This is a Standard Form 30 (SF 30) Amendment of Solicitation/Modification of Contract, Amendment Number 0001, issued on 29 July 2026 by the Wyoming Air Force Office of Personnel Management (W789 USPFO ACTIVITY WYANG 153) for solicitation W50S8W26RA001, dated 17 July 2026. The amendment is administered by the issuing office located at 217 Dell Range Boulevard, Cheyenne, Wyoming 82009-4799, with Benjamin Taylor serving as the contracting officer contact.

The amendment modifies the contract documents and attachments table, replacing the original Scope of Work (SOW), RFP Instructions (52.212-1), and Past Performance Questionnaire with amended versions dated 29 July 2026. Specifically, the amendment adds Attach 1 - SOW (W50S8W26RA001 Ammend 1) and Attach 6 - RFP Instructions (52.212-1 Ammend 1) while deleting the original versions of these documents along with Attach 4 - Past Performance Questionnaire. The remaining attachments—Drawings, Basis for Award, and Contractor EAL Form 10—remain unchanged with their original 17 July 2026 dates. Additionally, the amendment modifies clause 52.228-1 (Bid Guarantee, Sept 1996) to establish that bid guarantees shall be the lesser of 20 percent of the bid price or $3 million, and clarifies procedures for bid guarantee submission, return to unsuccessful bidders, and default liability terms. Offerors must acknowledge receipt of this amendment prior to the bid opening deadline through completion of items 8 and 15, receipt acknowledgment on offer copies, or separate written communication referencing the solicitation and amendment numbers.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

List of Contract Documents, Exhibits, or Attachments

The attachments table has changed from:

Identifie r

Document Name

Document Description Reference Identifier

Date Line Item Page N umbers

Docum ent Type

Provide d Under Separat e Cover

0001 Attach 1 -

SOW (W50S8

W26RA001)

Attach 1 - Scope of Work 17 Jul 2026 Attach ment

No

0002 Attach 2 - Drawings (W50

S8W26RA001)

Drawings 17 Jul 2026 Attach ment

No

0003 Attach 3 - Basis for Award (W50S8

W26RA001)

Basis for Award 17 Jul 2026 Attach ment

No

0004 Attach 4 - Past Performance Questionnaire

(26RA001)

Past Performance Questionaire 17 Jul 2026 Attach ment

No

0005 Attach 5 - 153AW Form 10, Contractor

EAL

Contractor EAL Form 10 17 Jul 2026 Attach ment

No

0006 Attach 6 - RFP Instructions (52.212-1)

RFP Instructions 17 Jul 2026 Attach ment

No

To:

Identifie r

Document Name

Document Description Reference Identifier

Date Line Item Page N umbers

Docum ent Type

Provide d Under Separat e Cover

0001 Attach 1 -

SOW (W50S8

W26RA001

Ammend 1)

Scope of Work 29 Jul 2026 Attach ment

No

W50S8W26RA0010001

0002 Attach 2 - Drawings (W50

S8W26RA001)

Drawings 17 Jul 2026 Attach ment

No

0003 Attach 3 - Basis for Award (W50S8

W26RA001)

Basis for Award 17 Jul 2026 Attach ment

No

0005 Attach 5 - 153AW Form 10, Contractor

EAL

Contractor EAL Form 10 17 Jul 2026 Attach ment

No

0006 Attach 6 - RFP Instructions (52.212-1 Ammend 1)

RFP Instructions 29 Jul 2026 Attach ment

No

The following contract documents were added:

Attach 1 - SOW (W50S8W26RA001 Ammend 1) Attach 6 - RFP Instructions (52.212-1 Ammend 1)

The following contract documents were deleted:

Attach 1 - SOW (W50S8W26RA001) Attach 4 - Past Performance Questionnaire (26RA001) Attach 6 - RFP Instructions (52.212-1)

Addendum to Solicitation Provisions

Additional Information/Notes

The following clauses were modified:

52.228-1 Bid Guarantee. Sep 1996 hereby reads as follows:

hereby reads as follows:

Bid Guarantee (Sept 1996)

Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of (a) bids, may be cause for rejection of the bid.

The bidder shall furnish a bid guarantee in the form of a firm commitment, bid bond (b) e.g., supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-

To unsuccessful bidders as soon as practicable after the opening of bids; and(1)

To the successful bidder upon execution of contractual documents and bonds (including any (2) necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

The amount of the bid guarantee shall be percent of the bid price or $ , whichever is (c) 20% 3M less.

If the successful bidder, upon acceptance of its bid by the Government within the period (d) specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

In the event the contract is terminated for default, the bidder is liable for any cost of acquiring (e) the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of clause)

IDCode: J
Page: 1
Pages: 4
AmendNo: 0001
EffDate: 29 JUL 2026
ReqNo:
ProjNo: DPEZ 262200
IssCode: W50S8W
AdmCode:
IssuedBy: W7N9 USPFO ACTIVITY WYANG 153

KO FOR WYANG DO NOT DELETE, 217 DELL RANGE BLVD

CHEYENNE, WY 82009-4799

UNITED STATES

BENJAMIN TAYLOR, EMAIL: BENJAMIN.C.TAYLOR10.MIL@ARMY.MIL TELEPHONE: 307-772-5328

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W50S8W26RA001
SolDate: 17 JUL 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE CONTINUATION
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: 1. Filling in clause 52.228-1 Bid Bond amount.

2. Change to RFP Instructions.

3. Updated SOW.

4. No other changes apply.

ContNameTitle:
CoNameTitle: BENJAMIN TAYLOR
ContDate:
CODate: 29 JUL 2026