TE_G_DID_A006_Test_Validation_Rpts.doc

DOC document 64 KB Posted

Attached to
Test Support Services
Solicitation number
W91151-12-R-0037
Issued by

About this file

Technical Exhibit G

View the file

Other files

File Type Posted
W91151-12-R-0037_Amendment_0003.doc DOC document
W91151-12-R-0037_Amendment_0002.doc DOC document
W91151-12-R-0037_Ammendment_0001.doc DOC document
TE_Z_USAOTC_SOP_G4_3_Uniforms2.pdf PDF
Attch_16_Base_Operations.pdf PDF
Attch_15_Test_Task_MultiRqmt.pdf PDF
TE_A_CDRL_Page_4of4.pdf PDF
TE_A_CDRL_Page_4of4.pdf PDF
TE_Y_DID_A007_Sensitive_Items_Rpts.doc DOC document
Attch_6_Security_Clearances.doc DOC document
W91151-12-R-0037_Final_RFP.doc DOC document
Pre-Solicitation_Conference_Sign_In_Sheet.pdf PDF
Attch_3a_GFP.xls XLS spreadsheet
Attch_6_Security_Clearances.doc DOC document
TE_J_DID_A009_Technical_Manuals.doc DOC document
TE_F_DID_A005_Emergency_Contact.doc DOC document
TE_N_DD_Form_254.pdf PDF
W91151-12-R-0037_Final_DRFP.pdf PDF
TE_A_CDRL_Page_1of3.pdf PDF
Attch_8_Task_MultiRqmt.doc DOC document
TE_A_CDRL_Page_3of3.pdf PDF
TE_M_DID_A012_HAZMAT.doc DOC document
Attch_10_Techn_Base_Sample.doc DOC document
Attch_1_OTC_MAP.pdf PDF
Attch_11_Airborne_Tech_Svc.doc DOC document
TE_K_DID_A010_Software_Doc.doc DOC document
TE_E_DID_A004_Weekly_Report.doc DOC document
Attch_12_Airborne_Data.doc DOC document
TE_B_DID_A001_Monthly_Report.doc DOC document
TE_Q_USAOTC_Policy_CG_9_CCIR.pdf PDF
TE_L_DID_A011_Personnel_Status.doc DOC document
Attch_13_HAZMAT.xls XLS spreadsheet
Attch_5_Historic.xls XLS spreadsheet
TE_W_Acronym_List.doc DOC document
Attch_2_GFF.pdf PDF
Attch_3b_GFSoftware.xls XLS spreadsheet
TE_T_USAOTC_Policy_SOP_Safety.pdf PDF
TE_U_USAOTC_SOP_G4_7_Fire_Prev.pdf PDF
TE_P_Wage_Determinations.doc DOC document
TE_C_DID_A002_Quarterly_Briefing.doc DOC document
Attch_4_Inst_Catalog.doc DOC document
Attch_7_Base_Operations.DOC DOC document
Attch_9_Task_Limited_Req.doc DOC document
TE_H_DID_A008_Engineering_Reports.doc DOC document
TE_V_USAOTC_SOP_G4_6_Env.pdf PDF
TE_D_DID_A003_TIP.doc DOC document
TE_A_CDRL_Page_2of3.pdf PDF
TE_S_USAOTC_Policy_G4_3_Loaned.pdf PDF
TE_R_USAOTC_Policy_G6_1_IT.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Form Approved

OMB NO. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503.

1. TITLE

A006, Test Instrumentation and Validation Reports

2. IDENTIFICATION NUMBER

3. DESCRIPTION/PURPOSE

To prescribe minimum requirements for contractor prepared test plans, test procedures, and test reports for test instrumentation development and validation. Contractor shall provide general and administrative support for sustaining engineering capabilities.

4. APPROVAL DATE (YYMMDD)

120821

5. OFFICE OF PRIMARY RESPONSIBILITY (OPR)

USAOTC G4

6a. DTIC APPLICABLE

6b. GIDEP APPLICABLE

7. APPLICATION/INTERRELATIONSHIP

This Data Item Description is applicable to all types of testing performed by the contractor to demonstrate conformance to Task Authorization Requests (TARs) requiring instrumentation acquisition or development. Types of test included are: engineering evaluations, prototype qualifications, first article, systems integration, software verification, delivery acceptance, and quality conformance. The resulting documents are subject to Government approval before being accepted as a deliverable.

8. APPROVAL LIMITATION

9a. APPLICABLE FORMS

9b. AMSC NUMBER

10. PREPARATION INSTRUCTIONS

10.1 The contractor shall provide test plans, procedures, and reports that meet the requirements of the TAR and paragraph 10.4 below. Contractor format is acceptable.

10.2 Only those portions of paragraph 10.4 as specified in the TAR are required. The contractor shall use his best judgment in determining the applicability of each submittal.

10.3 Definitions. Applicable to this data item only.

f. Engineering evaluation – exploratory type tests conducted to measure and record the performance characteristics of hardware, software, or systems.

g. Prototype qualification – tests conducted on prototype equipment to demonstrate conformance of the design to requirements of the work statement.

h. First article – tests conducted on equipment, produced using production tooling and processes, prior to continuing production, to demonstrate conformance of the design and production methods to requirements.

i. Software verification – tests conducted on computer software and firmware, prior to system integration, to verify requirements in the work statement.

j. System integration – test conducted on systems, consisting of two or more items of hardware which have undergone separate testing, or consisting of both hardware and software, to demonstrate conformance of the system to the requirements of the work statement.

k. Quality conformance – inspections and tests, conducted at a manufacturer or sub-contractor facility, to verify and demonstrate conformance with the work statement.

l. Delivery acceptance – tests conducted after delivery to the Government facility to assure that the item is free from shipping damage and to verify function and safe operating characteristics.

m. Verification Validation and Accreditation (VVA) – documentation needed to gain ATEC accreditation that the instrumentation provides and accurate representation of the real world and that the information collected is accurate and usable.

10.4 Test plans, procedures and reports, when required by the work statement, shall include, but are not limited by the following items and topics:

f. Test Plans/Procedures/Reports: All documents shall include the following:

(9) Title Page

(10) Table of Contents

(11) List of Illustrations

(12) Introduction/Purpose

(13) Test dates and location

(14) References

(15) Test Procedures

(16) Test Results

(17) Conclusion

(18) Recommendations

11. DISTRIBUTION STATEMENT

DISTRIBUTION STATEMENT A: Approved for public release; distribution unlimited.

DATA ITEM DESCRIPTION
Form Approved

OMB NO. 0704-0188

10.5 Test plans… (continued)

f. Test Plan. The test plan describes what the contractor intends to do to fulfill test requirements and in addition to “10.4 a” above, all test plans shall include:

(19) Basic test philosophy and approach

(20) Government furnished property (GFP), if required.

(21) Acceptance/rejection criteria

g. Test Plan (software). In addition to “10.4 b” above, all test plans involving software shall include:

(22) Interface requirements - This portion of the plan shall describe all interface conditions which must be satisfied. It shall include interface data for the following:

(a) Hardware I/O (Input/Output)

(b) Executive program

(c) Other supporting software

(d) Errors

(23) Software test environment

(24) Test identification

(25) Timing requirements

(26) Volume requirements (data)

(27) Input data format

h. Test Procedures. The test procedure describes in detail how the examinations and tests are to be performed and in addition to “10.4 a” above, all test procedures shall include:

(28) Scope

(29) Technical approach

(30) Functional block diagram of test set up

(31) Identification of test equipment required

(32) Number of test units or lot size and sampling plan

(33) Step-by-step procedures to be followed referenced to the particular requirement in the work statement.

(34) Data reduction and analysis

(35) Acceptance/rejection criteria

(36) Definitions and abbreviations

(37) Sample data sheets

(38) List of required GFP

(39) Planned test to be subcontracted

i. Test Procedures (software): In addition to “10.4 d” above, all test procedures involving software shall include:

(40) A full description of the procedures, giving particular attention to the following:

(a) Describe the function tested.

(b) Arrange test sequence for optimum performance.

(c) Provide detailed step-by-step procedures required to obtain desired results.

(d) Identify test results expected and provide for recording the actual results obtained.

(41) A description of all operating procedures including the following:

(a) Initial system set up and pre-operating procedures

(b) Normal operation modes

(c) Program completion notes

(d) Error conditions (and operator action, if applicable)

(e) Messages (and operator action, if applicable)

(f) Halts (and restart procedures, if applicable)

j. Test Report: The test report shall, in addition to “10.4 a” above include: [Note: Sections (1) through (6) shall be included in the main body of the report. Section (7) and (8) shall be included as an appendix].

(42) Executive Summary

(43) Description of test facility and conduct of the test including a description of how the test article was operated during the test. Brief description of test article.

(44) Manpower requirements

(45) Identification of test equipment and its calibration status

(46) Summary of tests results. Where these tests were to show compliance with a given statement of work and/or specification

(47) Functional block diagram of test set up

DATA ITEM DESCRIPTION
Form Approved

OMB NO. 0704-0188

10.6 Test Report… (continued)

(48) Deviation from test conditions. If value of data has been compromised due to test conditions, the reason and implication shall be stated.

(49) Data Collection and reduction

(50) Recorded test data or logs as appropriate, including instrument readings, correction factors, and reduced results presented in tabular or graphic form.

(51) Test log

(52) Certification that the test results are authentic, accurate, current, and in accordance with approved test procedures.

g. Recorded test data or logs as appropriate, including instrument readings, correction factors, and reduced results presented in tabular or graphic form.

h. Test Report Addendum: This report used to update the test report when design changes made and test are performed after the test report has been published. The updated information shall be related to the previous data in the test report.

i. Interim Test Report. Interim reports are prepared when reporting of test status is required during the period of the test.

(53) Initial interim reports shall contain the same contents as for test reports, except that the results and conclusions will be preliminary.

(54) Subsequent interim reports need not include descriptive data provided in the initial report, but only changes thereto.

10.7 Explanation of terms in paragraph 10.4: Self-explanatory terms are not listed. Other terms are listed to aid the contractor in understanding the requirement. Items listed under each term are to be included as applicable.

f. Basic test philosophy and approach.

(55) Facility requirements

(56) Test preparation plans

(57) Key personnel responsibilities

(58) Sub-contracting plan

(59) Description of test content and conduct

(60) Documentation requirement

(61) Logistics support

(62) Applicable MIL-STDs

g. Schedule of events.

(63) Network diagrams

(64) Gantt charts

h. Government Furnished Property (GFP)

(65) Describe contractor plan for maintenance and repair.

(66) Describe security measures to be taken for safeguarding.

(67) Describe accountability procedures.

i. General test approach.

(68) Facility requirements

(69) General description of the test content and conduct (i.e., will environmental test be conducted? Will test article be operated during the test? etc.)

j. Data reduction and analysis.

(70) Types of data to be recorded.

(71) Data reduction process and time test.

(72) Description of method for data reduction and analysis.

k. Subcontracting.

(73) Show which portions of the test are to be performed by the prime contractor.

(74) Show which portions of the test are to be performed by the sub-contractor(s).

(75) Identify sub-contractors by name and address.

l. Accept/reject criteria.

(76) Statements of test objectives are sufficient for exploratory type tests.

(77) Include criteria to be evaluated with pass/fail levels.

(78) Include exceptions or deviations (good or bad) and resulting impact.

DD Form 1664, APR 89 Previous editions are obsolete DD Form 1664, APR 89 Previous editions are obsolete

File details come from the government source that posted it. Updated .