About this file

This Statement of Work (SOW) details an emergency culvert repair project for the 118th Air National Guard at Berry Field in Nashville, Tennessee. The project involves replacing two damaged 12-inch ductile iron culverts leading to buildings 808 and 809, which have sustained significant structural damage from storm events and age-related deterioration. The primary objectives include restoring full storm water flow capacity, ensuring roadway structural integrity, preventing future erosion, and complying with local drainage and environmental regulations.

The 30-day project scope requires the contractor to provide all labor, equipment, materials, and supervision for comprehensive culvert replacement. Key tasks include site preparation, demolition and removal of damaged pipe sections, installation of new reinforced concrete pipe (RCP) culvert sections with concrete headwalls, backfilling with flowable fill and crushed stone, and implementing erosion control measures. The contractor must adhere to UFC 1-200-01 and Tennessee Department of Transportation specifications, submit various pre-construction, during-construction, and post-construction deliverables, and undergo government inspections, including a final video inspection of the completed culvert.

View the file

Other files for this federal contract opportunity

Other files attached to BKTZ212006 - B735 & Track Site Lighting, newest first.
File Type Posted
Bid Opening Roster.pdf PDF
W50S9725BA003_Abstract of Bids.pdf PDF
25BA003 Site Lighting and Culvert QA 7-10.pdf PDF
25BA003 Site Lighting and Culvert QA 1-6.pdf PDF
25BA003 SITE VISIT SLIDES 20250820.pptx PPTX presentation
Preproposal minutes W50S97B0003.pdf PDF
Site Visit Roster.pdf PDF
Attachment 4-Culvert Repair Drawings.pdf PDF
Solicitation Amendment W50S9725BA0030001 SF 30.pdf PDF
Solicitation - W50S9725BA003.pdf PDF
Attachment 1- SOW BKTZ212006 Site Lighting.pdf PDF
Attachment 2-Design BKTZ212006 Site Lighting.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

STORM WATER DRAINAGE CULVERT REPAIR

Project: Emergency Culvert Repair B808/B809

Location: 118th Air National Guard, Berry Field, Nashville TN

Date: 31 July 2025

1. PROJECT OVERVIEW

1.1 Background

The two existing 12-inch ductile iron culverts have sustained significant structural damage due to recent storm events and age-related deterioration. The culvert shows signs of joint separation, cracking, and poses risk to roadway integrity. Three sink holes have already formed due to undermining on the leaking culvert pipes. Period of Performance will be 30 days.

1.2 Project Objectives

- Restore full storm water flow capacity

- Ensure structural integrity of roadway crossing

- Prevent future erosion and undermining

- Comply with local drainage and environmental regulations

2. SCOPE OF WORK

2.1 Contractor provides all labor, equipment, material, and supervision to replace damaged culverts leading to buildings 808 and 809. The contractor will be fully responsible for compliance with all bases, local, state, and federal laws and regulations that apply including environmental and occupational safety. The scope of the work is shown on the drawings provided and further detailed below.

2.1 Site Preparation

- Establish work zone traffic control

- Install erosion and sediment control measures

- Locate and mark all underground utilities

- Set up temporary drainage diversions as needed

- Establish equipment staging area

2.2 Demolition and Removal

- Neatly saw-cut extents of excavation for pipe removal

- Excavate damaged culvert sections to design grades

- Remove and dispose of damaged concrete pipe segments

2.3 Culvert Installation/Repair

- Install two new 12-inch RCP culvert sections (ASTM C76, Class III minimum) with class ‘B’ bedding in location shown on drawings.

- Apply approved joint sealant at all pipe connections

- Install new concrete headwalls at inlet and outlet

- Backfill all areas under roadway with flowable fill

- Backfill areas in grass with crushed stone

- Construct a riprap apron at outfall of culvert for erosion protection

- Install filter fabric beneath riprap installations

2.4 Backfill and Restoration

- Place and compact select granular backfill around culvert in non-paved areas. Use flowable fill for all backfill in paved areas.

- Restore roadway base and surface materials to original specifications

- Grade and seed disturbed areas outside roadway

- Install permanent erosion control measures

4. DELIVERABLES

4.1 Pre-Construction

- Work Safety Plan, Schedule of Values, Construction Schedule

- Material submittals and shop drawings

4.2 During Construction

- Daily progress reports

- Material delivery receipts and certifications

- Photographic documentation of work progress

4.3 Post-construction

- Material certifications and test results

- Final inspection report

- Warranty documentation

6. QUALITY REQUIREMENTS

6.1 Standards and Codes

- UFC 1-200-01

- Tennessee Department of Transportation specifications

- USACE Safety and Health Requirements Manual, EM 385-1-1

6.2 Testing and Inspection

- Contractor will provide quality control for all work. The government will conduct random inspections of all work and notify contractors of any non-compliance. The contractor will notify the government for culvert inspection prior to backfilling operations.

- Final video inspection of completed culvert

STATEMENT OF WORK
1. PROJECT OVERVIEW
2. SCOPE OF WORK
4. DELIVERABLES
6. QUALITY REQUIREMENTS
- UFC 1-200-01