract Year 1
Basic Hourly Rate Contract Year 2
Basic Hourly Rate Contract Year 3
Site Safety and Health Officer Project Chemist Sampling Technician
Escalation Factor Over Previous Year Rates NA % %
G&A
OVERHEAD
PROFIT
Each Contract Year equates to one (1) calendar year from the date of contract (or option) award.
Per Diem shall be in accordance with the Joint Travel Regulations.
All other travel related costs shall be based on current competitive rates.
NOTE: The Government reserves the right to exercise any of the option years early. If any of the option years are exercised early, the labor rates from the year in which the option is exercised will apply, rather than the labor rates from the option year.
Option Period 1 (1-Year)
Option #1 Period (1YR) FFP Ceiling Fully Burdened Hourly Rates – These are Firm-Fixed Price (FFP) Ceiling Fully Burdened Hourly Rates. The contractor may propose lower rates for any task order, but shall not exceed these rates in task order proposals. AMENDMENT 0003…Provide labor rate calculation chart from Section J in support of listed rates… AMENDMENT 0003
*The offeror shall completely fill out all tables in Section B for the prime offeror and any key subcontractor firm(s).
TABLE 4
Key Personnel Basic Hourly Rate Option #1 (1YR) Contract Year 4
Program Manager $ Project Manager(s) $ Program Chemist $ Health & Safety Manager $ Contractor Quality Control (CQC) Systems Manager $ Environmental Engineer(s) $ Environmental Scientist(s) $ Site Superintendent $
Escalation Factor Over Previous Year Rates NA
G&A
OVERHEAD
Non-Key Personnel Basic Hourly Rate Option #1 (1YR) Contract Year 4
Site Safety and Health Officer $ Project Chemist $ Sampling Technician $
Escalation Factor Over Previous Year Rates
G&A
OVERHEAD
PROFIT
Each Contract Year equates to one (1) calendar year from the date of contract (or option) award.
Per Diem shall be in accordance with the Joint Travel Regulations.
All other travel related costs shall be based on current competitive rates.
NOTE: The Government reserves the right to exercise any of the option years early. If any of the option years are exercised early, the labor rates from the year in which the option is exercised will apply, rather than the labor rates
Option Period 2 (1-Year)
Option #2 Period (1YR) FFP Ceiling Fully Burdened Hourly Rates – These are Firm-Fixed Price (FFP) Ceiling Fully Burdened Hourly Rates. The contractor may propose lower rates for any task order, but shall not exceed these rates in task order proposals. AMENDMENT 0003…Provide labor rate calculation chart from Section J in support of listed rates… AMENDMENT 0003
*The offeror shall completely fill out all tables in Section B for the prime offeror and any key subcontractor firm(s).
TABLE 7
Key Personnel
Basic Hourly Rate Option #2 (1YR) Contract Year 5
(Also Applicable to Any Extension Exercised Under FAR 52.217-8) Program Manager $ Project Manager(s) $ Program Chemist $ Health & Safety Manager $ Contractor Quality Control (CQC) Systems Manager $ Environmental Engineer(s) $ Environmental Scientist(s) $ Site Superintendent $
Escalation Factor Over Previous Year Rates N/A
G&A
OVERHEAD
PROFIT
Non-Key Personnel
Basic Hourly Rate Option #2 (1YR) Contract Year 5
(Also Applicable to Any Extension Exercised Under FAR 52.217-8) Site Safety and Health Officer $ Project Chemist $ Sampling Technician $
Escalation Factor Over Previous Year Rates N/A
G&A
OVERHEAD
PROFIT
Each Contract Year equates to one (1) calendar year from the date of contract (or option) award.
Per Diem shall be in accordance with the Joint Travel Regulations.
All other travel related costs shall be based on current competitive rates.
NOTE: The Government reserves the right to exercise any of the option years early. If any of the option years are exercised early, the labor rates from the year in which the option is exercised will apply, rather than the labor rates
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been modified:
ATTACHMENTS
J-1 Service Contract Wage Determinations
Wage Determination No.: 2015-5681 Rev. 5; dated 01/10/2018
State: Alaska Area: Alaska Boroughs of Anchorage, Matanuska-Susitna Wage Determination No.: 2015-5685 Rev. 5; dated 01/10/2018
State: Alaska Area: Alaska Boroughs of Haines, Juneau, Ketchikan Gateway, Prince of Wales, Sitka, Skagway-Yakutat, Wrangell-Peter
Wage Determination No.: 2015-5687 Rev. 5; dated 01/10/2018 State: Alaska Area: Alaska Boroughs of Aleutian Island, Bethel, Bristol Bay, Dillingham, Kenai Peninsula, Kodiak Island, Nome, North Slope, Southeast Fairb, Valdez-Cordova, Wade Hampton, Yukon-Koyukuk
Wage Determination No.: 2015-5683 Rev. 5; dated 01/10/2018 State: Alaska Area: Alaska Borough of Fairbanks North
J-2 Wage Determination No.: WD 88-0162 (Rev.-15), 01/01/2019 Hazardous Waste Pickup/Disposal Services – Alaska Statewide
J-3 Quality Assurance Surveillance Plan (QASP)
J-4 Japan Status of Forces Agreement
J-5 Korea Status of Forces Agreement
J-6 USPACOM International Agreements
J-7 TASK ORDER Proposal Schedule and Checklist Form
J-8 US.370-WI.08 & SO-CT.104-WI Use of Synchronized Predeployment and Operational Tracker (SPOT) System
AMENDMENT 0003…J-9 Labor Rate Calculation Worksheet for Section B Contractually Binding Key Personnel Labor Rates…AMENDMENT 0003
NOTES:
1. The contract will comprise of the Solicitation Sections A through J and All Attachments listed in this Section J, as well as, all incorporated parts of the successful offeror(s) proposal as specified in the award.
2. All amendments to the solicitation are made part of the contract by reference.
3. Solicitation Section K (as completed by the successful offeror(s)), and Sections L and M are included in the
Solicitation only and will not be made a part of the awarded contract, but remain as part of the official solicitation record.
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
**Please note the changes throughout Section L to Page Llimitations as indicated in the responses to inquiries.**
The following have been modified: Bidder Inquiries Answered and Incorporated as of 02 MAY 2019
Project: Solicitation - W911KB19R0007 SB ERS $140M Solicitation (00001) Displaying 137 inquiries.
7926179 General Section L 2.1.3 and
2.2.1
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please resolve the discrepancy in the following paragraphs regarding "Volume 3":
Section 2.1.3 states: Submit Volume 1 and Volume 2 in the same binder. Submit one original and one (1) printed copies, as well as one (1) CD for Volumes 1 & 2. Submit Volume 3, Offer, in a binder separate from Volumes 1 and 2 and provide one (1) printed original, one (1) printed copy and one (1) separate CD.
Section 2.2.1 states: The proposal shall be submitted in two (2) Volumes: Volume 1, Technical Capability (includes all submittal requirements for Factors 1 thru Factor 4); and, Volume 2, Factor 5 and Required Pre- Award Information.
On: Apr 04 2019.
Government Response. . Section 2.1.3 will corrected by AMENDMENT 0002 to state: "Submit Volume 1 and Volume 2 in separate binders. Submit one original and one (1) printed copy for Volume 1, as well as one (1) CD for Volume 1. Submit Volume 2 in a binder separate from Volume 1 and provide one (1) printed original, one (1) printed copy and one (1) separate CD for Volume 2." On: Apr 17 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7928023 Construction Management
1 1 1
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
RFP page 347 of 371, 5.1 (b) A copy of the firm's current credit report(s).
Question: Are the two credit/trade references adequate for this requirement, if there is no credit report readily available?
On: Apr 05 2019.
Government Response. . Per RFP Section M, Paragraph 5.1 "(b) A copy of the firm's current credit report(s)..." already includes the request to include two (2) credit/trade references. This is adequate and acceptable. No Amendment Change will be made. On: Apr 17 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7928390 Contracting Section G.7.2 Fee Arrangement and G.8.2 Administration of Payments
For CPFF-CF task orders, please confirm that contractors may bill for the portion of fixed fee associated with completing the performance-based milestone, and not necessarily the entire CLIN.
On: Apr 05 2019.
Government Response. . See AMENDMENT 0001 where cost reimbursement type is removed from the solicitation in its entirety. On: Apr 17 2019
7928392 Contracting Section H 1.0 Minimum Insurance
Required
Please confirm that when required, qualified subcontractors and vendors can indemnify CAPE and the government and provide the following insurance: (d) Aircraft Public and Passenger Liability Insurance, and (e) Vessel Collision Liability and Protection and Indemnity Liability Insurance. Those types of insurance require firms to have licensed pilots, for example, so cannot typically be obtained by environmental contractors.
Government Response. . The FAR Clause 52.228-5 applies to this solicitation, as well as the items stated in SECTION H, Paragraph 1.1. The reference to FAR 28.307 is deleted in AMENDMENT 0003 (it is not applicable). Please note that the Government does not have purview over subcontractors or other vendors. The prime is responsible for what is required in the solicitation and any resultant contract. On: May 02 2019
7928393 Contracting Section L 52.215-20(b)
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
This clause references Seed and Sample Project Tasks, however only a sample project is provided in Attachment L-6. Is the reference to a Seed Project extraneous, or is the intent to actually award the project provided in Attachment L-6 as a CPFF-CF task order?
Government Response. . AMENDMENT 0002 will include this change. Section L, PROVISION FAR 52.215-20(b) will be corrected to delete the word "Seed." The solicitation has a sample task order project only. On: Apr 17 2019
7928395 Contracting Section L 2.1.1 Written Materials
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The requirements state "...the paragraph number from the submission requirements be used in the heading for the respective section/paragraph where the information is being provided." Does the underlined text mean to imply that the tabs should include the Section L paragraph number? For example, "3.1.1 Tab 1.1 Summary Table of
Environmental Experience (Attachment L)," instead of "Tab 1.1 Summary Table of Environmental Experience (Attachment L)" as noted in Table 1 – Proposal Content and Tabs List.
On: Apr 05 2019.
Government Response. . No change by Amendment will be issued for this inquiry. Please comply with RFP instructions. The Volume 1, Factor 1 does not need to reference the paragraph numbers but only the "TAB" it is under. On: Apr 17 2019
7928397 Contracting Section L 2.1.1(ii) Written
Materials
Please consider allowing a list of acronyms to be excluded from the page limitation.
Government Response. . A list of acronyms will not be part of the page count. This note will be added in a forthcoming AMENDMENT. On: Apr 17 2019
7928399 Contracting Section L 3.1 Tab 1.0
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section L.3.1.1 and L.3.1.2 both require information to be provided "...for the projects submitted for Tab 1.0 (maximum of 10 projects)." While it is clear what is required to be submitted in Tab 1.1 and Tab 1.2, it isn't clear what information is required or allowed to be submitted in our proposal under "Tab 1.0." Our interpretation is that "Tab 1.0 Factor 1 – Experience" will have no content (it's just a tab/section divider), and the instructions provided in paragraph 3.1 merely define what constitutes a relevant project and that we are to provide a list of those projects in Tab 1.1 using Attachment L-1, and provide summary information about those same projects in Tab 1.2 using Attachment L-2. Please clarify.
Government Response. . The "Tab 1.0 Factor 1 – Experience" will have no content (it's just a tab/section divider), and the instructions provided in paragraph 3.1 define what constitutes a relevant project and offerors are to provide a list of those projects in Tab 1.1 using Attachment L-1, and provide summary information about those same projects in Tab 1.2 using Attachment L-2. On: Apr 17 2019
7928401 Contracting Section L 2.2.1 Proposal Volumes and Sections
Aside from the title page and the table of contents, the first substantive content the evaluators will be seeing is Tab 1.1 Summary Table of Environmental Experience, and they will not know the team structure until 21 pages later in Tab 2.1 Management Plan. Therefore, we suggest allowing a brief two-page Executive Summary that allows an introduction of the Offeror and its team as part of Tab 1.0 FACTOR 1 – Experience, so that the evaluators understand the team structure for the context of experience demonstrated in Tabs 1.1 and 1.2.
On: Apr 05 2019.
Government Response. . Experience and Organizational Structure are evaluated separately and are not combined. No change as a result of this inquiry. Follow Section L and M as written or as updated with an official Amendment. On: Apr 17 2019
7928402 Contracting Section L 2.2.1 Proposal Volumes and Sections
Per Table 1 – Proposal Content and Tabs List, we are to provide tabs for "Tab 3.0 FACTOR 3 – Technical Approach to Sample CPFF Task Order Project" and "Tab 3.1 Sample Cost Reimbursable Fixed Fee – Completion Form (CPFF-CF) TO (Attachment L-6)." Please confirm that these tabs will have no content (they are just a tab/section dividers).
Government Response. . AMENDMENT 0001 removes all cost reimbursement contract type references. This solicitation will be FFP and FP-EPA only. No amendment needed to address this particular inquiry due to issued AMENDMENT 0001. On: Apr 17 2019
7928403 Contracting Section L 3.2.3 Tab 2.3 Key
Personnel
Please advise if the government has a preference of whether individual letters of commitment should be provided after each person's resume, or whether the government would rather see all resumes grouped together, and then all the letters of commitment grouped together.
Government Response. . Letters of Commitment are different from Key Personnel Resumes'. Do not group together. Submit as requested. No Amendment needed for this inquiry. On: Apr 17 2019 ****ANSWER REVISED PER THIS AMENDMENT 0003: The Key Personnel Letter of Commitment Can Follow the Key Personnel Resume (and not included in any page limitation). These Key Personnel Letters of Commitment may be different from Key Subcontractor Letters of Commitment.
7928404 Contracting Section L 3.2.3(h) Site
Superintendent
The requirements are "Minimum qualifications are at least five (5) years' experience as superintendent, managing multiple trades and subcontractor programs similar in size and complexity of the example projects." Please clarify if "example projects" is referring to the Sample Project PWS in Attachment L-6. If so, confirm that for this position, experience with the scope of the sample project will be evaluated more highly than the "depth and breadth of technical experience" as noted in Section M.
On: Apr 05 2019.
Government Response. . The sentence referenced is referring to the Sample Project PWS in Attachment L-6. Evaluation will be conducted as stated in Section M. No change as a result of this inquiry. On: Apr 30 2019
7928405 Contracting Section L 4.0 Volume 1 – Factor 4
– Past Performance Confidence Assessment
The requirement for past performance states "The offeror shall provide past performance information for each project submitted (up to 10) for FACTOR 1 as noted in this Section L. The title of the project shall be consistent with the project title in the experience description." Is the government requesting narrative information about past performance on each project in addition to the CPARs, PPQs, and performance recognition documents?
Government Response. . The Government is not requesting any past performance narrative - Only requesting as stated in Section L for FACTOR 4 - PPQs, CPARS, or other Performance Documents for each of the projects included in Factor 1. On: Apr 17 2019
7928406 Contracting Section L 4.0 Volume 1 – Factor 4
Are performance recognition documents limited to the projects submitted in Factor 1, or may other awards, etc.
be provided?
Government Response. . Performance recognition documents should be limited to the projects submitted in Factor 1, as these would be applicable to the type of work required under the contract;
whereas, other awards may not be related. On: Apr 17 2019
7928407 Contracting Section L 4.0 Volume 1 – Factor 4
Please consider eliminating the 3-year timeframe for performance recognition documents related to the projects submitted in Factor 1 since recency is defined as being completed within the past 8 years. A 3-year timeframe is reasonable for performance recognition documents not related to the projects in Factor 1.
On: Apr 05 2019.
Government Response. . The timeframe for performance recognition document related to the projects submitted in Factor 1 will be changed to coincide with the experience timeframe in a forthcoming Amendment. On: Apr 17 2019
7928408 Contracting Section L 5.1(a) Direct Labor
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The text references a Seed Task Order. Is this meant to be the Sample Task Order?
Government Response. . Section L, Paragraph 5.1, Tab 1.0 - Volume 2, Factor 5, (a) Direct Labor will be corrected to remove the word "seed" and insert the word "sample" via a forthcoming AMENDMENT. On: Apr 17 2019
7928409 Contracting Section L 5.1 Tab 1.0 – VOLUME
2, FACTOR 5 – CPFF Cost Proposal for Sample Task Order
The solicitation requires "backup documentation" for proposed subcontract costs and other direct costs such as materials, supplies, and equipment to be provided with the price proposal. Many subcontractors and vendors are not willing to provide pricing for a sample project that will not be awarded. If the sample project will not be awarded, may we include historical pricing, quotes from other proposals, or standard industry indexes (e.g., RS Means) as backup?
Government Response. . Section L. Paragraph 5.1, Tab 1.0 – VOLUME 2, FACTOR 5 – CPFF Cost Proposal for Sample Task Order has been revised as in issued AMENDMENT 0001. This information request has been removed per changes of AMENDMENT 0001. No additional amendment will occur as a result of this inquiry. On: Apr 17 2019
7928410 Contracting Section L Attachment L-8
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
If the Offeror is a joint venture, should the answers to questions 4 through 8, and copies of financial statements and credit reports be provided for the individual firms?
Government Response. . Yes. Copies of financial statements and credit reports shall be provided for the individual firms of a JV, as well as, the JV firm. On: May 01 2019
7928416 General Section 3.2.3 - Tab 2.3
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The solicitation states "The submitted resumes shall clearly display employer, proposed job title, education, states in which the individuals are registered, special qualifications and experience records showing title, specific duties, responsibilities, assignments, and the dates these were held within the last five (5) years." Could the USACE please clarify if offerors are permitted to show relevant project experience that is older than five years on personnel resumes? We respectfully request that there be no time restrictions on project experience on personnel resumes.
Government Response. . There can be beyond five (5) years experience on a resume; however, what's required on submitted resume(s) is what is requested - the experience records showing title, specific duties, responsibilities, assignments, and the dates these were held within the last five (5) is required to meet minimum required resume information. On: Apr 17 2019
7930236 General Section 2.1.3
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section 2.1.3 (page 338 of 371) references three volumes, including submitting Volume 1 and Volume 2 in the same binder. This appears incorrect. Please advise.
On: Apr 08 2019.
Government Response. . See answer from similar inquiry previously answered. This will be corrected via a forthcoming Amendment. On: Apr 17 2019
7930240 General Section 3.2.1
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section 3.2.1, Tab 2.1 Management Plan (page 341 of 371) states that the Management Plan shall be limited to three (3) double-sided pages. Please confirm this is the equivalent to six (6) single-sided pages.
(i) Government Response. . See answer from same inquiry. This will be corrected Attention should be brought to the FAR CLAUSE 52.204-4 where offerors and awardees are required to comply with "Printed or Copied Double-Sided on Post Consumer Fiber Content Paper" - See Clause Full Text in Section I of RFP. Single sided without being double-sided pages are not permitted. On: Apr 17 2019
****ANSWER CONFIRMED FOR ANY PAGE INQUIRY BY AMENDMENT 0003 RE-
CONFIRMING THAT NO CHANGE IS MADE TO WHAT IS IN RFP SECTION L, PARAGRAPH
2.1.1(ii): “…one side of the paper is one page; information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, each printed side of a fold-out page (11" x 14" or 11" x 17") will count as one page (Note: 11x17 equals “1 page”). Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are not included in the page limitation.” ****
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7930242 General Section C
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section C (page 28 of 341) states the Program Chemist shall have a minimum of six (6) years of professional experience. Section L (page 342 of 341) states the Program Chemist shall have a minimum of ten (10) years of professional experience. Please confirm which is accurate.
Government Response. . Section C, Paragraph 8.1.3 PROGRAM CHEMIST will be corrected to match what is stated in Section L via a forthcoming Amendment. On: Apr 17 2019
7930244 General Attachment L-6, Section 1.3
Attachment L-6, Section 1.3, Delivery Date (pdf page 445 of 490) states, "The delivery date for this contract ends on 29 May 2020. The contractor shall have all reporting documents finalized and submitted to the government by 30 April 2020. The contractor shall assume Notice To Proceed (NTP) will be provided by the government no later than 30 September 2019." Should this be corrected to say, "The delivery date for this contract ends on 29 May 2021. The contractor shall have all reporting documents finalized and submitted to the government by 30 April 2021. The contractor shall assume Notice To Proceed (NTP) will be provided by the government no later than 30 September 2019."
Government Response. . Corrections to Attachment L-6 Delivery Dates will be via a forthcoming
7930245 General Attachment L-6, Section 4.6.2
Attachment L-6, Section 4.6.2, Miscellaneous Abandoned Machinery (Project 17) (pdf page 460 of 490), second paragraph states "Contractor shall assume removal, sampling, and disposal of up to 25 pieces of abandoned machinery. Same location, third paragraph states: "Contractor shall collect one ISM sample for GRO, DRO, RRO, VOCs, SVOCs, PAH by SIM, metals, and PCBs under each piece of equipment for a total of 20 samples."
Please confirm that the contractor shall price collection of 20 rather than 25 ISM samples beneath the abandoned machinery.
Government Response. . Change sentence to read: "for a total of 25 samples." On: Apr 30 2019 Amendment 3 clarifies by stating: Contractor shall assume removal, sampling and disposal of fluids and batteries from all abandoned 20 pieces of machinery in Table 7.
7930932 Environmental 1 1 1
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
RFP SECTION 3.1.2, Tab 1.2 – Volume 1 Factor 1 - Project Experience Forms:
QUESTION: RFP Section M alone has 21 rating criteria requirements that: a) are overlapping; b) will not fit into a 2-page limit format that is responsive and wherein the government can easily check the boxes; and c) some Section M criteria can only or best be evaluated across the 10 featured projects and not at the individual project level (i.e., o Experience performing environmental services in all geographic regions of Alaska). Note: Section L states many of the same criteria but in a different way. Would the government consider consolidating these criteria to eliminate overlap and allow contractors to provide more responsive 2-page PD submissions?
Government Response. . The Federal Acquisition Regulation (FAR) states the required Uniform Contract Format (UFC) where Section L at the proposal requirements for submission and where Section M is how Section L proposals will be evaluated. The Section L and Section M will be reviewed -possible changes to page limitations may be made. Any changes will be included in an official
****ANSWER CONFIRMED FOR ANY PAGE INQUIRY BY AMENDMENT 0003 RE-
CONFIRMING THAT NO CHANGE IS MADE TO WHAT IS IN RFP SECTION L, PARAGRAPH
2.1.1(ii): “…one side of the paper is one page; information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, each printed side of a fold-out page (11" x 14" or 11" x 17") will count as one page (Note: 11x17 equals “1 page”). Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are not included in the page limitation.” ****
AMENDMENT 0003 specifically revises: SECTION L, Paragraph 3.1.2, Tab 1.2 – VOLUME 1, FACTOR 1 – Project Experience Forms – Provide information and references for the projects submitted for Tab 1.0 (maximum of 10 projects) to demonstrate the offeror’s or team member’s capability to successfully provide environmental services. If more than 10 projects are included, only the first 10 projects will be evaluated by the Government. Each project experience form is AMENDMENT 0003…limited to two (2) DOUBLE-SIDED 8.5” x 11” pages FOR TOTAL OF NO MORE THAN FOUR (4) PAGES per project for this Factor. Use the format provided in Section L, Attachment L-2. Page limitation is 20 pages total….AMENDMENT 0003.”
7931087 General Section 3.2.2
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section 3.2.2 (page 341 of 371) states that we are to include Letters of Commitment for each proposed key subcontractors (Attachment L-3). Does this mean there is no requirement for a Teaming Agreement? Please advise.
Government Response. . Question will be reviewed and any changes will be incorporated in a forthcoming Amendment. On: Apr 17 2019
***ANSWER REVISED PER THIS AMENDMENT 0003: “TEAMING AGREEMENTS are applicable if the offeror has a teaming agreement. It is up to the offeror to ensure the required, and applicable information is included in their proposal.”***
7931340 Contracting Sections L and M Tab 2.1
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
There are differences between the information required to be submitted as stated in Section L and the evaluation criteria in Section M for Tab 2.1 Management Plan. For example, Section M has several criteria that do not correspond to Section L requirements, e.g., Size and technical diversity of the local office; Organizational efficiency of the local office; Autonomy of the local office; Efficient and effective management of subcontracts;
Cooperation with client personnel after award; and Paid subcontractors/suppliers in a timely manner. Please confirm that our response should follow Section M rather than Section L.
Government Response. . Section L is what is required to be submitted with a proposal at a minimum.
Section M states how the Section L proposal will be evaluated. Section M guides offerors how Section L items will be evaluated. No change will be made as a result of this inquiry. Section L and Section M will be reviewed but no change now. On: Apr 17 2019
***ANSWER TO THIS INQUIRY IS FINAL PER AMENDMENT 0002 AS FOLLOWS: “No changes to Section L and/or Section M for FACTOR 1 are applicable. Please note that the SECTION L is WHAT THE OFFEROR SHALL SUBMIT; whereas, the SECTION M is how the OFFEROR SUBMITTAL will be evaluated. Both SECTIONS should be reviewed by offerors but should not match in order to ensure there is the ability for the Government to determine best value proposals by use of differentiating evaluation criteria. No change will be made as a result of this inquiry.”***
7931341 Contracting Section L 3.2.2 Tab 2.2
Organizational Structure of Proposed Team
Tab 2.2 Organizational Structure of Proposed Team appears to be asking for three different organizational structures: (1) the teaming arrangement (prime, key subcontractors), (2) key personnel, and (3) organization of the local office. Please confirm that all three organizational structures must be shown on one (1) 11" x 17" page.
Government Response. . The Key Personnel and any teaming arrangement/key subcontractors and the prime offeror's organization structure should indicate the interconnections and "big picture" on one page - the Government is not looking to receive multiple, separate organizational structures. Refer to Section L, Paragraph 3.2.2 Tab 2.2 – VOLUME 1, FACTOR 2 – Organizational Structure of Proposed
Team; and Section M TAB 2.2 (VOLUME 1, FACTOR 2) – Organizational Structure of Proposed Team. On: Apr 30 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7931343 Environmental Attachment L-6 PWS for Sample
CPFF-CF Task Order Project, para 1.3
The sample project requires completion in 8 months with much of the field work during the winter season. Based upon this period of performance, please confirm the expectation that the contractor will be performing field work during the winter season where challenges and risks to working outside the construction season will significantly drive up costs.
Government Response. . The sample project schedule will be revised per answer to another inquiry.
On: Apr 17 2019
7931344 Environmental Attachment L-6 PWS for Sample
3.8
Are the relief trips (2) in addition to providing mobilization and demobilization between Dutch Harbor and Fort Glenn for the QAR?
Government Response. . Assume for the sample FFP project that the relief trips are from Dutch Harbor to Fort Glenn. On: Apr 30 2019
***ANSWER REVISED PER AMENDMENT 0003: “Assume for the sample FFP project that the two (2) relief trips are from Dutch Harbor to Fort Glenn for the QAR and are in addition to the mobilization and demobilization.”***
7931346 Environmental Attachment L-6 PWS for Sample
3.3, 4.2.2, 4.3
A site visit is mentioned in passing in Sections 3.3, 4.2.2, and 4.3, but no detail is provided in the PWS. Should a site visit be priced as part of CLIN 2, and if so, are there any requirements for who will attend?
Government Response. . There will not be a site visit. This is a sample project. Any reference to a site visit will be removed in a forthcoming Amendment. On: Apr 17 2019
****THIS ANSWER REVISED AND MADE FINAL IN AMENDMENT 0003 INCORPORATION
AS FOLLOWS: Assume a site visit for pricing purposes for SAMPLE FFP PROJECT; however, an actual physical site visit will not be accomplished for this SAMPLE Firm-Fixed Price (FFP) Project.****
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7931348 Environmental Attachment L-6 PWS for Sample
6.6
Please confirm assumed review time of 20 work days/30 calendar days for USACE and regulatory agency.
Government Response. . Assume for the sample FFP project that the review time for USACE and regulators is 20 working days/30 calendar days. Remember that AMENDMENT 0001 removed the CPFF Sample Project. There is only the Sample FFP Project. On: Apr 30 2019
7931349 Environmental Attachment L-6 PWS for Sample
6.8
Section 6.8 includes a description of unit price payment conditions (including the requirement for a scale on-site).
However, the cost estimate specifies payment for the field work task as "JOB". Please clarify this discrepancy.
Government Response. . This question is overcome by Amendment 0001. The FFP Sample Project PWS Attachment L-6 states, "Payments will be made at the contract unit price - JOB is the Unit of Measure. On: Apr 30 2019
7931350 Environmental Attachment L-6 PWS for Sample
4.2
Section 4.2 includes allowances for 4 meetings but Section 6.6 indicates there are 6 meetings. Please clarify.
Government Response. . Any reference to more than 4 meetings shall be removed to coincide and indicate 4 meetings total. On: Apr 30 2019
7931352 Environmental Attachment L-6 PWS for Sample
4.8.1 and 6.6
Task 8 requires the preparation of a Removal Action Report but Section 6.6 describes the report as an RI report.
Please clarify.
Government Response. . The report required is a Removal Action Report. Any reference to "RI" report in the Sample FFP Project Attachment L-6 is removed and should be replaced with Removal Action Report. On: Apr 30 2019
7931354 Environmental Attachment L-6 PWS for Sample
4.8, 6.5, 6.6
Sections 6.5 and 6.6 indicate there are two (2) reports required for submittal. There are four reports described in Task 8. Assuming that two of the four reports required in Section 6.5 and 6.6 are the DQCR and CPSMR, can we assume the other two reports required are the RAR and the monthly exposure hours report?
Government Response. . Where applicable, change the Sample FFP Project PWS to include only reports being submitted as the DCQRs, the CPSMRs and the Removal Action report. Remove the "(2)" from the Submittal Type Table, and Submittal Schedule Table. On: Apr 30 2019
7931356 Environmental
CPFF-CF Task Order Project
Will the government require the contractor to provide an emergency medivac aircraft onsite in the event an emergency medical need arises during field operations?
Government Response. . No, the Government will NOT require the contractor to provide an emergency medivac aircraft onsite in the event an emergency medical need arises during field operations. On: Apr 30 2019
7931357 Environmental
Will the government require the contractor to provide a dedicated medical infirmary on site attended by a full-time Emergency Medical Technician (EMT III) during field operations?
On: Apr 08 2019.
Government Response. . Yes, the Government requires the contractor to provide a dedicated medical infirmary on site attended by a full-time Emergency Medical Technician (EMT III) during field operations. On: May 01 2019
7931358 Environmental
Will charter aircraft flights for government personnel to/from Fort Glenn require twin engines and two qualified pilots and be DoD Commercial Review Board-approved as required under Public Law 99-661 and DoD Directive 4500.53?
Government Response. . Assume that charter aircraft flights for Government personnel to/from Fort Glenn will require twin engines and two (2) qualified pilots and be DoD Commercial Review Board-approved as required under Public Law 99-661 and DoD Directive 4500.53 where applicable for the Sample FFP Project. On: Apr 30 2019
7931359 Contracting Section B Labor Rates
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section B indicates that we are to use a Labor Rate Calculation Chart from Section J in support of listed rates.
With regard to the Labor Rate Calculation Chart:
(1) Is the intent to show how each contractor's loaded rate is built (i.e., how indirect rate structure is applied to the unloaded hourly rate) for each listed key and non-key labor classification? This seems to align with the direction given in 5.3 of Section L.
(2) A Labor Rate Calculation Chart was not provided with the RFP. Can the contractor develop their own Labor Rate Calculation Chart that shows hour our indirect rate structure is applied to each key and non-key position, especially since each firms OH rate structure is different?
Government Response. . What will be required for labor rate other than cost or pricing data information (including any referenced Section J Labor Chart) will be clarified and issued with Amendment 0003. This is a firm-fixed price services solicitation that will be review key personnel labor rates, G&A, OH, and Escalation Rates. On: May 01 2019
****SEE AMENDMENT 0003 CHANGES REMOVING ANY WORKSHEET FOR
SUMBITTAL****
7932942 General Tab 5.1(c)
Regarding paragraph 5.1(c): "Offerors shall submit plans in accordance with FAR Clause 52.222-46 EVALUATION OF COMPENSATION FOR PROFESSIONAL EMPLOYEES for professional employee categories as defined within Clause." Please clarify the requirements for this submittal. Does the government require a compensation plan detailing all professional staff and their salaries?
On: Apr 09 2019.
Government Response. . The FAR Clause 52.222-46 EVALUATION OF COMPENSATION FOR PROFESSIONAL EMPLOYEES is not applicable to this solicitation and will be deleted via forthcoming AMENDMENT 0003. On: May 01 2019
7932954 General Tab 4.0
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Regarding 5.1 Tab 4.0 (d):"Offerors shall include a copy of the required policy in accordance with FAR Clause 52.237-10 IDENTIFICATION OF UNCOMPENSATED OVERTIME". Please clarify the requirements for this submittal. Does the government require a compensation plan detailing overtime policies?
Government Response. . This requirement has been removed due to the changes addressed in AMENDMENT 0001, issued 09 APRIL 2019 at www.fbo.gov. On: Apr 17 2019
7932965 General Tab 3.1 Sample Cost Reimbursable Fixed
Fee Task Order
Regarding Tab 3.1, page limitation is stated as "Limit the information in each sub-tab to two (2) pages or less."
There are 5 tabs, therefore, a maximum of 10 pages. Would the government instead allow the page limitation to be stated as: "Limit the information in this factor to 10 pages" so we can use more or less than two pages for each tab, as long as the total is 10 pages or less?
Government Response. . This inquiry appears to be overcome by Amendment 0001. On: Apr 30
7933027 General Attachment L-6 PWS: Section
4.6.1
Sample Project PWS Project 16 - Please clarify if only transformers require removal and disposal, or if other items listed in Table 5 (e.g. poles, stumps, guy lines, etc.) also require removal and disposal.
Government Response. . Only transformers require removal and disposal On: May 01 2019
Current Request Status: Request Closed
Information for this report is procurement sensitive.
7933029 General
4.6.2
PWS Project 17 - Please clarify if only fluids and batteries from the abandoned machinery listed in Table 7 require removal and disposal, or if the abandoned machinery also requires removal and disposal.
Government Response. . Assume that only transformers require removal for the Sample FFP Project.
On: Apr 30 2019
7933031 General
4.6.2
Can the USACE please provide a picture of the drill rig at Ashishik Point listed in Table 7?
Government Response. . No picture required for the Sample FFP Project (also no picture has been located to provide). On: Apr 30 2019
7933570 Environmental
1. Section B Base Period FFP Ceiling
Fully Burdened Hourly Rates.
Instructions at the top of the table requires Offerors to "provide labor rate calculation chart from Section J in support of listed rates". Review of the attachments in Section J did not reveal a labor rate calculation chart. Please clarify.
On: Apr 10 2019.
Government Response. . Labor rate chart format included in next Amendment 0003 anticipated to be issued 01 May 2019. On: Apr 30 2019
7933572 Environmental Section C 8.1
Each labor category with the exception of Site Superintendent state how many resumes the contractor can provide. Can we assume we are only allowed to provide one Site Superintendent?
Government Response. . For Site Superintendent provide only one (1) resume. On: Apr 30 2019
Information for this report is procurement sensitive.
7933890 Environmental Table 1
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Table 1 requests an Escalation Factor Over Previous Year Rates; however, Table 4 and Table 7 do not. Are the "NA" in error? Please clarify the escalation requirements.
Government Response. . The Base Period of three (3) years is the only place where "escalation rate" for Year 2 and 3 apply. Option Year rates are proposed without needing to specify any escalation rate.
On: Apr 30 2019
7934981 Environmental Proposal Submission
Requirements
Please clarify the discrepancy in paragraphs 2.1.3 Number of Copies and 2.2.2 Proposal Volumes and Sections.
Section 2.1.3 instructs offerors to submit Volumes 1 and 2 in the same binder and submit Volume 3, Offer, in a separate binder. Section 2.2.1 instructs offerors to submit the proposal in two volumes: Volume 1 (Factor 1 through Factor 4) and Volume 2, Factor 5 and Required Pre-Award Information. No content for Volume 3 is specified. Please clarify which instruction you would like us to follow.
Government Response. . Volume 3 verbiage will be removed. There are only two (2) Volumes required. Any changes necessary will be included in an official forthcoming Amendment. On: Apr 17
7934982 Environmental
Will the government accept proposals that include Volumes 1 and 2 in separate binders? Due to the volume of pages that could be required for Volume 2, included both volumes in a single binder may be difficult or impossible.
Government Response. . This is a Total Small Business Set-Aside acquisition. The Volumes are required to be in separate binders. On: Apr 17 2019
7934983 Environmental
On page 341 of the RFP, it states that 3.2.1, Tab 2.1 Volume 1, Factor 2, Management Plan should be no longer than 3 double-sided pages. Is that the only section that is to be double-sided, or will other sections of the proposal need to be double-sided? If so, which other sections should be double-sided?
Government Response. . Any page can be double-sided. On: Apr 30 2019 THIS ANSWER CHANGED AS NOTED BELOW AND FINAL IN AMENDMENT 0003. On: Apr 30 2019
AMENDMENT 0003 clarifies and confirms what is already in SECTION L on Pages – Double- Sided equals 2 pages. ****ANSWER CONFIRMED FOR ANY PAGE INQUIRY BY
AMENDMENT 0003 RE-CONFIRMING THAT NO CHANGE IS MADE TO WHAT IS IN RFP
SECTION L, PARAGRAPH 2.1.1(ii): “…one side of the paper is one page; information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, each printed side of a fold-out page (11" x 14" or 11" x 17") will count as one page (Note: 11x17 equals “1 page”). Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are not included in the page limitation.” ****Comply with FAR Clause 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper.****
7934984 Environmental
For the required information in 4.0 Volume 1, Factor 4 – Past Performance Confidence Assessment, as the projects in 3.1, Tab 1.0, Volume 1, Factor 1 – Experience can be ongoing (at least 50% complete), will the government accept interim CPARS for projects that are not yet complete at the time of proposal submission?
Government Response. . For Tab 4.0 Volume 1, Factor 4 – Past Performance Confidence Assessment, it states "Experience can be ongoing (at least 50% complete)." The Government will accept interim CPARS for projects (at least 50% complete) at time of proposal submission. On: Apr 30
7934985 Environmental
Given the large size of our JV Partner and the fact that they currently hold thousands of contracts and are engaged in a substantial number of task orders, would it be sufficient to the government to provide a list of current commitments pertinent to the scope of work for this ERS contract in response to Attachment L-8, question # 4?
On: Apr 10 2019.
Government Response. . Any offeror submitting as a JV shall provide an Attachment L-8 for each JV firm and for the JV company as well. On: Apr 30 2019
7934986 Environmental
Given the large size of our JV Partner and the fact that they currently hold thousands of contracts, would it be sufficient to the government to provide a list of relevant contracts awarded in the last 3 months valued at $1 million or more and within the last 3 years valued at $3 million or more in response to Attachment L-8, question #5?
Government Response. . Each offeror submitting as a JV shall provide an Attachment L-8 for each JV firm and for the JV itself. On: Apr 30 2019
7934990 Environmental RFP Clauses
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The RFP includes FAR clause 52.211-11, Liquidated Damages – Supplies, Services or Research and Development, to be specified when applicable. What is the nature of work that liquidated damages may be applicable?
Government Response. . The RFP includes FAR clause 52.211-11, Liquidated Damages – Supplies, Services or Research and Development, to be specified when applicable. This is exactly what it means -when a actual task order is issued the CLAUSE will contain the liquidated damages amount for that particular task order. The SAMPLE FFP PROJECT Task does not have liquidated damages because it is SAMPLE. On: Apr 30 2019
7934996…