B.06 RFIs Answered (26-R-A001).pdf
PDF 274 KB Posted
- Attached to
- CES - Repair Roof B37
- Solicitation number
- W50S8W26RA001
- Issued by
-
Department of the Army National Guard
About this file
This is a government response to submitted requests for information (RFI) for a federal contract opportunity regarding roof repairs at a facility in Cheyenne, Wyoming. The solicitation number is W50S8W-26-R-A001, with an RFI due date of 28 July 2026 at 10:00 MST and quotes due by 04 August 2026 at 10:00 MST. The contract is identified as "CES - Repair Roof B37."
The RFI response addresses six key questions regarding the scope of work. Roofing metal replacement is confirmed as part of the project scope. Contractors are not required to pay for Lightning Protection System (LPS) repairs. Insulation repair is estimated at approximately 1,100 square feet of full-depth work. EPDM (ethylene propylene diene monomer) membrane removal is not required; only partial removal is necessary. Drain replacement is not included in the scope. The government clarified bid requirements by revising the qualification language to state that offerors must provide proof of successfully installing the specified roofing material on a project of equal or greater complexity within the past five years, rather than limiting it exclusively to Wyoming projects. This modification broadens the acceptable experience qualifications for potential contractors.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Title CES - Repair Roof B37 RFI Due By 28 July 2026 @ 10:00 MST Solicittion No. W50S8W-26-R-A001 Quotes Due By 04 August 2026 @ 10:00 MST
Location Cheyenne, WY Subject Govt response to submitted request for infomration (RFI). Page 1 of 1
CONTRACTING OFFICER REP (COR) CONTRACTING OFFICER (KO)
DATE: 29 July 2026 DATE: 29 July 2026
No. Topic Reference Document
Question Type Govt Response
1 Roofing Metal Scope of Work All metal on the roof is also being replaced? Yes also metal on the roof also needs to be replaced.
2 LPS Scope of Work Does the contractor pay to repair LPS system? No
3 Insullation Scope of Work How much insullation needs replaced? Bid should include an estimated 1100 sf of full depth repair.
4 EDPM Scope of Work Do you want full removal of EDPM? No 5 Drains Scope of Work Does the contractor need to replace the drains? No the drains don't need to be replaced
6 Bid Requirements Scope of Work
The Scope of Work under “Bid Requirements” states that offerors must provide “evidence of successful WYMD roof installations with the specified material” and that contractors failing to provide this evidence will not be considered for award. Will other work suffice to meet the qualification requirement?
Verbiage has been changed to state, "Offerors must provide proof of successfully installing the specified roofing material on a project of equal or greater complexity within the past five years."
Questions
| 2026-07-29T12:53:50-0600 | |
| DOOLEY.MICHAEL.JOHN.1148518412 |
| 2026-07-29T13:14:13-0600 | |
| TAYLOR.BENJAMIN.COLTON.1149462542 |
File details come from the government source that posted it. Updated .