B.08 Attachment 0002 - Pricing Matrix.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
RANGE 27 - ROAD RECONSTRUCTION AND WATER MITIGATION CHANNELS TO PREVENT RANGE EROSION ISO OPM-SANG, KSA
Solicitation number
W519TC-25-R-A004
Issued by

About this file

The document is a Pricing Matrix for the Range 27 Project (Solicitation W519TC-25-R-A004) involving road reconstruction and water mitigation channels for the Ministry of National Guard (MNG) Khashm Al AAn Airfield in Saudi Arabia. The pricing breakdown includes five Contract Line Item Numbers (CLINs) covering mobilization/equipment, road remediation, transformer protection, deliverables, and 15% VAT, with detailed cost breakdown categories such as site grading, storm water mitigation, road washout remediation, drainage ditch repair, and transformer protection installation.

Key project details include an Industry Day scheduled for 16 March 2025, with controlled access requiring prior registration by 06 March 2025 at 3 PM KSA time. The project is managed by the Department of the Army Materiel Command Contracting Command Rock Island Arsenal and involves military training infrastructure improvements, specifically preparing Range 27 for heavy vehicle and aviation firing exercises. The pricing matrix provides granular work elements including subgrade preparation, aggregate base course installation, soil stabilization, and various site-specific reconstruction and protection tasks, though the current document shows placeholder/zero values for proposed costs.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RANGE 27 PROJECT 24-KSA-23

PRICE EVALUATION SHEETContractor Fill-In
W519TC-25-R-A004
Offeror Name:
CAGE:
Unique Entity ID:
Date:
CLINCLIN TypeDescription
Period Of PerformanceUSD Proposed CostSAR Total Price
Equipment$ - 0
Facilities and Mobilization$ - 0
0001FFPMobilization/ Equipment Cost1 Job$ - 0$ - 0
Back Fill Eroded Areas/Compact/Soil Stabilization$ - 0
Remediate Road$ - 0
Remove Silt Buildup/ Regrade Existing Ditches$ - 0
0002FFPRoad Remediation1 Job$ - 0$ - 0
Precast Transformer Protection/ Delivery to Site$ - 0
Installation/ Footer Installation$ - 0
0003FFPTransformer Protection1 Job$ - 0$ - 0
0004FFPDeliverables1 Job$ - 0
0005FFP15% VAT1 Lot$ - 0$ - 0
Total Price by Ordering Period$ - 0$ - 0
Total Evaluated Price

$ - 0

Range 27 COST BREAKDOWN

CLINItem NumberCategoryWork ElementUnitEstimated Cost
00012.1.1Mobalization/ EquipmentSite Grading and Road Reconstruction Plan
00012.1.2Mobalization/ EquipmentStorm Water Mitigation Plan
00012.1.3Mobalization/ EquipmentTransformer Protection Plan
00012.1.4Mobalization/ EquipmentQuality Control Plan (QCP)
00012.1.5Mobalization/ EquipmentCommunication Management Plan
00012.1.6Mobalization/ EquipmentSubmittal Plans
00012.1.7Mobalization/ EquipmentInspection Plans
00012.1.8Mobalization/ EquipmentMobilization
00022.2.1Road reconstructionMajor Road Washout Remediationm
00022.2.2Road reconstructionMinor Road Washout Remediationm
00022.2.3Road reconstructionDrainage Ditch Cut (Road Crossing)m
00022.2.4Road reconstructionDrainage Ditch Repairm
00022.2.5Road reconstructionSubgrade Preparation and Compactionm²
00022.2.5Road reconstructionMinor Road Washout Remediationm
00022.2.6Road reconstructionAggregate Base Course Installationm³
00022.2.6Road reconstructionDrainage Ditch Cut in Roadm
00022.2.7Road reconstructionDrainage Ditch Repairm
00022.2.7Road reconstructionSurface Course Finishingm²
00032.3.1Transformer ProtectionSubgrade Excavation and Shapingm
00032.4.1Transformer ProtectionTransformer Protection - DesignLS
00032.4.2Transformer ProtectionSoil Mound Repair and Damp ProofingEach
00032.4.2Transformer ProtectionTransformer Protection - Precast ManufacturingLS
00032.4.3Transformer ProtectionTransformer Protection - DeliveryLS
00042.4.4DeliverablesTransformer Protection - InstallationLS
00042.6.1DeliverablesMiscellaneous Demobilization and Final Site RepairLS
00042.6.2DeliverablesAccess/Security ComplianceLS
00022.6.3Road ReconstructionVegetation and Debris RemovalLS
00022.7.1Road ReconstructionSoil Stabilization and Compactionm²
00043.1DeliverablesAs-Built DrawingsLS
00043.2DeliverablesWarranties and DocumentationLS
SCOPE OF WORK TOTAL BEFORE 15% VAT IN SAR$0.0000
SCOPE OF WORK TOTAL BEFORE 15% VAT IN USD$0.0000