W52P1J-22-R-5002 -- Solicitation Attachment 0001 -- SOW Build Splash Pad.pdf
PDF 291 KB Posted
- Solicitation number
- W52P1J-22-R-5002
About this file
This Scope of Work document requests proposals for the construction of a splash pad at the Rock Island Arsenal in Rock Island, Illinois. The project involves demolishing existing volleyball courts and playground equipment, excavating for a concrete pad and underground water distribution system, installing grass and other landscaping, and constructing the splash pad features and controls. Proposals are due by 14 February 2022. Contractors must be licensed in Illinois and follow all specifications in the appendices, which reference codes like the International Building Code and the National Fire Protection Association standards. The work must be completed by 3 June 2022 and contractors will be responsible for watering new grass for two months. The project prioritizes safety, environmental protection, security protocols, and waste management requirements.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR #2022- 102 Splash Pad Project
Rock Island Arsenal Scope of Work
PR #2022-102
Build a Splash Pad in Memorial Park
23 December 2021
US Army Garrison‐Rock Island Arsenal Directorate of Public Works Engineering and Services Division
IMNE‐RIA‐PWF
1 Rock Island Arsenal Rock Island, IL 61299‐5000
PROJECT SUMMARY: The Rock Island Arsenal has a project to install a splash pad for children interaction with various water spraying features in Memorial Park at the Rock Island Arsenal. The work will include replacing the existing sand volley ball courts with grass, and excavating for a new concrete pad, and related buried water distribution piping. Including a below ground structure to contain a storm sewer and the splash pad water distribution system to the various interactive water spray playing features. The island potable water supply will be used and the work will include providing a dedicated water line from the island supply water piping buried near Rodman Avenue, and drainage piping from the new splash pad down to Sylvan Slough. A sidewalk will be provided from the parking lot to the Splash Pad. Install a dedicated power source. The work will include repairing the grass damaged during the installation, and the installation of benches for parents to watch while the children are playing. The contractor will be responsible for watering the new grass for a period of two months or as recommended by the seed supplier. The work is to be performed from 0700 to 1700 Monday thru Friday.
All Federal Holidays will be observed.
PART 1 SPECIFIC PROJECT
1.1 CONTENTS:
1.1.1 SCOPE OF WORK:
1.1.1.1 Appendix A: Project Specifications
1.1.1.2 Appendix B: Project Site Drawings
1.1.1.3 Appendix C: Splash Pad Drawings (Basis of Design)
1.1.1.4 Appendix D: Proposed Submittal Register
1.1.1.5 Appendix E: Non-Hazardous Construction and Demolition Debris
Submittal Form
1.2 PROJECT DESCRIPTION:
1.2.1 US Army Garrison – Rock Island Arsenal (RIA) is seeking a Contractor to furnish labor, equipment and material to furnish and install a splash pad as indicated in this Scope of Work and Appendix’s. Demolition work for this project includes excavation of the existing sand volley ball courts (2 courts), swing set (with sand base), and excavation for the concrete walks, slab and vault below the slab, and the new buried water and drainage piping. New site work will include providing and grading black topsoil to replace the sand volley ball courts and to slope the top soil to the new concrete surfaces. Topsoil shall be capable of growing grass. All disturbed areas shall receive an urban salt resistant hydraulic seed, fertilizing and mulching mix. Electrical power for the splash pad features/controller shall be obtained from a nearby distribution panel fed from an OH pole transformer source. The new splash pad and features shall be designed, furnished and installed in accordance with the Project Specifications in Appendix A and the Splash Pad Drawings (Basis of Design) in Appendix C.
1.3 SUBMITTALS/DELIVERABLES:
1.3.1 Design Phase:
1.3.1.1 Contractor shall submit Splash Pad Drawings, similar to those in
Appendix C, for review by the government prior to the start of construction.
1.3.1.2 The government shall provide review comments within 10 business days.
1.3.1.3 If required, the Contractor shall make necessary changes and resubmit the drawings to the government for review.
1.3.2 Construction Phase:
1.3.2.1 All construction phase submittals are indicated in the Project
Specifications – Appendix A and Project Drawings – Appendix B.
1.3.2.2 Additional submittals maybe required based upon the Splash Pad
Drawings.
1.4 BASE BID:
1.4.1 The Base Bid consists of the design work and the construction work indicated on the drawings, and as required in the specifications and this Scope of Work. The design site plan “C sheets” shall be constructed using the using the Iowa State Urban Design and Specifications Program (SUDAS) 2021 edition. These specifications can be found at the following web address; https://iowasudas.org/manuals/specifications-manual/.
https://iowasudas.org/manuals/specifications-manual/ https://iowasudas.org/manuals/specifications-manual/
PART 2 GENERAL REQUIREMENTS:
2.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
The contractor shall be required to commence work under this contract within 14 calendar days after the date the Contractor receives the notice to proceed, prosecute the work diligently, and complete the entire work ready for use not later than 3 June 2022. The date stated for completion shall include final cleanup of the premises.
2.2 EXISTING CONDITIONS:
2.2.1 Site condition information including utility locates provided by the
Government shall be field verified by the Contractor prior to construction.
2.2.2 The Government shall furnish, at no additional charge, the use of water and electricity.
2.3 SPECIAL CONDITIONS:
2.3.1 Staging Area: Coordinate with the Contracting Officer for locations around the site for parking and staging as needed.
2.3.2 Construction Schedule and Closure Periods: Contractor shall submit a schedule for approval prior to mobilization. Schedule shall include all definable features of work, including submittals, design drawings, and construction activities. Construction activities include, but are not limited to, mobilization, demolition, excavation and grading, removal of trees (including stumps) placement of reinforcement bars and concrete, removal and replacement of concrete cannon pad, removal and replacement of sidewalk and installation of the shelter,
2.3.3 Disruption of traffic and use of sidewalks shall be minimized. Any potential interferences with the rest of the Rock Island Arsenal’s (RIA) services, personnel or entities shall be coordinated with the COR so as to minimize disruption.
2.3.4 Contractor shall be responsible for accurate measurements of all existing site conditions.
2.3.5 Contractor shall provide all services, labor, materials, supervision, equipment, tools, etc. necessary to accomplish the work described in the Contract Documents.
2.3.6 Contractor shall submit all samples to COR for review and approval as required by Project Specifications. Schedule the submission of the samples to allow Government review time and still obtain approval of the submittal 14 calendar days prior to the date the construction schedule is showing the installation of the submitted product.
2.3.7 Access and Working Hours:
2.3.7.1 Work hours at Rock Island Arsenal are Monday through Friday between 0600 and 1700 hours, excluding Federal holidays. The contractor’s schedule may deviate from these hours when approved by the COR.
2.3.7.2 The Federal Holidays are: New Year's Day, January 1; Martin Luther King Day, 3rd Monday in January; President's Day, 3rd Monday in February; Memorial Day, last Monday in May; Juneteenth National Independence Day, June 19: Independence Day, July 4; Labor Day, 1st Monday in September; Columbus Day, 2nd Monday in October;
Veteran's Day, November 11; Thanksgiving Day, 4th Thursday in November; Christmas Day, December 25.
2.3.7.3 If a holiday falls on Saturday, the preceding Friday is a holiday. If a holiday falls on Sunday, the following Monday is a holiday.
2.3.8 Utilities: Contractor shall notify the COR 30 days in advance for any planned utility outages. Any valves on the active water distribution system shall be opened and closed only by the Government or their designated representatives. Contractor shall coordinate required valve turns through the COR.
2.3.9 Miscellaneous: Fire service outages shall be performed on the weekend.
Should the outage require a fire watch, Contractor shall provide the necessary manpower during the outage.
2.4 LICENSE REQUIREMENTS:
2.4.1 Contractors and sub-contractors shall be licensed in Illinois according to the work they are performing. If applicable to a trade or profession, workers shall be licensed as required by local municipality or by the State of Illinois.
PART 3 SECURITY
3.1 OPERATIONS SECURITY (OPSEC) REVIEW:
3.1.1 AT Level I training. All contractor employees, to include sub-contractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and sub-contractor employee, to the COR or to the Contracting Officer, if a COR is not assigned, within 5 Calendar days after completion of training by all employees and sub-contractor personnel.
3.1.2 Access and general protection/security policy and procedures.
Contractor and all associated sub-contractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
3.1.3 For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
3.1.4 iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 5 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
3.1.5 For contracts that require OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC
Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
3.1.6 Threat Awareness Reporting Program. For all contractors with security clearances. Per AR 381-12 Threat Awareness and Reporting Program (TARP), contractor employees must receive annual TARP training by a CI agent or other trainer as specified in 2-4b of AR 381-12.
3.2 RIA specific provision/clause language:
3.2.1 A non-disclosure agreement will be signed by the project prime before report/start date of contract.
3.2.2 All Training will be face to face, provided by a level II certified ATO and
OPSEC officer, conducted on RIA. Any conflicts with training locations/performance will be directed by the project COR. Training is provided on Thursdays, 0800, building 90, room 25.
3.2.3 Contractors, sub-contractors will be escorted by the COR in areas where they may be exposed to classified and/or sensitive materials. All contractor employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials. The Vendor will coordinate with the Contracting Officer, or their designated COR, and/or the facility security office for access when required.
3.2.4 All personnel requesting access to Rock Island Arsenal will only enter through a manned and operational Access Control Point and present a United States National or State issued identification that is capable of being scanned for valid entry. All contractor and contractor employees' vehicles, equipment, and packages are subject to inspection or examination (search) at entry/exit of the Rock Island Arsenal. Only authorized individuals that pass a screening and vetting process will be permitted access. All contractor and subcontractor personnel will be required to submit the required identification credentials and must receive a favorable background check as conducted through the National Crime Information Center (NCIC) Interstate ID Index (III) to gain access and work on the installation.
3.2.5 Building Stand-Off: All occupied buildings on Rock Island Arsenal require a 33 feet stand-off by all vehicles and equipment. At no time will unoccupied vehicles, equipment or tools/tool boxes be left unattended within 33 feet of installation buildings.
3.2.6 Force Protection Condition (FPCON) impact on work levels: During FPCONs Charlie and Delta, contract services will be diminished and/or discontinued. Services will resume when the FPCON level is reduced to level Bravo or lower.
PART 4 SAFETY REQUIREMENTS
4.1 Contractor shall comply with Engineering Manual EM-385-1-1 “Safety and Health Requirements Manual”.
4.2 Contractor shall designate a Site Safety and Health Officer (SSHO) in accordance with EM 385-1-1, Section 01.A.17. SSHO shall also be responsible to coordinate contract employees in the event of an emergency.
4.3 The following safety submittals are required prior to performing work:
4.3.1 Accident Prevention Plan (APP) (EM 385-1-1, Section 01.A.12)
4.3.2 Activity Hazard Analysis (AHA) (EM 385-1-1, Section 01.A.15)
4.3.3 Emergency Plan (EM 385-1-1, Section 01.E)
4.3.4 Supplemental plans in accordance with EM 385-1-1 shall be required as dictated by the types of work being performed (e.g. Hazardous Energy Control Program, Hot Work, Hazardous Material Abatement).
4.4 The Contractor shall adhere to the most current requirements of NFPA 241, EM 385-1-1 and local Fire Department requirements as supplemented below.
If a conflict between requirements occurs the most stringent shall apply.
4.5 Fires, regardless of size, will be reported to the fire department.
4.6 Contractor storage areas in RIA buildings shall be inspected and approved by the RIA Fire Department prior to use.
4.7 Extinguishers for hot work shall be a minimum of 10 lb. ABC Type (UL
Rating 4A:80B:C). Building extinguishers shall not be used to meet this requirement.
4.8 Contractors shall provide flameproof tarps or shields to protect combustible material during hot work.
4.9 The Contractor shall make requests in writing to the COR no less than two weeks in advance for approval to connect to a fire hydrant. The Contractor is responsible for installing the water meter/back flow preventer and providing their own hose, hose connections, and hydrant wrenches for opening/closing fire hydrants. The Contractor shall not use pipe wrenches, channel locks, etc.
for opening/closing of fire hydrants.
4.10 Contractor shall comply with all emergency communication instructions provided through official channels to include the outdoor speaker system, building notification systems, direction by emergency service personnel, or the COR.
4.11 Upon award, the Government will provide further information regarding building points of contact, areas of refuge, and access restrictions.
4.12 Contractor vehicles and/or equipment shall not block fire department access, hose connections, alarm panels, access roads, fire hydrants, building safety features, etc. without prior approval. The Contractor shall make requests in writing to the COR no less than three weeks in advance of blocking items listed above. Request shall include proposed length of closure.
PART 5 ENVIRONMENTAL PROTECTION:
5.1 The Contractor shall follow all environmental requirements in accordance with this SOW, the attached specifications (Appendix A), and the attached plans (Appendix B).
5.2 Compliance with Environmental Laws and Regulations. Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement, or Status-of-Forces Agreement. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the KO/COR. The Environmental Coordinator's Office will review questions on environmental compliance, and provide guidance as needed. In case of an environmental event or disaster, the Contractor shall comply with the Government's emergency services plan. All environmental protection matters shall be coordinated with the KO/COR.
5.3 Compliance with Green Procurement Requirements. Contractor shall follow Federal EPA Comprehensive Procurement guidelines (www.epa.gov/cpg) and Army Contracting Command Quick Guide (https://acc.aep.army.mil/accapps/ACCMAP/Documents/Quick-Guide-for- Sustainable-Procurement.docx) for acquisition of building materials and products and select materials that have a long life cycle; the least toxic materials; recyclable materials; materials that are resource-efficient; materials with the maximum recycled content; materials harvested on a sustained yield basis; and products causing the least pollution during their manufacture, use, and reuse.
5.4 Compliance with License and Certification Requirements. Contractor shall obtain all licenses and certifications required by Federal, State, and Local environmental laws and regulations necessary to adhere to the specifications of this contract. The Contractor shall submit all plans, notifications, reports, submittal documents, and fees required by Federal, State, and Local environmental laws and regulations to the appropriate Federal, State, and Local authority and/or agency as necessary to adhere to the specification of this contract. All required licenses and certifications required by Federal, State, and Local environmental laws and/or regulations shall be considered a contract deliverable upon award.
5.5 Notification of Federal and State Regulators. Contractor shall immediately notify the Designated Government Representative (DGR) and KO/COR of the arrival on site of any Federal, State, and/or DoD environmental regulator or enforcement agent and/or the receipt of any correspondence from a Federal or State environmental agency.
5.6 Inspections of Work Sites. Any of the facilities operated by the Contractor may be inspected by the KO/COR, the RIA Environmental Coordinator, or other Regulatory Officials on a non-notice basis. Contractor shall submit to potential Federal, State, Army and installation work site environmental regulatory inspections and/or investigations into noncompliance, and fully cooperate with such inspections/investigations by providing the appropriate records and documentation. Environmental regulatory agencies are authorized by law to inspect any work site for environmental compliance with regulatory requirements. If an inspection is conducted, it will not stop or disrupt ongoing contract activities. The inspection will only require the work site environmental officer, or supervisor/manager to answer questions and/or escort the inspector to specific work site areas with the potential to affect environmental quality.
5.7 Reporting Noncompliance and Citations. Citations/Fines for non-compliance with environmental standards on Government facilities operated by the Contractor are a matter for resolution through the Environmental Coordinator's Office and between the RIA Garrison Commander and the issuing office of Environmental Protection Agency (EPA) or State of Illinois Regulatory Authorities. If the citations/fines are issued due to faulty operation or maintenance practices, the KO/COR shall deduct the fine from any monies due the Contractor.
5.8 Verification of National Environmental Policy Act Documents. NEPA review and analysis is done in accordance with 32 CFR Part 651 and addresses actions to be taken by contractor prior to and during commencement of contract actions. The NEPA process consists of evaluating the environmental effects of a federal action including its alternatives. A Record of Environmental Consideration was prepared by the Public Works Environmental Division. Per 32 CFR Part 651.29(a) (1, 2, and 3): The action has not been segmented, no exceptional circumstances exist (b) (1-14), and one or more of the Categorical Exclusions (CX’s) encompass the proposed action. Per 32 CFR Part 651, Appendix B, Section II, the following CX applies which states: (c) Construction and demolition: (1) Construction of an addition to an existing structure or new construction on a previously undisturbed site if the area to be disturbed has no more than 5.0 cumulative acres of new surface disturbance. The project is excluded from further coordination.
5.9 Assignment of Environmental Compliance Designee (ECD). Contractor shall appoint an ECD for all contract work periods exceeding 180 consecutive days.
Contractor shall appoint a primary and alternate ECD for each production, shop or work area that uses and/or stores hazardous materials and/or generates hazardous wastes. Contractor ECDs shall monitor implementation of all environmental regulatory requirements, report all environmental noncompliance to the work site supervisor, correct all environmental noncompliance, and verify implementation of directed actions to correct identified environmental noncompliance. Contractor shall have at least one ECD on duty at all times at each shop or work area. Contractor shall require all personnel designated as ECDs to complete the initial ECD training through the installation or Major Subordinate Command (MSC) environmental compliance point of contact within 15 days of the start of contract performance. Contractor personnel appointed as ECDs may perform other duties provided they do not prevent the performance of ECD duties.
Contractors may request a waiver of this requirement through the KO/COR and DGR, if using and/or storing very small quantities of hazardous materials.
5.10 Competency Training for Contractor Personnel. Contractor shall not allow personnel to perform any activities and/or tasks on the installation without proper and adequate qualifications or job competency training. In the event of any identified noncompliance, the Contractor shall, if requested, provide proof of contract personnel training or qualification (individual name, training/qualification type, training/qualification certificate, and date of training/qualification) to perform those contract activities associated with the identified noncompliance.
5.11 Generation of Waste. Contractor shall remove from the installation and dispose of all waste generated, which cannot be recycled to an approved and permitted off-post disposal facility,
5.11.1 Contractor shall submit a non-hazardous solid waste disposal plan identifying methods and locations for solid waste disposal, including clearing debris. The plan shall include schedules for disposal. The Contractor shall identify any Sub-Contractors responsible for the transportation and disposal of solid waste. Licenses or permits shall be submitted for solid waste disposal sites that are not a commercial operating facility. Evidence of the disposal facilities acceptance of the solid waste shall be attached to this plan. Submit in writing the quantities of waste removed and recycled to the DGR and/or KO/COR on a monthly basis. The submittal shall include the date of disposal/recycling, the disposal/recycling facility, the types of material disposed/recycled and the quantities of materials disposed/recycled by weight.
5.11.2 Contractor shall submit a recycling and solid waste minimization plan.
The plan shall detail the Contractor's actions to comply with and to participate in Federal, State, Regional, and local government sponsored recycling programs to reduce the volume of solid waste at the source. It is the goal to recycle and/or divert 50% of the total waste stream from this project. Prior to any work, the Contractor shall submit a preliminary Non- Hazardous Construction/Demolition Debris Disposal/Diversion/Recycling Submittal form. This form is listed as Appendix E. The form shall be annotated to depict the various non-hazardous waste streams expected during the work and the anticipated recycle and/or diversion rate.
5.11.3 Prior to final payment, the Contractor shall submit a final Non-Hazardous Construction/Demolition Debris Disposal/Diversion/Recycling Submittal form. Form shall be annotated to depict the actual quantities for the various non-hazardous waste streams generated during the work and the final recycle and/or diversion rates. Copies of all certified weigh-bills shall also be provided for each load of material that was disposed, diverted, or recycled.
5.12 Generation of Hazardous Waste. The Contractor shall follow all hazardous/special waste disposal requirements in accordance with this SOW, the attached specifications (Appendix A), and the attached plans (Appendix B). Contractor shall assign all hazardous waste management responsibilities to the appointed ECD. Contractor shall contact the DGR and/or COR to obtain technical assistance from the Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous waste storage and disposal requirements. Contractor shall properly profile all waste generated as part of this contract to determine if any waste is hazardous waste as defined by 40 CFR. Contractor shall accumulate hazardous waste prior to disposal shipment in a satellite accumulation point at or near the point of generation or in a less-than-90-day site, in accordance with Federal, State, Army, and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement or Status-of-Forces Agreement. The Contractor shall properly package the hazardous waste and complete the hazardous waste manifest, then take the manifest to DGR for approval and signature prior to removing any hazardous waste from the installation. Contractor shall contact DGR to obtain the installation’s hazardous waste EPA ID number for the hazardous waste manifest. The Contractor shall notify the DGR 24 hours prior to removing any hazardous waste from the installation. The contractor shall remove and dispose of manifested hazardous waste generated by contract activities from the installation, to an approved off-post permitted hazardous waste disposal facility. The DGR shall assist contractors with profiling their waste upon request. All disposal procedures will be IAW Federal and State EPA regulations. A copy of any paperwork, including manifests, shall be forwarded to, Environmental Coordinator’s Office, RIA.
5.13 Use of Hazardous Materials: Contractor shall assign all hazardous materials management responsibilities to the appointed ECD. Contractor shall contact the DGR or KO/COR to obtain technical assistance from Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous material storage, issue, use, and disposal requirements. Contractor shall submit to the KO/COR and/or DGR a hazardous material inventory. The hazardous material inventory will be submitted 30 days prior to commencement of work for contracts that exceed 180 consecutive days. The inventory list will contain the hazardous material type and maximum quantities of materials anticipated to be stored on-site. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. The Contractor shall maintain copies of Safety Data Sheets for all hazardous materials used and stored on-site during performance of the contract. Contractor shall not supply or deliver any hazardous materials or chemicals to an installation that are listed on EPA toxic chemical list without prior written approval from DGR and/or KO/COR.
5.14 Prevention of Storm Water Pollution. The Contractor shall perform, track, participate, implement, and comply with storm water pollution prevention minimum control measures, protocols, and best management practices (BMP) and ensure that water quality standards are not violated in accordance with all regulations and policies as applicable to the National Pollutant Discharge Elimination System (NPDES) general permit requirements. Applicable permits include the General NPDES Permit for Storm Water Discharges from Construction Site Activities (ILR10). The minimum control measures for construction sites include, but are not limited to:
5.14.1 Public Education and Outreach on Storm Water Impacts
5.14.2 Public Involvement and Participation
5.14.3 Illicit Discharge Detection and Elimination
5.14.4 Construction Site Storm Water Run-off Control
5.14.5 Post Construction Storm Water Management in New Development and
Redevelopment
5.14.6 Contractors will obtain permit coverage for construction activities disturbing over one acre of land (total acreage is cumulative across all portions of the project). Requirements include, but are not limited to:
5.14.6.1 Preparing a Notice of Intent (NOI)
5.14.6.2 Preparing and implementing a site-specific Storm Water Pollution
Prevention Plan (SWPPP) as outlined in the permit and prior to any soil disturbance.
5.14.6.3 Prior to submission of the Notice of Intent (NOI), Storm water Pollution Prevention Plan (SWPPP), Notice of Termination (NOT) and associated fees to the state of Illinois, these documents must be approved by Public Works – Environmental (PW-E) through the
KO/COR.
5.14.6.4 When the on-site SWPPP binder is compiled, a copy must also be submitted to PW-E for their records. Inspection reports should be submitted to PW-E through the KO/COR on a regular basis as required by the Permit. Contractor is responsible for all associated fees.
5.14.6.5 Installing and managing erosion and sediment control.
5.14.6.6 Make available, upon request, permit associated documentation.
5.14.6.7 Practicing spill prevention and good housekeeping.
5.14.6.8 Schedule inspections and provide corrective actions for noted deficiencies.
5.15 Protection of Work Site Resources. Contractor shall confine all activities to areas defined by the drawings and specifications. Prior to the beginning of any work, the Contractor shall identify any land resources to be preserved within the work area. Except in areas indicated on the drawings or specified to be cleared, the Contractor shall not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms. The Contractor shall provide effective protection for land and vegetative resources at all times. Prior to site clearing and grubbing, the Contractor shall coordinate harvesting of saleable timber with the DGR and/or KO/COR. Contractor shall notify the DGR and/or KO/COR if any trees are required to be disposed or removed. The Contractor is not authorized to remove or dispose of any tree greater than 6 inches in diameter unless permission has been granted in writing by the DGR or KO/COR.
5.16 Prevention of Spills: Contractor shall adopt the installation's Spill Prevention Control and Countermeasures Plan (SPCC) if transporting, processing, storing, or in any way managing hazardous waste, hazardous material, petroleum-oils-lubricants, or other restricted items. In case of a spill, the person in control of the spill site or their designated representative shall take appropriate action to protect workers and bystanders; contain the spill (if it can be done safely); secure the spill site; restrict ignition sources; and immediately contact the installation Fire and Emergency Services (Fire Department).
5.17 Protection of Sensitive Areas. Contractor shall comply with all installation designated sensitive and/or off-limit area restrictions. Sensitive areas are generally demarked indicating what activities (e.g., driving, digging, foot traffic) are prohibited. The Contractor shall also adhere to the following installation sensitive areas requirements:
5.17.1 Cultural Resources Sites: Do not excavate, remove, damage, or otherwise deface any archeological resource located on public lands.
5.17.2 Endangered Species Habitats: Do not initiate any action that may disturb, endanger, or damage to any degree the habitat of a threatened or endangered species.
5.17.3 Wetlands: Do not excavate or take any action that could fill or damage any wetland unless working under a project specific Corps of Engineers 404 permit. Wetlands include streams, riparian areas, bogs, marshes, and swamps.
5.18 Corrective Action for Noncompliance. Contractor shall when given a verbal and/or written notice of environmental noncompliance or nonconformance by the KO/COR, take immediate corrective action. Failure or refusal to comply promptly may be grounds for the Contracting Officer to invoke the appropriate contractual remedies. This may cause all or part of the work to be stopped immediately until satisfactory corrective action has been taken.
5.19 Noise: Contractor shall make the maximum use of low-noise emission products, as certified by the EPA. Blasting or use of explosives will not be permitted without written permission from the Contracting Officer, and then only during the designated times. Pile-driving operations shall be coordinated through the DGR and KO/COR.
5.20 Mercury. Mercury is prohibited, unless specified otherwise, and with the exception of mercury vapor lamps and fluorescent lamps. Dumping of mercury-containing materials and devices such as mercury vapor lamps, fluorescent lamps, and mercury switches, in rubbish containers is prohibited.
Remove without breaking, pack to prevent breakage, and transport out of the activity in an unbroken condition for disposal as directed. Immediately report to the DGR and KO/COR instances of breakage or mercury spillage. Clean mercury spill area to the satisfaction of the Contracting Officer. Cleanup of a mercury spill shall not be recycled and shall be managed as a hazardous waste for disposal.
5.21 Universal Waste / e-Waste Management. Universal waste including but not limited to some mercury containing building products such florescent lamps, mercury vapor lamps, high pressure sodium lamps, CRTs, batteries, aerosol paint containers, electrical equipment containing PCBs, and consumed electronic devices, shall be managed in accordance with applicable environmental law and installation instructions.
5.22 Pollution Prevention / Hazardous Waste Minimization. Contractor shall minimize the use of hazardous materials and the generation of hazardous waste. Consult with the Environmental Office for suggestions and to obtain a copy of the installation's pollution prevention/hazardous waste minimization plan for supporting waste minimization.
PART 6 AREAS ASSIGNED
6.1 The Contractor shall be required to maintain areas assigned in a clean and orderly manner. The Contractor will not modify areas assigned without the written consent of the KO/COR. Approved modifications are at the Contractor's expense. The Contractor will, at their expense, restore areas assigned damaged during their performance of the contract to their original condition upon completion of the contract.
6.2 The Contractor shall follow the publications referenced in accordance with this SOW, the attached specifications (Appendix A), and the attached plans (Appendix B).
6.3 In the event of conflict between References and/or Applicable Military Criteria, the most stringent criteria will apply, unless otherwise specifically noted in the SOW.
6.4 The Contractor shall be required to submit a DD Form 1354. To ensure the proper use of this form, the Contractor shall meet with the Government representatives prior to any demolition or construction to receive training and sample documents. A draft version of the form shall be prepared and maintained by the Contractor throughout construction and shall be made available to the Government upon request. Upon project completion, the draft DD Form 1354 shall be finalized by the Contractor to reflect all construction, repair, relocation, and demolition information. The final version shall then be submitted to the Government as a part of the final submittal package.
PART 7 DEFINITIONS: N/A
PART 8 APPLICABLE PUBLICATIONS:
8.1 The Contractor shall abide by all applicable regulations, publications, manuals, and local policies and procedures. The applicable codes and standards shall include, but not be limited to, those indicated in the following sections. In the event of conflict between References and/or Applicable Military Criteria, the most stringent criteria will apply, unless otherwise specifically noted in the scope of work.
8.1.1 Architectural Barriers Act (ABA) Standards
8.1.2 International Building Code (IBC) (2018)
8.1.3 Engineering Manual EM-385-1-1 “Safety and Health Requirements
Manual”
8.1.4 UNIFIED FACILITIES CRITERIA (UFC)
8.1.4.1 UFC 1-200-01 (February 01, 2018): DoD Building Code
8.1.4.2 UFC 1-300-02: Unified Facilities Guide Specifications (UFGS)
Format Standard with Standard 2
8.1.4.3 UFC 3-301-01: Structural Engineering with Change 4
8.1.4.4 UFC 3-600-01: Fire Protection Engineering for Facilities with Change
8.1.4.5 UFC 4-010-01: DoD Minimum Antiterrorism Standards for Buildings
8.1.4.6 UFC 3-501-01: Electrical Engineering
8.1.5 National Fire Protection Association publications (https://www.nfpa.org/) and associated UL publications:
8.1.5.1 NFPA 101: Life Safety Code.
8.1.5.2 IEEE 142, Recommended Practice for Grounding of Industrial and
Commercial Power Systems.
8.1.5.3 NFPA 70, National Electrical Code
8.1.5.4 NFPA 70B, Recommended Practice for Electrical Equipment
Maintenance
8.1.5.5 NFPA 77, Recommended Practice on Static Electricity
8.1.5.6 NFPA 780, Standard for the Installation of Lightning Protection
Systems.
8.1.5.7 UL96, Lightning Protection Components.
8.1.5.8 UL 467, Grounding and Bonding Equipment.
8.1.6 Army Regulations
8.1.6.1 AR 420-1; ARMY FACILITIES MANAGEMENT
8.1.6.2 ARMY GENERAL ORDER 2017-01
- END OF SCOPE OF WORK -