Attachment 0001 - Statement of Work - Revised 23 April 2026.pdf
PDF 86 KB Posted
- Solicitation number
- W519TC26QA127
About this file
This is a Statement of Work for the revitalization of an Uninterruptable Power Supply (UPS) system supporting First Army Headquarters at Building 68, Rock Island Arsenal, Illinois.
First Army requires replacement of internal UPS componentry using original equipment manufacturer parts from Schneider Electric, specifically the modular revitalization kit SKU WMPR505-MP-505. The existing UPS system is a 500 kW Symmetra unit operating at 480 volts with 108 installed batteries. Components to be replaced include intelligence modules, static switch and H.E. power modules, power view display, network management card, switchgear board, battery monitor board, and system PSU. Associated work includes component delivery, on-site certified service professionals for removal and installation, system configuration to meet supply specifications, disposal of old componentry, and a one-year service agreement. The total period of performance is 12 months, with revitalization and installation timing to be coordinated with the government upon award to minimize operational impact, and the service agreement commencing immediately upon government acceptance of installed componentry. The contractor must deliver a kick-off meeting coordination within 14 days of award, provide hardware delivery prior to installation, complete installation and configuration per approved schedule, submit testing and acceptance documentation within three days of installation completion, provide disposal certificates within 14 days, and activate service agreement documentation upon final acceptance. The one-year service agreement must include next business day on-site response for break-fix scenarios, yearly preventive maintenance visits, and discounted parts and labor rates.
All contractor personnel must obtain Real ID clearance, pass background checks, and complete AT/FP Level I training within 30 days of contract start. The contractor is responsible for maintaining strict OSHA compliance, implementing lockout/tagout procedures for the 480-volt system, safe removal and compliant disposal or recycling of old components, and daily site cleanup. Work hours are preferred at 0730-1600 but can be accommodated outside this window; if total power cutoff is required, off-hours work is preferred. If a temporary UPS is needed during revitalization to maintain power to critical loads, the cost must be included in the firm-fixed price. Work is restricted on standard federal holidays.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUBJECT: Statement of Work for Revitalization of the Uninterruptable Power Supply for First Army Headquarters
1. General
First Army is seeking a revitalization of the Uninterruptable Power Supply (UPS) system that supports the Headquarters facility in building 68 on Rock Island Arsenal. The UPS cabinet and batteries are to remain in place. Therefore, we specifically require replacement of componentry with original equipment manufacturer parts from Schneider Electric.
Schneider Electric Modular Revitalization is performed through the purchase of SKU
WMPR505-MP-505.
2. Scope of Work
a. Associated components for replacement are as follows: intelligence modules, static switch+ H.E. power modules, power view display, network management card, switchgear board, battery monitor board, system PSU.
b. Associated work for revitalization of the UPS is as follows: delivery of all components, on-site certified service professionals to remove old componentry and install new componentry, configuration of system ensuring it meets required supply specifications, disposal of old componentry, and one year service agreement.
3. Period of Performance (PoP)
The Period of Performance for this contract includes the initial equipment revitalization, installation, and a one-year service agreement.
Phase Expected Timeframe
Total Period of Performance
12 Months
Revitalization & Installation
To be coordinated with the Government upon contract award to minimize operational impact.
Service Agreement One (1) year commencing immediately upon Government acceptance of the installed componentry.
4. Existing Equipment Details
• UPS Model and Serial Number:
• UPS: Serial Number QD1612220822
• Symmetra Display Screen: Model Number ON-95865SYPX, Serial Number
QD1611130084
• Symmetra PX 250 kW Circuit Breaker: SYIOF500KMBR
• Symmetra 500KW: WSYSW500KD
• Voltage Configuration: 480 Volts
• Other Information:
• One unifying number sticker on all equipment: P1F F.A.T.
• The system has 108 batteries installed. Model: SYBTU2-PLP
• 10 Modules total
• Predictive maintenance on Modules shows AVG 21% or 26 months left
• All batteries were replaced 7/20/2023
• UPS Module Redundancy N+6
• UPS Load 32kVA 17%
5. Place of Performance, Access, and Work Hours
• Location: Building 68, Rock Island Arsenal, IL 61299.
• Access: Entering Rock Island Arsenal requires personnel to have a Real ID. For access to building 68, contractors need to be able to pass a background check. First Army will escort all contractor personnel working inside of building 68.
• Work Hours: Preferred work hours are 0730-1600. However, hours outside of this window can be accommodated. If all power has to be cut to the building, work outside of standard hours is preferred to mitigate operational conflicts.
• Restricted Periods: Work will be restricted on standard federal holidays.
6. Continuity of Operations
The UPS provides backup power to mission-critical loads in the event of a power outage.
The facility must remain operational during the revitalization. There is a bypass switch on the UPS. If it is determined that a temporary UPS is needed to maintain power to critical loads during the work, the cost of that temporary equipment must be included in the offeror's firm-fixed price.
7. Deliverables & Schedule
The contractor shall provide the following deliverables to the Contracting Officer's Representative (COR) or designated First Army Point of Contact.
Deliverable Description Timeline / Due Date
Kick-off Meeting Coordination meeting to finalize the installation schedule, background checks, and building power bypass requirements.
Within 14 days of contract award.
Hardware Delivery Delivery of all Schneider Electric OEM componentry to Building 68, Rock Island Arsenal.
Prior to the scheduled installation date.
Installation & Configuration
Removal of old componentry and installation/configuration of the new WMPR505-MP- 505 modular revitalization kit.
In accordance with the approved schedule.
Testing & Acceptance Report
Documented proof of successful load testing, system configuration, and verification of backup power functionality.
Within 3 days of installation completion.
Disposal Documentation
Certificate of recycling/destruction for the removed electrical components.
Within 14 days of installation completion.
Service Agreement Documentation activating the one-year service plan (Next Business Day response, yearly PM, discounted rates).
Upon final acceptance of the installation.
8. Service Agreement Requirements
The one-year service agreement shall include:
• A Next Business Day on-site response for break-fix scenarios.
• A yearly Preventive Maintenance (PM) visit.
• Discounted parts and T&M rates for service visits for the initial year following installation.
9. Security & OPSEC Requirements
Because this work takes place on a military installation and inside a Headquarters facility, the following standard security requirements apply.
Security Requirement
Description
Base Access & Background Checks
All contractor personnel must possess a Real ID and pass a background check to access Rock Island Arsenal and Building 68.
Escort Requirements
First Army personnel will escort all contractor personnel while working inside Building 68. Contractors must remain with their escort at all times.
AT/FP Level I Training
All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete Antiterrorism (AT) Level I awareness training within 30 calendar days after contract start date.
iWATCH Army Training
The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local designed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR.
10. Safety & Environmental Requirements
Given the high-voltage nature of the UPS system and the disposal of electronic components, strict safety protocols are required.
Safety & Environmental Category
Requirement Details
OSHA Compliance All work shall be performed in strict accordance with Occupational Safety and Health Administration (OSHA) standards.
Lockout/Tagout
(LOTO)
The contractor must implement strict LOTO procedures when working with the 480V system to ensure the safety of installation personnel and building occupants.
Hazardous Materials & Disposal
The contractor is responsible for the safe removal, transport, and environmentally compliant disposal or recycling of all old UPS componentry.
Site Cleanup The contractor shall leave the work area in a clean and safe condition daily.
All packing materials and debris must be removed from Building 68 upon project completion.