This is a Questions and Answers document for federal contract solicitation W50S9B-26-Q-0004 addressing an electrical lighting upgrade project.
The project involves replacement of lighting fixtures with new LED units and installation of two new 20-ampere circuits. The contractor must obtain electrical permits through Henrico County requirements, with the County providing inspections; the Government owner must be notified and present during all County inspections. Blank panel space is confirmed available for the new circuits, eliminating the need for panel modifications. Work hours are 0700-1600 Monday through Friday, with flexibility available for times outside these hours if required. Existing circuit homeruns for replacement lighting will be reused; if the contractor discovers hazardous conditions or deficient wiring, work must stop for owner notification and resolution via Change Order at no cost to the Government. Replacement LED fixtures must be commercially available products meeting or exceeding minimum specifications in Section 3.1 and Attachment 5.4, with cut sheets demonstrating equal attributes; the Federal Energy Work group will review all proposed fixtures prior to contract award. The new LED fixtures do not require integral emergency battery drivers as existing circuitry will facilitate emergency lighting functionality. Closeout documentation includes panel schedule updates, product submittals, cut sheets, warranty information, and disposal documentation with no additional documents required. Payment terms are Net 14 with invoices submitted through Wide Area Workflow. Contingent bids for Virginia licensure are acceptable provided compliance with state and federal regulations is achieved. The location is not on a military base, so no base access passes or on-base lodging are available. Only one site visit was scheduled; no additional site visits will be provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers W50S9B26Q0004.pdf | ||
| Site Visit Sign in Sheet.pdf | ||
| Questions and Answers W50S9B26Q0004.pdf | ||
| Att 4 SOW Replace Lights REV02 29 Jun 26.docx | DOCX document | |
| Att 2 DBA WD VA20260155.pdf | ||
| Att 5.3 Electrical Scope.pdf | ||
| Att 4 SOW Replace Lights REV01 18MAY26.docx | DOCX document | |
| Att 5.1 Lighting Scope.pdf | ||
| Att 3 Past Performance Questionnaire Package.docx | DOCX document | |
| Solicitation_W50S9B26Q0004.docx | DOCX document | |
| Att 5.4 – Electrical Specifications.docx | DOCX document | |
| Att 5.2 Emergency Lighting Layout.pdf | ||
| Att 1 Provisions and Clauses.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers W50S9B-26-Q-0004
1. Is the contractor required to obtain an electrical permit and inspection from the local Authority Having Jurisdiction, or will all inspections and final acceptance be performed by the Government?
ANSWER: Yes. Vendor will obtain a permit through typical Henrico County requirements. Henrico County will provide inspections – note that - Owner must be notified prior to conducting County Inspections on site as we must be present during this activity.
2. For the two new 20A circuits, should the contractor assume adequate breaker spaces are available in the existing panel, or should pricing include panel modifications if required?
ANSWER: Yes - blank panel space is available. New or modified circuits shall be labeled prior to close out per notes in Section 2.1, paragraph 1 of the SOW.
3. Will the Government provide uninterrupted access to all work areas during normal work hours (0800–1530), or should the contractor anticipate phased access or scheduling restrictions?
ANSWER: Yes. Vendor may submit work schedule between the hours of 0700-1600 (M-F). We will work with you on times proposed outside of these hours if required.
4. Are existing circuit homeruns for the replacement lighting intended to be reused, or should the contractor include replacement of branch circuit wiring if deficiencies are discovered?
ANSWER: Yes. We expect to maintain existing circuits for all lights. Should Vendor discover a hazardous condition, deficient wiring or other limitation, Vendor shall stop work to notify Owner. We will work with you to resolve the condition via a Change Order and this scope is not required to be priced in your quote.
5. For the new LED fixtures, is it acceptable to provide commercially available fixtures that meet or exceed the minimum specifications listed in Attachment 5.4, or is the Government expecting fixtures from a preferred manufacturer?
ANSWER: Yes. We can accept this only if selection cut sheets clearly show that all attributes are equal to our performance specs noted in Section 3.1 & Attachment
5.4. Our Federal Energy Work group will review all proposed fixtures to confirm that your products are comparable to the requirements and this must occur prior to issuing a Contract Award.
6. Aside from updating the panel schedule and providing product submittals, cut sheets, warranty information, and disposal documentation, are there any additional closeout documents required for project completion?
ANSWER: No.
7. I'm interested in bidding on this project as a subcontractor. Do you have a list of general contractors I can reach out to, or if not, do you know who I could contact regarding this project?
ANSWER: We have a sign-in sheet that will be posted on SAM.gov.
8. Unfortunately, we were unable to attend the scheduled site visit on June 25. Would it be possible to arrange an additional site visit on Wednesday July1?
ANSWER: We are not able to provide another site visit. If you have any other questions, please let us know.
9. Will the construction work areas be available to the contractor 24 hours a day, 7 days a week, for a minimum of four (4) consecutive weeks? If so, is there any penalty or restriction if the work is completed ahead of schedule?
ANSWER: No. The hours are listed in the Statement of Work. If work is completed ahead of schedule there is no penalty or restriction.
10. Are on base guest lodging accommodations available for contractors? If so, what are the applicable rates, availability, and reservation procedures?
ANSWER: No, there is no on base lodging available to contractors.
11. What is the process and eligibility criteria for obtaining base access passes for contractors and their employees performing work under this contract?
ANSWER: This location is not on base.
12. We are a Louisiana based, master licensed electrical contractor owned and operated by a former U.S. Air Force service member. We are currently obtaining Virginia licensure through the Commonwealth’s Universal License Recognition program. Based on our discussions with the requirements, including holding a master electrician license for more than three years. May we submit a bid that is contingent upon obtaining Virginia licensure prior to contract award or before commencement of work?
ANSWER: Yes but you will have to be in compliance with state and federal regulations.
13. Will funding be fully available upon project completion to ensure timely payment of approved invoices? Additionally, what is the anticipated payment timeline after invoice submission and acceptance of the completed work?
ANSWER: Funds will have to be available to award this requirement. Payment terms are Net 14 and invoices are submitted through Wide Area Workflow.
14. Could you please confirm whether the replacement LED fixtures are required to include integral emergency battery drivers, or whether the contractor should replace the fixtures while maintaining the existing emergency lighting circuitry and functionality where applicable?
ANSWER: We do NOT need to add the integral emergency battery driver to our LEDs.
Our new LED’s will function as Emergency Lights without any upgrades/adds. This is because our existing circuit will facilitate this condition and it will be compatible with the new LEDs w/o making changes to the product or circuit.