IEWTPT Quality Assurance Surveillance Plan (New)

View the file

Other files for this federal contract opportunity

Other files attached to Intelligence & Electronic Warfare Tactical Proficiency Trainer (IEWTPT) Draft Solicitation Update, newest first.
File Type Posted
Attachment_10_Data_Item_Form.doc DOC document
Attachment_4_Question_and_Comment_Form.docx DOCX document
Attachment_1_SOW_03FEB16.docx DOCX document
Attachment_9_Govt_WBS.docx DOCX document
Attachment_7_Preaward_Survey_of_Accounting_System.doc DOC document
IEWTPT_Responses_10FEB16.pdf PDF
Exhibits_A-C.pdf PDF
Attachment_3_SSS_Distro_Agreement.docx DOCX document
IEWTPT_PSC_13JAN16.pdf PDF
Attachment_12_DD254.pdf PDF
Attachment_5_Evaluated_Price.xlsx XLSX spreadsheet
Attachment_8_Performance_Risk_Questoinnaire.doc DOC document
W900KK-16-R-0005_Draft_Solicitation_10FEB16.doc DOC document
Attachment_6_Cost_Adequacy.xlsx XLSX spreadsheet
IEWTPT_PSC_Attendees_13JAN16.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE SURVEILLANCE PLAN

XX August 2015 for the Intelligence and Electronic Warfare Tactical Proficiency Trainer (IEWTPT) Contract Number: W900KK-15-R-0010 Contractor’s name: TDB

1. PURPOSE.

This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:

· What will be monitored

· How monitoring will take place

· Who will conduct the monitoring

· How monitoring efforts and results will be documented

This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance. In addition, the QASP should recognize that unforeseen and uncontrollable situations may occur.

This QASP is a “living document” and the Government may review and revise it on a regular basis. However, the Government shall coordinate changes with the Contractor. Updates shall ensure that the QASP remains a valid, useful, and enforceable document. Copies of the original QASP and revisions shall be provided to the Contractor and Government officials implementing surveillance activities.

The following FAR clauses apply based on contract type:

52.246-2 Inspection of Supplies – Fixed Price 52.246-3 Inspection of Supplies - Cost-Reimbursement 52.246-6 Inspection – Time-and-Material and Labor-Hour 52.246-8 Inspection of Research and Development – Cost Reimbursement

2. GOVERNMENT ROLES AND RESPONSIBILITIES.

The following personnel shall oversee and coordinate surveillance activities.

a. Contracting Officer (KO) - The KO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The KO shall also assure that the Contractor receives impartial, fair, and equitable treatment under this contract. The KO is ultimately responsible for the final determination of the adequacy of the Contractor’s performance.

Assigned KO: Glenda Torres Organization or Agency: Army Contracting Command - Orlando Telephone: (407) 380-4413 Email: glenda.m.torres.civ@mail.mil

b. Contract Specialist (KS) - The KS acts as an acquisition consultant and serves as liaison between the requesting program office, the Contractor, and the supporting contracting office.

Assigned KS: Aurora Ramirez Organization or Agency: Army Contracting Command - Orlando Telephone: 407-208-3495 Email: aurora.i.ramirez2.civ@mail.mil

c. Contracting Officer’s Representative (COR) - The COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance. The COR shall keep a quality assurance file. At the conclusion of the contract or when requested by the KO, the COR shall provide documentation to the KO. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf. The contractor shall refer any changes they deem may affect contract price, terms, or conditions to the KO for action.

Assigned COR: TBD Organization or Agency: PEO STRI, PM ITTS-PdM STS Telephone: 407-384- Email: TBD

3. CONTRACTOR REPRESENTATIVES:

The following employees of the Contractor serve as the Contractor’s Program Manager and Task Manager for this contract.

a. Contract Coordinator – TBD Telephone: TBD Email:

b. Task Manager – TBD Telephone: TBD

PHONE (AFTER HOURS): TBD

Email: TBD

c. Program Manager – TBD Telephone: TBD Email:

d. Project Engineer – TBD Telephone: TBD Email: TBD

4. PERFORMANCE STANDARDS.

Performance standards define desired services. The Government performs surveillance to determine if the contractor exceeds, meets or does not meet these standards.

The IEWTPT Statement of Work (SOW) (PEO-STRI-XX-XXXX), dated XX July 2015 and the IEWTPT Performance Specification (PRF-PT-XXXX), dated XX July 2015 delineate the tasks required by the Government. These tasks shall be subject to the following performance standards listed in the table below. When referenced SOW paragraphs contain sub-paragraphs, all sub-paragraphs are subject to inspection/evaluation unless specifically excepted.

Task
Performance Standard
Method of Surveillance
Frequency
SOW Paragraph -3.1 Program Management
Manage program to achieve technical, budget, and schedule objectives.
A, D, E
Weekly meetings and monthly reports

SOW Paragraph -

3.1.2 Integrated Master Schedule (IMS)

Manage and track schedule status and critical events. Manage critical path tasks to eliminate or reduce schedule risks.
B, D, E
Weekly meetings and monthly reports

SOW Paragraph -

3.1.3 Financial Management

Manage project within the available budget. Evaluate program activities to identify opportunities to increase efficiencies and reduce costs.
D, E, F
Weekly meetings and monthly reports
SOW Paragraph 3.1.4 Earned Value Management (EVM)
Establish and maintain an EVM program in compliance with American National Standards Institute/Electronic Industries Alliance Standard 748 to manage and track cost, schedule, and performance of the Cost portions of the contract within budget.
D, E, F
Monthly reports
SOW Paragraph 3.1.8 Configuration Management
Establish and maintain effective configuration management processes and procedures to control the allocated and product IEWTPT software and hardware baselines, system configuration items, and project artifacts. Establish and maintain a systematic and measurable configuration change management process.
D, E, F
Monthly reports

SOW Paragraph -

3.1.9 Risk Management

Prepare, implement, and maintain Risk Management Plan (RMP) that identifies, analyzes, and mitigates and tracks program risks. Develop, submit and maintain an RMP as part of the Systems Engineering Management Plan (SEMP).
A, D, E
Monthly meetings
SOW Paragraph 3.1.11 Sensitive Compartmented Information Facility (SCIF)
Maintain a certified SCIF IAW applicable regulations and a sufficient number of properly cleared personnel to support the IEWTPT effort.
A, D, E
Quarterly reports

SOW Paragraphs 3.1.11.1 Cybersecurity Accreditation; 3.1.12.8 Cybersecurity Information Technology (IT) Training; 3.2.6 Cybersecurity

Establish and maintain the necessary cybersecurity posture of the IEWTPT effort (networks, systems, subsystems) IAW applicable instructions, directives, and regulations. Comply with applicable National Security Directives and DoD-Army security accreditation policies and instructions consistent with IEWTPT operations and/ or operational environment. Develop and field accreditable systems. Support program accreditation activities. Comply with policies and procedures for obtaining required software application Certificates of Networthiness. Establish and maintain Host-based Security System (HBSS) compatibility and compliance for IEWTPT systems. Ensure all personnel are properly trained and certified and training/certification is properly documented.
C, D, E
Weekly meetings, Monthly reports

SOW Paragraphs 3.1.12 AntiTerrorism (AT)/Operations Security (OPSEC); 3.1.12.3 AT Awareness Training for US Based Contractor Personnel Traveling Overseas;

3.1.12.4 iWATCH Training;

3.1.12.7 Requirement for OPSEC Training; 3.1.12.9 IA/IT Certification

Ensure all prime and subcontractor personnel are properly trained and/or certified as outlined in the sub-paragraphs at all times. Provide proof of training/certification to COR as identified in the sub-paragraphs.
B, E, F
Quarterly reports
SOW Paragraph 3.2 Systems Engineering
Implement and maintain appropriate Systems Engineering processes to support the IEWTPT hardware and software IAW applicable instructions, directives, and regulations. Update and maintain the SEMP. Develop, produce and maintain accurate Product Definition Data (PDD).
A, B, D, E,
Bi-weekly meetings and Monthly reports
SOW Paragraph 3.2.4 Hardware and Software Integration
Deliver fully-integrated, fully- functional, and accreditable systems and support systems that performs and operates in accordance with applicable specifications to the Government by the specified delivery date(s). Demonstrate an Army Operating Environment Data Center/Cloud (COE DC)-compliant training capability in an operational test environment within 24 months of contract award. Deliver a cloud-optimized training capability within 24 months of the operational test demonstration.
B, D, E
Monthly meetings and reports
SOW Paragraph 3.2.4.2 Modification/ System Upgrades
Ensure the IEWTPT capability maintains concurrency with existing and evolving complementary systems operational capabilities through modification, obsolescence management and Pre-Planned Product Improvement (P3I).
C, D
Quarterly meetings
SOW Paragraph 3.3 Logistics
Establish quantitative and qualitative supportability design guidelines. Coordinate with existing life cycle support contractors. Develop initial fielding plans for the system and verify that the maintenance actions and support structure are aligned with the maintenance concept. Effectively manage Government Furnished Property (GFP), Government Furnished Equipment (GFE), and Government Furnished Software (GFS).
C
Quarterly inventories
SOW Paragraph 3.3.2 Training Products
Develop and implement training and training products for operators and maintainers IAW TRADOC Regulation 350-70, Systems Approach to Training.
A, C
Semi-annual inspection
SOW Paragraph 3.5 Operational Site Activation
Coordinate and conduct all activities required to successfully field fully operational IEWTPT systems to designated locations when directed by the Government.
A, D, E
Monthly meetings and reports
SOW Paragraph 3.7 System Sustainment
Provide support for those functional and technical capabilities, processes, ancillary activities, and logistical support the Reliability, Availability, and Maintainability (RAM) goals of the IEWTPT program. Provide transition support for the Government-designated follow-on organization during the final 12 months of the contract period of performance.
A, D, E
Monthly meetings and reports

Notes:

(1) Frequency can be adjusted based on contractor performance to ensure risk is adequately managed and mitigated.

(2) The Government technical team consists of subject matter expertise from the U.S. Army Intelligence Center of Excellence (USAICoE), PEO-STRI PM ITTS PdM STS, and Program Executive Office, Intelligence, Electronic Warfare and Sensors (PEO IEW&S).

(3) Methods of Surveillance are explained in Section 5 below.

5. Methods of QUALITY ASSURANCE Surveillance.

Various methods exist to monitor performance. The COR shall use the surveillance methods listed below in the administration of this QASP.

Regardless of the surveillance method, the COR shall always contact the Contractor's task manager or on-site representative when a defect is identified and inform the manager of the specifics of the problem. The COR, with assistance from the COD KS, shall be responsible for monitoring the Contractor’s performance in meeting a specific performance standard/AQL.

A. Direct Observation. (Can be performed periodically or through 100% surveillance.)

B. Management Information Systems (MIS). (Evaluates outputs through the use of management information reports. Best used for general surveillance and may need to be supplemented by periodic inspections.)

C. Periodic Inspection. (Uses a comprehensive evaluation of selected outputs. Inspections will be as required.)

D. Progress or status meetings.

E. Analysis of contractor's progress reports. (Evaluate cost, schedule, etc.)

F. Performance reporting. (Evaluate metrics for a specific time period. Develop metrics or use metrics found in MIS.)

6. RATINGS.

Metrics and methods are designed to determine if performance exceeds, meets, or does not meet a given standard and acceptable quality level. A rating scale shall be used to determine a positive, neutral, or negative outcome.

Surveillance results may be used as the basis for actions (to include payment deductions) against the contractor. In such cases, the Inspection of Services clause in the Contract becomes the basis for the KO’s actions. Additionally, surveillance results may be used to prepare Performance Assessment Reports through the Contract Performance Assessment Reporting System (CPARS).

Performance will be documented using the Department of Defense standard colors for Performance Assessments. The standard colors, with their definitions, are as follows:

a. Exceptional (dark blue). Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

b. Very Good (purple). Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

c. Satisfactory (green). Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

d. Marginal (yellow). Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

e. Unsatisfactory (red). Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

7. DOCUMENTING PERFORMANCE.

a. ACCEPTABLE PERFORMANCE.

The Government shall document positive performance. Any report may become a part of the supporting documentation for fixed fee payments or other actions. The COR will document performance in the COR Tracking tool. Additionally, surveillance results may be used to prepare Performance Assessment Reports in CPARS.

b. UNACCEPTABLE PERFORMANCE.

When unacceptable performance occurs, the COR shall inform the Contracting Officer and the Contractor. This will normally be in writing unless circumstances necessitate verbal communication. The COR will document performance in the COR Tracking tool. In any case the COR shall document the discussion and place it in the COR file.

The Contractor shall acknowledge receipt of the issue in writing. If necessary, the Contractor is required to prepare a corrective action plan to document how the Contractor shall correct the unacceptable performance and avoid a recurrence. The Government will also state how long after receipt the Contractor has to present this corrective action plan to the COR and Contracting Officer. The Government shall review the Contractor's corrective action plan to determine acceptability.

Any documentation detailing unacceptable may become a part of the supporting documentation for contract payment deductions, fixed fee deductions, award fee nonpayment, or other actions deemed necessary by the KO. Additionally, surveillance results may be used to prepare Performance Assessment Reports in CPARS.

8. FREQUENCY OF MEASUREMENT.

a. Frequency of Measurement.

During contract/order performance, the COR shall take periodic measurements as specified in the AQL column of the Performance Standards Summary Matrix, and shall analyze whether the negotiated frequency of measurement is appropriate for the work being performed.

b. Frequency of Performance Assessment Meetings.

At a minimum, the COR shall meet with the Contractor on a bi-weekly basis via teleconference sessions and quarterly at the contractor’s facility to assess performance and shall provide a written assessment.

Prepared by:

TBD

Contracting Officer’s Representative