W56ZTN18R0002
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 0006 is being issued for the follow ing reasons:
a. To provide responses dated 28 June 2018 to additional RFIs/Questions received. See MS Word document w hich is being posted as a separate attachment in Fedbizopps under this Amendment.
b. Revise basis for aw ard and update SOW (add 4.10) for QCM and quality control requirements. Changes are noted in "track changes".
c. All other terms and conditions remain unchanged. The due date of proposals remains unchanged from Amendment 0005.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 18
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-Jun-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W56ZTN18R0002
X 9B. DATED (SEE ITEM 11)
21-Apr-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-Jun-2018
CODE
ACC-APG - GARRISON DIVISION (W56ZTN)
ACC-APG GARRISON DIVISION
BLDG 6001
6565 SURVEILLANCE LOOP
ABERDEEN PROVING GROUND MD 21005-3013
W56ZTN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been modified:
BASIS FOR AWARD
BASIS FOR AWARD AND FACTORS/SUB-FACTORS TO BE EVALUATED
A. BASIS FOR AWARD
The award will be made based on the best overall proposal with appropriate consideration given to the following three evaluation factors: Technical (Factor I), Past Performance (Factor II), and Price (Factor III). To receive consideration for an award, an “Acceptable” rating must be achieved for the following two evaluation factors: Technical (Factor I) and Past Performance (Factor II). Factors I and II are of equal importance. All subfactors under Technical (Factor I) are of equal importance. Award will be made to the single responsible offeror, whose proposal has been determined to be technically acceptable (Factor I), acceptable for Past Performance (Factor II), and who has offered the lowest total price (Factor III), inclusive of all CLINs and options. Offerors must be rated as acceptable for all factors and subfactors to receive the award. Price will be evaluated in accordance with FAR 15.404-1. The Government intends to evaluate proposals and make award without discussions. Offerors should ensure the completeness of their proposals and offer their best terms and conditions with their initial proposals. If negotiations are considered necessary, they will be conducted with those offerors in a competitive range.
The determination of the competitive range will be the responsibility of the Contracting Officer and the Source Selection Authority. Factors and sub-factors are not numerically weighted. Price will be the ultimate determining factor for proposals rated as acceptable for Technical and Past Performance.
In order to be considered for award, offerors must be registered in the System for Award Management (SAM) under NAICS 237310 (Size Standard $36.5M) prior to contract award.
B. FACTORS AND SUB-FACTORS TO BE EVALUATED
The following evaluation factors and subfactors will be used to evaluate each proposal.
A detailed explanation of the criteria for evaluation is set forth in the “evaluation approach”, paragraph C of this section. During evaluation of each proposal, the Government will assign each factor/sub-factor an Acceptable/Unacceptable rating. Each sub-factor will be evaluated to determine if the proposed approach associated with each factor meets or does not meet the minimum performance or capability requirements. To receive an overall “Acceptable” factor rating, all sub-factors must receive an “Acceptable” rating.
Factor 1: Technical
The Technical factor is further divided into the following sub-factors:
a) Bonding Capacity
b) Contract Management Plan (CMP)
c) Key Personnel:
• Project Manager (PM)
• Superintendent
• Quality Control Manager (QCM)
Factor 2: Past Performance:
Each offeror's past performance will be reviewed and evaluated on an acceptable or unacceptable basis.
Factor 3: Price:
The resulting award will be a Requirements-type Indefinite Delivery contract with task orders issued on a Firm Fixed Price (FFP) basis based on line item pricing incorporated into the award. The Government will evaluate offers for award purposes by adding the total of all CLIN/SubCLIN prices, including spreadsheets included in the solicitation.
C. EVALUATION APPROACH
All proposals shall be subject to evaluation by the Source Selection Team (SST). The SST will evaluated the proposals on an “Acceptable” or “Unacceptable” basis.
1. The overarching evaluation approach for all factors and sub-factors is an adequacy of response. The proposal will be evaluated to determine whether the offeror’s methods and approach have adequately and completely considered, defined, and satisfied the requirements specified in the RFP. The proposal will be evaluated to determine the extent to which each requirement has been addressed in the proposal in accordance with the proposal submission section of the RFP.
TECHNICAL EVALUATION APPROACH.
The Technical factor is divided into the following sub-factors and evaluated on an “Acceptable” or “Unacceptable” basis.
Table – Technical Acceptable/Unacceptable Ratings
Rating Description Acceptable Proposal clearly meets the minimum requirements of the solicitation.
Unacceptable Proposal does not clearly meet the minimum requirements of the solicitation.
2. The Technical factor is divided into the following sub-factors:
Subfactor a: Bonding Capacity:
The Government will evaluate the offeror’s ability to provide evidence from its chosen Surety that it can obtain $10 Million of payment and performance bonds per year of performance specifically for this paving contract based on the documentation that it submits with its proposal.
Subfactor b: Contract Management Plan (CMP):
The Government will evaluate the offeror’s ability to perform based on its submitted information for the CMP. The evaluation will be based on the adequacy of response for the following items:
Description of the overall company structure related to the performance and SOW.
Overview of contract execution.
Organization. Description of its ability to manage multiple projects through adequate and qualified on-site staffing to support at least 10 ongoing projects.
Equipment list (currently owned and planned purchases/lease): Detailed list of equipment to be used in this contract. Age of the vehicles, pictures, and personnel to use this equipment. Identification of current equipment owned and any plans to purchase/lease additional equipment after award during the one (1) month transition-in/phase-in period. NOTE: Contractors should assume for proposal purposes that approximately $5M-$10M of work will be awarded per year or will be ongoing at any time. Currently owned and planned purchases/leased equipment list must be adequate for handling this magnitude of workload.
Scheduling methodology: Description of the scheduling techniques and project planning methodology. Description of the criteria for selecting and qualifying subcontractor(s).
Quality control. Description of how the prime contractor plans to control the quality of work.
Safety: safety program, training, and OSHA requirements within 3 years.
Subfactor c: Key Personnel (NOTE: Qualifications, education, and other information as outlined below in "Proposal Submission Requirements" must be clearly demonstrated/listed in the resumes provided. The Government will not make assumptions or fill-in the blanks)
Project Manager (PM):
The Government will evaluate the offeror’s ability to provide a PM that possesses the following experience:
Minimum of 7 years of experience in the construction, including minimum of 5 years of experience in paving management.
Graduate of an accredited university or college with an engineering degree in the civil construction field.
Has at least 2 years of supervisory experience in the construction field related to paving.
Superintendent:
The Government will evaluate the offeror’s ability to provide a Superintendent that possesses the following experience:
Minimum of 7 years journeyman level experience in the paving field and minimum of 3 years of experience in supervisory position related to paving.
Quality Control Manager (QCM):
The Government will evaluate the offeror’s ability to provide a QCM that possesses the following experience:
Possesses the current license/certification in the following areas: American
Concrete Institute (ACI) concrete Field Testing Grade I Certification, 30-hour OSHA Safety Inspection Certification, Storm Water Permit Certification (N/A to the QCM but the certificate must be held by one of the offeror’s National Institute for Certification in Engineering Technologies (NICET) Level 1 Soil Certification, and the US Army Corps of Engineers Quality Control Training Course Completion Certificate.
Minimum of 10 years combined specialized experience as a Quality Control Manager in industrial, institutional, and DoD activities.
3. Past Performance
The Government will evaluate the offeror’s record of past and current performance to ascertain the probability of successfully performing the required efforts of the SOW. Past Performance factor considers each offeror’s demonstrated recent and relevant record of performance in providing services that meet the contract requirements. Recent past performance is considered to be efforts awarded during the past five (5) years, from the issue date of this RFP. Relevant efforts are defined as services that are the same as or similar services as compared to the North American Industry Classification System (NAICS) Code 237310 (Highway, Street, Bridge Construction). Work may include work performed for commercial or Governmental clients. The size and scale of the projects provided will also be considered when determining relevancy.
Evaluation of past performance shall be in accordance with this plan utilizing the forms and questionnaires set forth in Attachment 2. The Government may consider a wide array of information from a variety of sources, but is not compelled to rely on all the information available.
The Government may use data provided by the offeror in its proposal and data obtained from other sources, including data in Government files (i.e., CPARs) or data obtained through interviews with personnel familiar with the contractor and their current and past performance.
Data used in conducting past performance assessments shall not extend past five years prior to the issue date of the RFP, but may include performance data as a prime. The Government reserves the right to limit the number of references it decides to contact and to contact references other than those provided by the Offeror including sources outside the Government.
The Government will evaluate the offeror’s proposal against the above requirements to determine whether the proposal is acceptable or unacceptable for the Past Performance factor, using the ratings and descriptions outlined in Table 1 below.
Table 1 – Past Performance Ratings
NOTE: If an Offeror submits a certification statement that it has no relevant past performance and the Government has no other information available regarding the Offerors past performance, that Offeror will receive a neutral/unknown rating (i.e.), the Offeror is evaluated neither favorably nor unfavorably) for past performance. If the Offeror provides past performance information that is not relevant and current as defined in the RFP, the Offeror will receive a neutral/unknown past performance rating for those contracts. Neutral/unknown is the equivalent of Acceptable for this acquisition.
4. Price.
The Government will evaluate the price proposal for award purposes by adding the total of all CLIN/SubCLIN prices, including all options by using price analysis techniques describe in FAR 15.404-1. Examples include using historical price information, price competition information, the Independent Government Estimate (IGE), and any other pricing tools necessary. Offers that are unbalanced between years or CLINs may be found unacceptable.
A price is considered reasonable when, in its nature or amount, it does not exceed what an ordinarily prudent person in the conduct of competitive business would incur. A balanced offer is one that contains prices properly distributed over all line items throughout the life of the contract including any base and option period(s).
Rating Description Acceptable Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown.
Unacceptable Based on the offeror’s performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort.
Reasonableness will be established using historical price information, price competition information, the Independent Government Estimate (IGE), and any other pricing tools necessary. Offers that are unbalanced between years or CLINs may be found unacceptable.
PROPOSAL SUBMISSION REQUIREMENTS (INSTRUCTIONS TO OFFERORS):
1. INTRODUCTION.
a. The offeror’s proposal shall be submitted electronically as set forth below to:
US Army Contracting Command-Aberdeen Proving Ground Attn: Mr. Lane M. Gary, Contracting Officer
b. The offeror’s proposal shall consist of four (4) separate and clearly marked and separated volumes. The Volumes are: Volume I – Technical; Volume II – Past Performance;
Volume III – Price; and Volume IV - Solicitation, Offer, Award Documents, and Certification/Representations, Teaming, Joint Venture documentation (if applicable).
Proposals shall not contain classified data. The use of hyperlinks in proposals is prohibited. The Government is establishing a 150 page limit on proposals. Volume IV does not count against the page limitation. If potential offerors believe that an expansion of the page limit is warranted, they must submit a request in writing to the Government during the Question and Answer period of the solicitation for Government consideration.
NOTE: Pages that exceed the required page limitations will not be evaluated. Additional pages over the maximum allowed will be removed or not read and will not be evaluated by the Government.
c. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal. Proprietary information shall be clearly marked.
2. PROPOSAL SUBMISSION REQUIREMENTS.
a. Electronic offers shall be submitted via the AMRDEC SAFE site.
https://safe.amrdec.army.mil/safe/About.aspx. Proposals shall be sent to Ms. Sandra A.
Anderson, sandra.a.anderson12.civ@mail.mil and Mr. Lane M. Gary, lane.m.gary.civ@mail.mil.
3. PROPOSAL FILES
a. Format. The submission shall be clearly indexed and logically assembled.
Each volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date and RFP number in the header and/or footer. The submission shall use MS Word 2013 (or previous version) or Adobe PDF as the file type.
b. File Packaging. Zip files are not permitted. Files shall be in Adobe PDF or
MS Word 2013 (or previous version). Any price breakdown information submitted to aide in the price evaluation shall be submitted in Microsoft Office Excel 2013 (or previous version) Read/Write format.
c. Content Requirement. All information shall be confined to the appropriate file.
The Offeror shall confine submissions to essential matters and sufficient to define the proposal in a concise manner, to permit a complete and accurate evaluation of each proposal. Offerors are cautioned that “parroting” of the Statement of Work (SOW) with a statement of intent to perform does not reflect an understanding of the requirement or indicate the ability to perform any task in the SOW and will be rated as “Unacceptable”. Proprietary information shall be clearly marked.
The following shall be included in the Volumes:
(i) VOLUME I – Factor 1 – Technical.
Offerors shall clearly articulate the technical approach (including risks and contingencies) for performing the work, an understanding of the requirement and the capacity to perform the work. The Technical volume shall be organized into the following below sections:
Subfactor a: Bonding Capacity:
Offeror shall provide a signed letter from its chosen Surety that it can obtain $10M of performance and payment bonds or evidence that it currently has $10M of spare performance and payment bond capacity for this contract. The Offeror shall also provide contact information for the surety so that the Government can at its discretion verify the information provided.
Subfactor b: Contract Management Plan (CMP):
Offeror shall provide information that substantiates the following:
Describe the overall company structure related to the performance and SOW.
General overview of planned contract execution.
Organization: Provide an organizational chart by title/position showing how offeror plans to execute this contract. Address the ability to manage multiple projects through adequate and qualified on-site staffing to support at least 10 ongoing projects.
Equipment: supply a detailed list of existing equipment to be used in this contract. List age of the vehicles, pictures, and personnel to use this equipment.
Clearly identify current equipment owned and any plans to purchase/lease additional equipment after award during the transition-in/phase-in period. For planned purchases/leases, describe the purchasing plans and suppliers. For planned purchases/leases, provide evidence of financial capability such as letter of credit, bank statements, stock holdings, balance sheet info, etc. to demonstrate that the offeror has the financial strength to purchase/lease the equipment.
Scheduling methodology: describe the scheduling techniques and project planning methodology. Describe the criteria for selecting and qualifying subcontractor.
Describe the offeror’s plan to ensure Quality control of the contract and projects.
Safety: Describe/provide safety program, training, and OSHA requirements within 3 years.
Subfactor c: Key Personnel
Project Manager (PM):
Offeror shall provide resume(s), including training certificates for the person(s) that will perform the Project Manager duties. The resume shall demonstrate the following:
Minimum of 7 years of experience in the construction, including minimum of 5 years of experience in paving management.
Graduated from an accredited university or college with an engineering degree in the civil construction field.
Has at least 2 years of supervisory experience in the construction field related to paving.
Superintendent:
will perform the Superintendent duties. The resume shall demonstrate the following:
Minimum of 7 years journeyman level experience in the paving field and minimum of 3 years of experience in a supervisory position in this field.
Quality Control Manager (QCM):
will perform the QCM duties. The resume shall demonstrate the following:
Possesses the current license/certification in the following areas: American Concrete Institute (ACI) concrete Field Testing Grade I Certification, 30-hour OSHA Safety Inspection Certification, Storm Water Permit Certification (N/A to the QCM but the certificate must be held by one of the offeror’s staff per Amendment 3), National Institute for Certification in Engineering Technologies (NICET) Level 1 Soil Certification, and the US Army Corps of Engineers Quality Control Training Course Completion Certificate.
Minimum of 10 years combined specialized experience as a Quality Control
Manager in industrial, institutional, and/or DoD activities.
VOLUME II – Factor II – Past Performance. This volume shall contain past performance information regarding similar contracts. Offerors shall submit (maximum of 10) all contracts for the prime offeror and each major subcontractor in performance or awarded during the past five (5) years, from the issue date of this RFP, which are relevant to the efforts required by this solicitation. Relevant efforts are defined as services that are the same as or similar services as compared to the North American Industry Classification System (NAICS) code 237310 are considered relevant. Major subcontractors are defined members of an offeror’s overall team who are expected to perform ten (10) percent or more of the proposed effort. This volume shall be organized into the following sections:
(1) Section 1 - Contract Descriptions. This section shall include the following information in the following format:
(a) Contractor/Subcontractor place of performance, CAGE Code and DUNS Number. If the work was performed as a subcontractor, also provide the name of the prime contractor and Point of Contact (POC) within the prime contractor organization (name, and current address, e-mail address, and telephone and fax numbers).
(b) Government contracting activity, and current address, Procuring Contracting Officer's name, e-mail address, telephone and fax numbers.
(c) Government’s technical representative/COR, and current e-mail address, telephone and fax numbers.
(d) Government contract administration activity and the Administrative Contracting Officer's name, and current e-mail address, telephone and fax numbers.
(e) Government contract administration activity's Pre-Award Monitor's name, and current e-mail address, telephone and fax numbers.
(f) Contract Number and, in the case of Indefinite Delivery type contracts, GSA contracts, and Blanket Purchase Agreements, include Delivery Order Numbers.
(g) Contract Type (specific type such as Fixed Price (FP), Cost
Reimbursement (CR), Time & Material (T&M), etc.). In the case of
Indefinite Delivery contracts, indicate specific type (Requirements, Definite Quantity, and Indefinite Quantity) and secondary contract type (FP, CR, T&M, etc.)
(h) Awarded price/cost.
(i) Final or projected final price/cost.
(j) Original delivery schedule, including dates of start and
(k) Completion of work.
(l) Final, or projected final, delivery schedule, including dates of start and completion of work.
(2) Section 2 - Performance. Offerors shall provide a specific narrative explanation of each contract listed in Section 1, Contract Descriptions describing the objectives achieved and detailing how the effort is relevant to the requirements of this RFP.
(a) For any contracts that did not/do not meet original schedule or technical performance requirements, provide a brief explanation of the reason(s) for the shortcomings and any corrective action(s) taken to avoid recurrence. The Offerors shall list each time the delivery schedule was revised and provide an explanation of why the revision was necessary. All Requests for Deviation and Requests for Waiver shall be addressed with respect to causes and corrective actions. The Offerors shall also provide a copy of any Cure Notices or Show Cause Letters received on each contract listed and a description of any corrective action implemented by the Offeror or proposed subcontractor. The Offerors shall indicate if any of the contracts listed were terminated and the type and reasons for the termination.
(b) Past Performance Questionnaire. For all contracts identified in Section
1, Contract Descriptions, Offerors must make a reasonable attempt to have a Past Performance Questionnaire (Solicitation Attachment 2) completed (maximum of 10 and minimum of 5) and submitted by the client. The offeror shall complete Part I of the Past Performance Questionnaire and email the questionnaire to both the Army contracting activity and technical representative responsible for the past/current contract. The POC's shall be instructed to electronically complete Part II of the questionnaire and directly email the entire questionnaire to the Contracting Office no later than the proposal due date, to Sandra Anderson at sandra.a.anderson12.civ@mail.mil and Lane Gary at lane.m.gary.civ@mail.mil. The offeror shall also include a list of all the POC’s who were sent a questionnaire in the proposal. The POC List shall be include the following information: Solicitation Number; Company Name; Contract Number; Army Agency; POC Last Name, First Name; POC Title; POC Telephone Number; POC E-Mail Address; Date E-mailed to POC (month/day).
The Government will focus its inquiries on the offeror’s (and major subcontractor’s) record of performance as it relates to all solicitation requirements, including cost, schedule, performance and management of subcontractors. A significant achievement, problem, or lack of relevant data in any element of the work can become an important consideration in the evaluation process. Therefore, offerors will be reminded they must at a minimum include the most recent and relevant efforts (performance within the past five (5) years) in their proposal. Absent any recent and relevant past performance history or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on past performance. In some circumstances Past Performance may receive a neutral rating. Therefore, when a neutral rating is assigned, it shall be assumed that the offeror will perform in an acceptable manner.
VOLUME III – Factor III – Price.
Price proposal shall consist of the following:
1. The MS Excel bid schedule is provided in Attachment 1 including Base Year, Option Year 1, Option Year 2, Option Year 3, and Option Year 4.
BASE YEAR: Offeror shall subtotal Base Year of Line Items from (e.g. 1001 through 1025) from the spreadsheet (Attachment 1) to achieve a TOTAL for the Base Year. Offeror shall then transfer the TOTAL AMOUNT to Section 00 10 00 of the RFP.
OPTION YEAR 1: Offeror shall subtotal Option Year 1 of Line Items from (e . g. 2001 through 2025) from the spreadsheet (Attachment 1) to achieve a TOTAL for the Option Year 1. Offeror shall then transfer the TOTAL AMOUNT to Section 00 10 00 of the RFP.
OPTION YEAR 2: Offeror shall subtotal Option Year 2 of Line Items from (e . g. 3001 through 3025) from the spreadsheet (Attachment 1) to achieve a TOTAL for the Option Year 2. Offeror
OPTION YEAR 3: Offeror shall subtotal Option Year 3 of Line Items from (e . g. 4001 through 4025) from the spreadsheet (Attachment 1) to achieve a TOTAL for the Option Year 3. Offeror
OPTION YEAR 4: Offeror shall subtotal Option Year 4 of Line Items from (e . g. 5001 through 5025) from the spreadsheet (Attachment 1e) to achieve a TOTAL for the Option Year 4. Offeror
The offeror shall provide Unit Price and Total Price for each ITEM/SUB- ITEM in the Excel Spreadsheets provided (Attachments 1). The offeror shall then transfer the total pricing information to Section 00 10 00 of the RFP.
When submitting a proposal, offerors shall utilize the Excel spreadsheets provided (Attachment 1).
As noted in the CLINs, a normalized/estimated amount of $100,000.00 will be assumed for bonding premiums per year for all offerors.
VOLUME IV – Solicitations, Offer and Award Documents and Certifications/ Representations/Teaming, Joint Venture documentation (if applicable)
Certifications and Representations - Each offeror shall complete (fill-in and signatures) the solicitation sections indicated below using the file (without modification to the file) provided with the solicitation. An authorized official of the firm shall sign the SF1442 and all certifications requiring original signature. Offerors are required to acknowledge all amendments (SF 30) in accordance with (IAW) FAR 52.215-1. Offerors also must complete Online Representations and Certifications Application (ORCA) registration IAW FAR 52.212-3.
An Acrobat PDF file shall be created to capture the signatures for submission.
If a teaming or joint venture arrangement is contemplated, the offeror shall provide complete information about the arrangement, including any relevant and recent (up to five (5) years) of past/present performance information for the team members and/or joint venture. If this is a first time team/joint effort, each party to the arrangement must provide a list of past and present relevant contracts.
Relevant efforts are defined as services that are the same as or similar services as compared to the North American Industry Classification System (NAICS) code 237310.
Joint Venture Offerors: If the offeror is a joint venture, the offers shall provide all requirement solicitation information for all parties including a copy of the signed joint venture agreement with the proposal. The agreement shall include information, which identifies the responsibilities for each entity under this contract. The agreement shall demonstrate the relationship between firms and identify contractual relationships and authorities to bind each entity of the joint venture. If the joint venture is comprised of 8(a) firms, you shall provide a copy of the Small Business Administration (SBA) approval letter with your solicitation.
Teaming Offerors: If the offer is based on a teaming/partnering relationship, the offeror shall provide all required solicitation information for all parties including a copy of the teaming/partnership agreement. The agreement shall include information, which identifies the responsibilities for each entity under this contract. The agreement shall demonstrate the relationship between firms and identify contractual relationships and authorities to bind each entity of the teaming/partnering relationship. If the teaming is comprised of 8(a) firms, you shall provide a copy of the Small Business Administration (SBA) approval letter with your solicitation.
SECTION 00010 - SOLICITATION CONTRACT FORM
The Issued By organization has changed from
ACC-APG - GARRISON DIVISION (W56ZTN)
ACC-APG GARRISON DIVISION
BLDG 6001
6565 SURVEILLANCE LOOP
ABERDEEN PROVING GROUND MD 21005-3013
to
ACC-APG - TENANT DIVISION (W91ZLK)
ACC-APG TENANT DIVISION
BLDG 6001, 2ND FLOOR, ROOM C2-101
6565 SURVEILLANCE LOOP
ABERDEEN PROVING GROUND MD 21005-3013
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been modified:
SCOPE OF WORK
SCOPE OF WORK STATEMENT OF WORK (SOW)
SBA Requirement Number: 0373/18/800060/01
STATEMENT OF WORK, WORK SPECIFICATIONS, REQUIREMENTS AND RESPONSIBILITIES
Title: Requirements Contract for Paving, Drainage and Civil Site Work for Aberdeen Proving Ground, Maryland.
1. Location(s)
1.1. For the length or duration of this contract, the Department of the Army at Aberdeen Proving Ground (APG), Maryland shall require all work be performed, in individual delivery order, at one of the following areas:
Aberdeen Area, Edgewood Area, Churchville Area, Carroll Island Area, Spesutie Island Area, and Grace’s Quarters Area.
1.2. Military Construction Acquisition (MCA) projects executed by the Corps of Engineers are excluded from this contract.
2. Specifications:
2.1. The most current specifications as designated by the Maryland Department of Transportation State Highway Administration, Standard Specification for Construction and Materials Manual January 2011, and the latest Maryland Department of the Environment, Water Administrations 1999 Standard and Specifications and the Water Administrations 2000 Storm water Guidelines Volumes I and II; Manual on Uniform Traffic Control Devices (MUTCD) ; Annotated Code of Maryland Business Occupations and Professions Article, Title 15 Professional Land Surveyors Code of Maryland Regulations (COMAR) 09.13.01 through .08 and 09.01.02 & .03. or the most recent Standards shall be the standard used within this contract for the construction and process of building, altering, repairing, improving, filling grading, paving, pouring of concrete or demolishing any structure required in the construction of roads, sidewalk, parking lots, runway, storm drains, waterlines (Note: water and sewer lines in the Aberdeen Area is not part of this contract.), steam line, trenching, paving, erosion control, storm water management, curbing, Low Impact Development (LID)( pervious pavers, etc.), and grading of materials shall be adhered.
Information by the State Highway Administration can be obtained at: www.marylandroads.com
3. Requirements: The contractor shall be required to furnish all plant, labor, material, equipment, services incidental for performing all work during construction as associated with paving and drainage.
3.1. The contractor shall be required to furnish and install and or remove pavement markings (both permanent and temporary), lines and symbols, including complete covering of existing markings. A striping plan is part of this cost and is not a separate line item cost.
3.2. The contractor shall be required to furnish and install various aggregate bases and sub base material for the repair, patching and or construction of paving structures, flat concrete, vertical concrete (walls, stairs etc.) work formed concrete work, drainage devices, gabion, piping systems, etc. The contractor shall protect the sub-grade and base against damage from all causes.
3.3. The contactor shall be required to provide all labor, equipment and material for the installation of hot mix asphalt pavement as stipulated within the contract information.
3.4. The contractor shall be required to complete all earthwork as associated with paving and drainage, such as, clearing and grubbing, excavation and grading, geotextiles, topsoil, seeding and mulching, sod, rip rap, soil stabilization, etc.
3.5. The contractor shall be required to furnish and install storm drains, pipes, end sections, headwalls, manholes, inlets, under drains, curbs gutters, flumes, ditches, swales, etc.
3.6. The contractor shall be required to furnish and install handicapped ramps, sidewalks curb cuts, metal handrails, and related incidentals.
3.7. The contractor shall be required to adjust manhole frames, inlet grates and utility boxes and or manholes with the work area to conform to new or final grades. The contractor shall be required to demo and reconstruct new boxes, inlets, grates surfaces and manholes as per design or according to standard specifications for construction.
The contractor shall be required to reconstruct existing manholes, inlets and grates.
3.8. The contractor shall be required to install new manholes, inlets and utility boxes.
3.9. The contractor shall be required to provide surveying information. All survey work completed shall be required to be sealed by a Licensed Professional Land Surveyor or Licensed professional Engineer.
3.10. The contractor shall be required to establish 90% vegetative cover over the entire site where seeding and stabilization is required.
3.11. The contractor shall be required to construct all erosion and sediment control measures and storm water control devices to include Best Management Practices (BMP) such as bio retention ponds and storm water ponds.
3.12. The contractor shall be required to provide investigations for surface and sub surface buried unexploded ordinances.
3.13. The contractor shall be required to construct of flat work and vertical poured work, forms, reinforcement within formed concrete, placement and cutting of joints, surface finishing, curing and incidentals. This includes polished, stamped, and colored concrete.
3.14. The contractor may be requested to assist in emergency repairs of waterlines, sewer lines, force mains, collapsed culverts, and road damage. The contractor shall respond within one half (½) hour of notification.
3.15. The contractor shall be responsible for the demolition of bituminous and Portland Cement Concrete paving and drainage structures including but not limited to: removal, hauling, disposal, metal salvage, saw cutting, milling and grinding, etc. and placing the material on sites as designated the COR.
3.16. The contractor is required to submit all testing of materials. The materials shall be required to be tested by an independent state approved commercial laboratory and submitted to the COR for approval.
3.17. The contractor maybe required to install fence while working in a secure/safety areas. Fence is only incidental to this work and other contracting mechanism to install fence may be used by the Government. Fence shall meet UFC 4-022-03.
3.18. The contractor shall provide and install traffic signs: regulatory; warning and guide (excluding street names). This includes metal/aluminum post sleeve approximately 4” x 4” x 10-ft. Minimum thickness of aluminum post sleeves shall be .125-inch thick wall. Finish post sleeve color shall be “Aberdeen Brown (AB.BN)” and electrostatically applied/sprayed to post sleeve.
3.19. The contractor shall replace damaged roadway lighting including lamp, arm, poles etc.
3.20. The contractor shall perform diagnostic and submit a report of traffic signal systems.
3.21. The contractor shall replace signal heads, controller, and detectors (loop, radar, and video, infrared).
3.22. The contractor shall replace pedestrian indicator and push buttons.
3.23. The contractor shall provide designs associated with the paving project.
3.24. The contractor shall provide traffic studies.
3.25. Contractor shall place metal/aluminum post sleeves shall be fabricated to fit over 4” x 4” x 10-ft (Cut to size); actual size 3.5-in x 3.5-in x 120-in (Cut to size) wood street sign post. Post sleeve shall abut top of reinforced concrete post footing at grade and cover the entire wood post to the top where the sign caps are secured. Minimum thickness of aluminum post sleeves shall be .125-inch thick wall. Finish post sleeve color shall be “Aberdeen Brown (AB.BN)” and electrostatically applied/sprayed to post sleeve.
4. Management:
4.1. The contractor shall have an office located within one (1) hour driving time from APG AA, at the intersection of Susquehanna Ave and Maryland Blvd.
4.2. The contractor shall notify the COR, in writing, no less than five (5) working days prior to the start of work, requiring the closure of any roads or buildings.
4.3. The contractor shall have separate Key Personnel in the positions of Program Manager, Superintendent, and a Quality Control Manager. These individuals shall attend the Government Program Manager’s (GPM) weekly meetings. At the meeting the contractor shall inform the Government of any problems/issues; submit updated schedule, and records which reflect the priorities as established by the GPM. The contractor shall submit meeting minutes to the COR two days after the meeting. The following Key Personnel shall have the minimum qualifications as follows:
a) Program Manager shall:
1) Be an employee of the prime contractor, speak English, minimum of 7 years’ experience in the construction, including minimum of 5 years’ experience in paving management.
2) Graduate of an accredited university or college with an engineering degree in the civil construction field.
3) Supervisory experience in the construction field related to paving.
b) Superintendent shall:
1) Be an employee of the prime contractor, speak English, and be directly accountable to the
PM.
2) Minimum of 7 years journeyman level experience in the paving field and minimum of 3 years’ experience in supervisory position related to paving.
c) Quality Control Manager shall:
1) Be an employee of the prime contractor, speak English, and be directly accountable to the
QCM staff.
2) Minimum of 10 years combined specialized experience a Quality Control Manager in industrial, institutional, and DOD activities.
4.4. Superintendent shall be on the project site at all times when the work is in progress or with the approval of the COR, shall assign a Site Foreman.
4.5. The contractor shall assign a Site Foremen (Foreman). The Foreman is responsible for the work, employees, equipment, documents, and that inspections are completed daily. The Foreman shall receive instruction from the COR and shall have full authority to execute the order or direction from the COR without delay and to promptly supply such materials, equipment, tools, machinery, labor and incidentals as may be required to complete the work in the absence of the Superintendent.
4.6. The contractor shall complete a weekly progress report for each project and submit the progress report to the COR by the end of the work week or no later than the first day of a new work week.
4.7. The contractor shall notify and coordinate utilities outage or relocation with the COR.
4.8. The contractor shall be required to perform multiply delivery orders at the same time.
4.9. The contractor shall have personnel on-site who have and maintain current Red Cross certification for Standard First Aid, and Adult cardiopulmonary resuscitation (CPR) including recognition and response for Heat Related Disorders. This certification shall be in their possession and available for inspection at all times.
4.10. The contractor shall maintain a quality control team that holds the American Concrete Institute (ACI) Concrete Field testing certification, storm water permit certification, Level 1 soil certification, OSHA Safety inspection certification, and USACE QC Training course. The contractor may use subcontractors/third party vendors to assist, but the prime contractor is ultimately responsible for QC and is the Government's point of contact for all matters.
4.11. No space for office, storage, personnel shall be provided on APG.
4.12. The contractor shall provide a person whom is identified as the “Responsible Person” a minimum of five
(5) days prior to any work beginning. The contractor shall submit the qualifications of this person. He is required to be certified as the “Responsible Person.” The Certification is to be kept current. Replacement of this person will require approval by the COR. The “Responsible Person” shall have primary responsibility and authority for the implementation of the approved erosion and sediment control plans, schedules, and methods of operation during the entire construction activity.
4.13. When the contractor believes that a Differing Site Condition has occurred the contractor shall notify the
COR within 30 minutes of that occurrence. The contractor shall perform no further work until direct by the COR.
4.14. Contractor shall appoint an Environmental Compliance Designee (ECD) for all contract work periods exceeding 180 consecutive days. Contractor ECDs shall monitor implementation of all environmental regulatory requirements, report all environmental noncompliance to the work site supervisor, correct all environmental noncompliance, and verify implementation of directed actions to correct identified environmental noncompliance. Contractor shall have at least one ECD on duty at all times at each shop or work area. Contractor shall require all personnel designated as ECDs to complete the initial ECD training through the installation or Major Subordinate Command (MSC) environmental compliance point of contact within 15 days of the start of contract performance. Contractor personnel appointed as ECDs may perform other duties provided they do not prevent the performance of ECD duties. Contractors may request a waiver of this requirement through the COR and DGR, if using and/or storing very small quantities of hazardous materials.
4.15. The contractor shall provide valid certification of the individual(s) to operate the Asphalt Paver Machine.
The employee shall have the ability to speak English.
4.16. The contractor shall provide a valid certification of the individual(s) to operate the Milling Machine. The individual shall have the ability to speak English.
5. Safety:
5.1. The contractor shall be required to provide pedestrian and vehicular traffic control at all times for all work performed under this contract. Traffic control is incidental to the work on this contract. The contractor shall ensure all personnel controlling traffic is properly attired in protective safety attire and has been trained in traffic safety for public safety. All traffic plans shall be submitted for approval and shall have concurrence from the COR prior to proceeding.
5.2. The contractor shall furnish, erect and maintain warning and direction signs. No work may be begin unless an adequate number of signs of the proper category are in place and approved by the COR.
5.3. The contractor shall follow the instructions as specified in the excavation permit.
5.4. The contractor shall give 5 days’ notice and hold a preconstruction meeting with the COR. The contractor shall have all sub-contractors at the preconstruction meeting and shall provide an outline of worker safety procedure.
5.5. The contractor shall install traffic control devices.
6. Plans:
6.1. The contractor shall design Sediment and Erosion Control Plan and obtain Maryland Department of Environment (MDE) approval. The contractor shall have the capability of obtaining an MDE approval using an MDE approved expedited reviewer. The contractor is responsible for the fees required to process and to obtain the permits.
6.2. The contractor shall design Storm Water Management Plans and obtain MDE approval. The contractor shall have the capability of obtaining an MDE approval using an MDE approved expedited reviewer. The contractor is responsible for the fees required to process and to obtain the permits.
6.3. The contractor shall design Critical Area Plans and obtain State of Maryland Critical Area Commission approval. The contractor is responsible for the fees required to process and to obtain the permits.
6.4. The contractor shall be required to provide as-built drawings for all work constructed. The contractor shall show both horizontal and vertical control points. All utilities unearthed, installed relocated, or test pitted shall have an as-built location showing the depth, location and coordinated values for location. All as-built information shall be submitted to the COR on compact disk(s) and hard copies at a minimum scale of 1-iches 50-feet. All asbuilt drawings shall be certified and sealed by a qualified licensed professional.
As-built Drawings are not a line item cost item (ITEMS/SUB-ITEMS (CLINs or subCLINs)).
6.5. The contractor shall be required to provide the “Real Property Closeout Report” IMAP-PWM 003 at the completion of each project. This is not a line item cost item (ITEMS/SUB-ITEMS (CLINs or subCLINs)).
7. Equipment:
7.1. The contractor shall be required to keep all equipment in safe and operating working condition and shall have the proper equipment or rent the proper equipment to meet the specification and requirements of this contract.
7.2. The contractor shall be required to keep all certifications current and up to date for each excavation box used in trenching and shall be required to have the inspection certification on site for each box used during any excavation required to complete the specified work as stated in the delivery order.
7.3. The contractor shall be required to provide the equipment to crush demoed concrete and macadam into usable material crushed down to ¾ to 1 ½ inches in diameter. Material shall be crushed when the accumulation reaches 100 cubic yards. The contractor shall be provided a place for crushing and storage of the demoed and crushed material.
7.4. The contractor shall ensure that all equipment is in proper working condition.
7.5. The contractor shall inspect each piece of equipment and complete daily inspection sheets which shall be available to the COR.
8. Warranties:
8.1. The contractor shall warrant for one (1)-year from the time the COR has issued approval of final payment as dated and noted on the contract paper work for…
This is the start of the file's text. The full file is on GovTribe.