REQUEST FOR INFORMTION (RFI) RESPONSES TO SOLICITATION NO. W56ZTN-18-R-0002 DATED 11 JUNE 2018
| No. |
| Question: |
| Response: |
| 1 |
| The specification section for bid items 10 07AE, Tank Mix and 10 07AS, Runway Mix is 02554, Hot Mix Asphalt Pavement. This specification states that bituminous concrete mixes and materials shall be in accordance with Section 504 of Maryland State (Highway) Specifications. This section, or any other section of the Maryland State Highway specifications, does not provide specifications for either the Tank Mix or Runway Mix. Please provide specifications for the required mix design. |
| In accordance with: Runway mix: Unified Facilities Criteria (UFC) 3-260-01 Airfield & Heliport Planning & Design Guide; Tank Mix: Maryland Department of Transportation (DOT) Level 5 |
| 2 |
| Regarding the MDE permit acquisition and expedited review, should this be a line item on the bid sheet? |
| Yes, See CLIN 10 25 AY for Maryland Reviewer. |
| 3 |
| We are pursuing for this project and would like to ask you about the teaming with other Small Business, but non-8(a) firm. |
SBA approval for teaming arrangements is not required. In accordance with the Partnership Agreement between SBA and the agency, the Partnership Agreement represents delegation of the SBA's 8(a) contract execution authority to other federal agencies, which includes full administrative authority to the Contracting Officer to review and approve subcontractors to the 8(a) Participant. We would draw your attention to the 8(a) firm's requirement to meet the limitations on subcontracting per 13 FR 125.6. 13 CFR 125.6(c) specifically discusses subcontracts to similarly situated entities. Because this procurement is an 8(a) competitive, the case where the prime is 8(a) and the subcontractor is a small business (no 8(a) certification), they would not be viewed as similarly situated and that subcontractor's performance would not count towards the 8(a)'s 15% self-performance requirement as outlined in the RFP. If both entities were 8(a), both of their performance would count toward the 15% requirement. Finally, because this is 8(a) competitive, we would strongly suggest that you contact your local SBA Business Opportunity Specialist for additional guidance and confirmation of what was stated.
| 4 |
| Is SBA approval required for teaming arrangement with my 8(a) firm and one other Small Business, non 8(a) firm? |
See above response for No. 3.
| 5 |
| 17 Subfactor 2: key personnel |
Project Manager
Will the government accept an active PE license in lieu of an engineering degree?
No. Must have an Engineering Degree.
| 6 |
| 18 VOLUME II – Factor II – |
Past Performance
The RFP states “Offerors shall submit all contracts for the prime offeror and each major subcontractor.” Will the Government please provide a maximum number of projects that are to be provided?
A maximum of 10. BASIS FOR AWARD AND FACTORS/SUB-FACTORS TO BE EVALUATED updated to reflect this maximum number of 10. (See attachment)
| 7 |
| N/A |
Excel Price Sheets
Does the government want the line item pricing loaded with General Conditions, Overhead, and Profit?
Yes. Submit fully loaded line item prices.
| 8 |
| N/A |
Excel Price Sheets
Will the Government please provide the quantities that were used for each line item on the existing contract?
This information is not available. The current contract number is W56ZTN-17-D-0002. Public information pertaining to spending on this contract can be found at: https://www.usaspending.gov.
| 9 |
| Will the Government provide enough work on this contract for the Contractor to be able to schedule crews to work continuously or will numerous mobilizations and demobilizations be required? |
| The Government is unable to specify future workloads because it depends on the need, funding availability, and unpredictable factors such as the weather. Consequently, the requirement is being competed and awarded as an Indefinite Delivery requirements-type contract. |
| 10 |
| How is the cost for traffic control to be captured by the contractor? Can you provide an idea of the number or percentage of delivery orders that will require traffic control? |
Traffic control is to be captured as part of the offeror’s proposed loaded prices in the spreadsheets. The Government cannot provide a number or percentage of task orders that will require traffic control.
| 11 |
| What percentage of work will be required to be performed “off-hours” for logistical, safety or other reasons? How is the cost of overtime pay to be captured by the contractor for the additional expense? |
The Government cannot provide a percentage of “off hours” for safety or other reasons. It will depend on the requirement when the need arises. Contractor will need to capture those expenses as part of their overhead expenses which are to be included in line item pricing. Task Orders are issued on a firm fixed price basis.
| 12 |
| How is the contractor to be compensated for additional cost associated with an “off hour” emergency response? |
Contractor will need to incorporate those expenses as part of their function of the contract and overhead expenses if the need arises. Off-hour Emergency responses have historically been rare, averaging less than one per year.
| 13 |
| How is scheduling affected by APG specific factors such as access to secure areas, firing schedules, military activities, etc? How are delays and de and re-mobilization costs from these and similar restrictions compensable to the contractor? |
This is a firm fixed price requirement. The Government and the contractor discuss firing schedules, military activities, etc. during the site visit and when agreeing upon an appropriate performance period. The contractor can refer to FAR 52.243-1, 52.243-4, and 52.243-5 Changes and 52.236-2 Differing Site Conditions Clauses within the solicitation for additional delays.
| 14 |
| Will the Wage Rates specified in the solicitation remain in effect for the duration of the contract including option years / extensions? If the wage rates are revised during the contract period will we have an option to adjust our pricing to reflect the change? |
No. Wage Determination Rates will change annually as the Option Years are exercised. Regarding adjustments to contract pricing, it depends. Reference FAR 52.222-43.
| 15 |
| What documentation is required for planned equipment purchases? |
Please review the solicitation package carefully. Equipment is mentioned in several places throughout the document. Example: Technical Evaluation Approach Subfactor b: Contract Management Plan (CMP) – bullet “4” request “Equipment List” – please provide a detailed document of what is being requested in this bullet. Again, Proposal Submission Requirements, Subfactor b: Contract Management Plan (CMP) – bullet “4” Equipment. Please read carefully. It is ultimately up to the offeror to provide sufficient information and detail to enable the Government to evaluate the proposal and determine whether the planned equipment purchase plan is adequate for the requirement.
| 16 |
| If UXO is discovered on a project and it results in a delay, how is the contractor to be compensated? |
See contract clauses within the solicitation package for Changes and Changed Conditions.
| 17 |
| If a differing site condition is discovered how is the contractor to be compensated during the mandated work stoppage while awaiting direction from the COR? |
See contract clauses within the solicitation package for Changes and Changed Conditions. Reference FAR 52.236-2.
| 18 |
| ACI Field Testing and NICET Soil Certifications are typically obtained by specialists who work exclusively in those specific fields. Can the requirement for those certifications be satisfied by person(s) other than the QCM? |
Yes, more than one person is acceptable.
| 19 |
| Please clarify the 40-Hour OSHA Safety Inspection Certification for the QCM. Should this refer to OSHA 30-Hour certification? |
Yes, 30 hour OSHA Certification is required. BASIS FOR AWARD AND FACTORS/SUB-FACTORS TO BE EVALUATED updated to reflect 30 hours. (See attachment)
| 20 |
| Is a Safety Officer required? Can that requirement be met by one of the other Key Personnel? |
Yes, a dedicated Safety Officer is Required. No, the requirement cannot be met by another Key Personnel. Reference Engineer Manual (EM) 385-1.
| 21 |
| 10 01AT Light and Signal Pole – Please specify size and type of construction, footer / base requirements |
Please note that specifications for lights, signals, poles, etc. shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011. See Scope of Work, Specification 2.1. Please review line items.
| 22 |
| 10 01AU Light and Signal Mast – Please specify size and type of construction |
Please note that specifications for lights, signals, poles, etc. shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011. See Scope of Work, Specification 2.1.
| 23 |
| 10 04AL Armor Stone- Typically armor stone falls into one of two categories. The first is 500 lbs. to 1500 lbs. and the second is 1000 lbs. to 2500 lbs. Please specify which of these two materials is required |
Maybe both depending on the particular task order. The CLIN is requesting pricing for 100 TN.
| 24 |
| 10 07AL Rumble Strips milled; rolled/formed- Please provide specifications/details for this item and clarification what this item is to be used for |
Design will be part of the task order and purpose to alert traffic of possible obstacles.
| 25 |
| 10 17AI Handicapped Walk & Curb Cut 12:1 Slope Max.- Is this a duplicate of 10 17AH which states the same thing? |
Yes, this is a duplicate. Delete 10 17 AI
| 26 |
| 10 22AC Metal Traffic Barrier End Treatments – There are 8-10 different end treatments in the MDSHA specifications and the prices vary substantially between them. Please specify which end treatment is required |
Type E
| 27 |
| 10 22AL Signal Head – Please provide details on type and function of head |
This will be part of the design/build of task order. See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011.
| 28 |
| 10 22AM Video Detectors – Please provide details on type and function |
This will be part of the design/build of task order. See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011.
| 29 |
| 10 22AN Radar Detectors – Please provide details on type and function |
This will be part of the design/build of task order. See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011.
| 30 |
| 10 22AO Infrared Detectors – Please provide details on type and function |
This will be part of the design/build of task order. See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011.
| 31 |
| 10 22AP Controller – Please provide details on type and function |
This will be part of the design/build of task order. See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011.
| 32 |
| 10 22AQ Wiring System to support traffic control system – Please provide details on type of system |
This will be part of the design/build of task order. See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011.
| 33 |
| 10 22 AR Traffic Arm 15 foot – Please specify type of construction and should unit of measure be Each instead of LF? |
See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011. 0-14 Feet. Measured by Each
| 34 |
| 10 22 AS Traffic Arm 15 foot – Is this a duplicate of 10 22 AR which states the same thing? |
See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011. 15-20 Feet. Measured by Each
| 35 |
| 10 22 AT Traffic Arm 20 - 25 foot – Pleas specify type of construction and should unit of measure be Each instead of LF? |
See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011. Measured by Each
| 36 |
| 10 22 AU Traffic Arm 30 - 35 foot – Please specify type of construction and should unit of measure be Each instead of LF? |
See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011. Measured by Each
| 37 |
| 10 22AV Pole – Please specify type, height, with or without support base |
See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011.
Height will vary and it is with support base.
| 38 |
| 10 22AX Pedestrian LED Sign – Please specify type of fixture. Is pole, power & control wiring to be included |
See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011. Pole and control wiring would be separate.
| 39 |
| 10 25AA Traffic Control System Analysis… - Is this for Traffic Control Engineering & Design or Troubleshooting / Repair? |
Yes, for everything.
| 40 |
| 10 25BL Parking Lot Lights pole with 2.0 fc… - Please specify pole construction & fixture type/height |
This will be part of the design/build of task order. See Scope of Work, Specification 2.1. Shall be in accordance with the specifications outlined by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual dated January 2011.
| 41 |
| 10 25 BM Parking Lot Lights wiring system – Does this line item include a control system for the lights (timeclock / photocell / other) |
Yes.
| 42 |
| 1. On the Base Year spreadsheet, to the right of 1007AO-1007AS there is information for 5008AA-5008AD which includes pricing. On the other 4 spreadsheets, only part of this information is there. Is this missing? |
Please see the revised CLIN numbers.
| 43 |
| 1. We have performed hundreds of applicable jobs over the past 5 years. The solicitation references inclusion of all projects that are similar in scope and NAICS code. Since that would be an extensive effort, please clarify how many Past Performance Questionnaires we need to submit? Would 10 be acceptable as a max? Is there a min number? |
Maximum 10 and Minimum 5. BASIS FOR AWARD AND FACTORS/SUB-FACTORS TO BE EVALUATED updated to reflect this maximum number of 10. (See attachment)
| 44 |
| 1. We have performed civil site work on previous IDIQ contracts. Can we submit Past Performance Questionnaires per Delivery Order or do they have to be submitted per contract? |
Either is fine so long as the projects meet the RFP definition of recent and relevant. Reference page 18 of the RFP for Volume II –Factor II – Past Performance
| 45 |
| 1. If there are problems submitting documents via the AMRDEC SAFE site, is there a backup procedure to use? |
We have not experienced any issues in the past with AMRDEC but if there are any problems, please contact via email the POC Sandra.a.anderson12.civ@mail.mil prior to the due date and time. Offerors are cautioned not to wait until the last minute to submit proposals.
License/Certificates requirement can be met by using more than one person. (Delete/Remove “per Amendment 3” language from this statement) See Attached BASIS FOR AWARD AND FACTORS/SUB-FACTORS TO BE EVALUATED updated to reflect this change.
| 47 |
| Section 00010 – Solicitation Contract Form |
Items 1001, 2001, 3001, 4001 and 5001 state:
Yes, this is an estimated amount plus or minus for the annual bond premium amount for all offerors.
| 48 |
| Specification 02010 Unexploded Ordnance – No. 4.1 indicates “The contractor shall employ one of the following EOD organizations or a Government (APG) approved equal: |
| Contractor shall obtain an approved EOD organization. The organization does not have to be on the list provided, however the firm must be approved by the Garrison Safety Officer. Also an organization may obtain approval status. |
| 49 |
| The Solicitation Instructions to Bidders, Section 1, Introduction, states: |
"The Government is establishing a 150 page limit on proposals. Volume IV does not count against the page limitation."
We would like to request clarification on this because it seems to include the pricing volume within this 150 page limitation. Volume III combined with Section 00010, SF1442 and addendums already exceed the 150page limit. Shouldn't Volume III be excluded from the page count as well as Volume IV?
Please also confirm that the PPQs which are returned directly to the Government are not included against this page count.
Volume I – Technical, Volume II – Past Performance and Volume III – Price. These 3 volumes has a total page limit of 150 pages. Volume IV which is your SF 1442, addendums, certification/representations, teaming, joint venture documentation (if applicable) does not count against the page limitation.
Past Performance Questionnaires that are returned directly to the Government are not included in the page count.